Email from S. Freeman to D. Failla, FW: Meeting with Westinghouse/Pci to Discuss Site Activities
ML13218B252
Person / Time
Site: Watts Bar Tennessee Valley Authority icon.png
Issue date: 01/14/2012
From: Freeman M
NRC/RGN-II
To: Failla D
NRC/RGN-II
References
FOIA/PA-2013-0139
Download: ML13218B252 (2)


Text

Nazario, Tomy From: Freeman, Scott Sent: Tuesday, January 17, 2012 10:12 AM To: Failla, David Cc: Nazario, Tomy

Subject:

FW: Meeting With Westinghouse/PCI to Discuss Site Activities Dave, Can you sit in on this call?

From: Nazario, Tomy Sent: Tuesday, January 17, 2012 7:02 AM To: Freeman, Scott

Subject:

RE: Meeting With Westinghouse/PCI to Discuss Site Activities Agreed, we were planning on meeting Wed. since Westinghouse corporate reps will be onsite that day. If there is someone available from your branch to tie in, just let me know and we'll be happy to do so.

From: Freeman, Scott Sent: Tuesday, January 17, 2012 6:57 AM To: Nazarlo, Tomy

Subject:

RE: Meeting With Westinghouse/PCI to Discuss Site Activities We'll help if we can. The earlier we know the better. As for next week, we have the management retreat on Mon - Wed.

From: Nazarlo, Tomy Sent: Tuesday, January 17, 2012 6:49 AM To: Freeman, Scott; Failla, David Cc: Haag, Robert; Michel, Eric; Lewis, Russ; Fong, CJ; VanDoorn, Peter

Subject:

FYI: Meeting With Westinghouse/PCI to Discuss Site Activities Scott, As we discussed at the end of 2011, Westinghouse/PCI has a series of work activities lined up for early this year, several of which may require your branch's assistance. These include:

. RPV stud hole remediation

- SG remediation

- PZR remediation Both you and Dave were kind enough to provide assistance last month and we anticipate seeking out your branch's expertise over the coming months. In the interest of planning and keeping your branch in the loop, we plan on having an onsite meeting to discuss these upcoming activities, most of which Dave is very familiar with. We'll set up a date and exact time for this status meeting and were hoping your branch could tie in sometime next week, if available.

Tomy From: WBNNRCU2 [maiIto:wbnnrcu2(3tva.qov1 Sent: Tuesday, January 17, 2012 6:35 AM

To: Nazario, Tomy

Subject:

FW: Meeting With Westinghouse/PCI to Discuss Site Activities

Tomy, We will have one of our program managers from Pittsburgh on site 1/25/12 and available to join our discussion on near term WEC/PCI activities. We will work with you next week to set up a time a place for the meeting. One other update from our previous discussion, WEC will not be issuing a report on the phase one RV stud hole remediation, there will be one report issued at the end of phase two.

Thanks - Mike Michael E. Easter Westinghouse Electric Company Watts Bar Nuclear Plant 2