|
---|
Category:Letter
MONTHYEARML23319A2452024-01-29029 January 2024 Issuance of Amendment Nos. 366 and 360; 164 and 71 Regarding the Adoption of TSTF-567, Revision 1, Add Containment Sump TS to Address GSI-191 Issues ML24008A2462024-01-18018 January 2024 Revision to the Reactor Vessel Material Surveillance Capsule Withdrawal Schedule CNL-24-017, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions2024-01-17017 January 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions CNL-24-016, Supplement to Application to Modify the Technical Specification Surveillance Requirement 3.9.5.1 (WBN-TS-21-14)2024-01-10010 January 2024 Supplement to Application to Modify the Technical Specification Surveillance Requirement 3.9.5.1 (WBN-TS-21-14) CNL-23-052, Application to Adopt TSTF-427-A, Revision 2, Allowance for Non-Technical Specification Barrier Degradation on Supported System Operability2024-01-0909 January 2024 Application to Adopt TSTF-427-A, Revision 2, Allowance for Non-Technical Specification Barrier Degradation on Supported System Operability CNL-23-062, Application to Revise the Technical Specifications Section 3.8.2, AC Sources-Shutdown, to Remove Reference to the C-S Diesel Generator (WBN-TS-23-018)2024-01-0808 January 2024 Application to Revise the Technical Specifications Section 3.8.2, AC Sources-Shutdown, to Remove Reference to the C-S Diesel Generator (WBN-TS-23-018) ML23346A1382024-01-0303 January 2024 Regulatory Audit Summary Related to Request to Increase the Number of Tritium Producing Burnable Absorber Rods CNL-23-069, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-21021 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000390/20234412023-12-21021 December 2023 Plantfinal Significance Determination for a Security-Related Greater than Green Finding, Nov, and Assessment Follow-up, 05000390-2023441 and 05000391-2023441-Public CNL-23-036, Application to Revise Function 5 of Technical Specification Table 3.3.2-1, Engineered Safety Feature Actuation System Instrumentation, for the Sequoyah Nuclear Plant and Watts Bar Nuclear Plant (SQN-TS-23-02 and WBN-TS-23-08)2023-12-18018 December 2023 Application to Revise Function 5 of Technical Specification Table 3.3.2-1, Engineered Safety Feature Actuation System Instrumentation, for the Sequoyah Nuclear Plant and Watts Bar Nuclear Plant (SQN-TS-23-02 and WBN-TS-23-08) IR 05000390/20234042023-12-14014 December 2023 Security Baseline Inspection Report 05000390/2023404 and 05000391/2023404 CNL-23-001, Rebaseline of Sections 3.1 and 3.2 of the Technical Specifications (WBN-TS-23-01)2023-12-13013 December 2023 Rebaseline of Sections 3.1 and 3.2 of the Technical Specifications (WBN-TS-23-01) ML23293A0572023-12-0606 December 2023 Issuance of Amendment Nos. 163 and 70 Regarding Adoption of TSTF-501-A, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control IR 05000390/20230102023-11-30030 November 2023 RE-Issue Watts Bar Nuclear Plant - Biennial Problem Identification and Resolution Inspection Report 050000390/2023010 and 05000391/2023010 and Apparent Violation CNL-23-067, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-11-27027 November 2023 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions IR 05000390/20230032023-11-13013 November 2023 Integrated Inspection Report 05000390/2023003 and 05000391/2023003 and Apparent Violation ML23312A1432023-11-0808 November 2023 Submittal of Dual Unit Updated Final Safety Analysis Report (UFSAR) Amendment 5 CNL-23-059, Supplement to Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-2023-09-20020 September 2023 Supplement to Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 CNL-23-061, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision2023-09-20020 September 2023 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision ML23251A2002023-09-11011 September 2023 Request for Withholding Information from Public Disclosure for Watts Bar Nuclear Plant, Units 1 and 2 CNL-23-057, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC-EPIP-1, Revision 76 and CECC-EPIP-9, Revision 642023-09-0505 September 2023 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC-EPIP-1, Revision 76 and CECC-EPIP-9, Revision 64 IR 05000390/20230052023-08-30030 August 2023 Updated Inspection Plan for Watts Bar Nuclear Plant, Units 1 and 2 - Report 05000390/2023005 and 05000391/2023005 ML23233A0042023-08-28028 August 2023 Proposed Alternative to the Requirements of the ASME Boiler and Pressure Vessel Code for Upper Head Injection Dissimilar Metal Butt Welds IR 05000390/20230022023-08-16016 August 2023 Reissue - Watts Bar Nuclear Plant - Integrated Inspection Report 05000390/2023002 and 05000391/2023002 ML23220A1582023-08-0909 August 2023 Integrated Inspection Report 05000390/2023002 and 05000391/2023002 CNL-23-045, License Amendment Request to Revise Technical Specification Table 1.1-1 Regarding the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Bolts (WBN-TS-23-010)2023-08-0707 August 2023 License Amendment Request to Revise Technical Specification Table 1.1-1 Regarding the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Bolts (WBN-TS-23-010) CNL-23-028, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 and WBN-TS-23-06)2023-08-0202 August 2023 Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 and WBN-TS-23-06) ML23192A4472023-07-31031 July 2023 Staff Assessment of Updated Seismic Hazards at TVA Sites Following the NRC Process for the Ongoing Assessment of Natural Hazards Information CNL-23-055, Tennessee Valley Authority - Emergency Preparedness Department Procedure Revision. Includes EPDP-3, Revision 3, Emergency Plan Exercises and Preparedness Drills2023-07-25025 July 2023 Tennessee Valley Authority - Emergency Preparedness Department Procedure Revision. Includes EPDP-3, Revision 3, Emergency Plan Exercises and Preparedness Drills IR 05000390/20230112023-07-24024 July 2023 Quadrennial Focused Engineering Inspection (FEI) Commercial Grade Dedication Report 05000390 2023011 and 05000391 2023011 CNL-23-053, Tennessee Valley Authority - Radiological Emergency Plan Revisions2023-07-18018 July 2023 Tennessee Valley Authority - Radiological Emergency Plan Revisions CNL-23-020, Application to Revise Technical Specifications to Adopt TSTF-501-A, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control (WBN-TS-22-06)2023-06-28028 June 2023 Application to Revise Technical Specifications to Adopt TSTF-501-A, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control (WBN-TS-22-06) CNL-23-049, Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan .2023-06-26026 June 2023 Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan . ML23122A2322023-06-0707 June 2023 Issuance of Amendment Nos. 162 and 69 Regarding Change to Date in Footnotes for Technical Specification 3.7.11, Control Room Emergency Air Temperature Control System (Creatcs) CNL-23-044, Transmittal of Revision 3 to WCAP-18774-P and WCAP-18774-NP, Addendum to the Rotterdam Dockyard Company Final Stress Report for 173 P.W.R. Vessels TVA III & IV (Report No. 30749-B-030, Rev. 3) - Evaluation of One Closure Stud Out2023-06-0101 June 2023 Transmittal of Revision 3 to WCAP-18774-P and WCAP-18774-NP, Addendum to the Rotterdam Dockyard Company Final Stress Report for 173 P.W.R. Vessels TVA III & IV (Report No. 30749-B-030, Rev. 3) - Evaluation of One Closure Stud Out IR 05000390/20234032023-05-30030 May 2023 Cyber Security Inspection Report 05000390/2023403 and 05000391/2023403 ML23131A1812023-05-23023 May 2023 Correction to Amendment No. 161 to Facility Operating License No. NPF-90 CNL-23-042, Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-05-16016 May 2023 Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions IR 05000390/20220032023-05-0909 May 2023 Reissue Watts Bar Nuclear Plant - Integrated Inspection Report 05000390/2022003 and 05000391/2022003 ML23125A2202023-05-0505 May 2023 Issuance of Amendment No. 161 Regarding a Change to Footnotes for Technical Specification Table 1.1-1 Modes (Emergency Circumstances) IR 05000390/20230012023-05-0404 May 2023 Integrated Inspection Report 05000390/2023001 and 05000391/2023001 CNL-23-043, Emergency License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical Specification Table 1.1-1, Modes (WBN-TS-23-09)2023-05-0404 May 2023 Emergency License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical Specification Table 1.1-1, Modes (WBN-TS-23-09) CNL-23-032, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 412023-04-27027 April 2023 Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 41 CNL-23-030, Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System Project Milestone Status Update2023-04-27027 April 2023 Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System Project Milestone Status Update CNL-23-033, Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revision2023-04-24024 April 2023 Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revision CNL-23-029, Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-04-11011 April 2023 Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML23072A0652023-04-0505 April 2023 Units 1 and 2 Issuance of Amendment Nos. 364 and 358; 160 and 68 Regarding a Revision to Technical Specification 3.4.12 ML23073A2762023-04-0303 April 2023 Individual Notice of Consideration of Issuance of Amendments to Facility Operating Licenses, Proposed No Significant Hazards Consideration Determination, and Opportunity for a Hearing (EPID L-2023-LLA-0029) (Letter) CNL-23-023, Annual Insurance Status Report2023-03-30030 March 2023 Annual Insurance Status Report CNL-23-024, TVA Guarantee of Payment of Deferred Premiums - 2022 Annual Report2023-03-29029 March 2023 TVA Guarantee of Payment of Deferred Premiums - 2022 Annual Report 2024-01-09
[Table view] Category:Licensee Response to Notice of Violation
MONTHYEARML21027A3942020-12-0707 December 2020 TVA Response to Notice of Violations (EA-19-092) ML20198M4202020-07-0808 July 2020 William Bill Sprinkle, Response to Apparent Violation, IA-20-018 L-19-048, Response to Apparent Violation in NRC Inspection Report 05000390/2019013 and 05000391/2019013, EA-19-0422019-09-12012 September 2019 Response to Apparent Violation in NRC Inspection Report 05000390/2019013 and 05000391/2019013, EA-19-042 ML16344A0482016-12-0909 December 2016 Reply to Notice of Violation (EA-16-117) CNL-15-217, Reply to Notice of Violation (EA-15-112)2015-10-16016 October 2015 Reply to Notice of Violation (EA-15-112) CNL-15-152, Reply to Notice of Violation (EA-15-075)2015-07-24024 July 2015 Reply to Notice of Violation (EA-15-075) CNL-15-079, Reply to Notice of Violation (EA-14-179)2015-05-0101 May 2015 Reply to Notice of Violation (EA-14-179) ML13204A3832013-07-18018 July 2013 Reply to Notice of Violation (EA-13-019) 391/2013611-01, -02, and -03 Related to Tva'S Commercial Grade Dedication Program ML13192A0332013-07-0303 July 2013 Reply to a Notice of Violation; EA-13-018 IR 05000391/20106032012-07-17017 July 2012 Units 1 & 2 - Reply to Notice of Violation 05000391/2010603-08 - Failure to Adequately Evaluate and Qualify Molded Case Circuit Breakers - Revised Response ML12202A0102012-07-17017 July 2012 Units 1 & 2 - Reply to Notice of Violation 05000391/2010603-08 - Failure to Adequately Evaluate and Qualify Molded Case Circuit Breakers - Revised Response ML12172A4122012-06-18018 June 2012 Tennessee Valley Authority - Reply to Notice of Violation 05000391-10-603-08 - Failure to Adequately Evaluate and Qualify Molded Case Circuit Breakers - Revised Response ML12160A3522012-06-0707 June 2012 Reply to Notice of Violation 391/2012612-01 - Failure to Correct a Condition Adverse to Quality Associated with Containment Spray Pump Layup and Preventive Maintenance ML11164A1412011-06-0909 June 2011 Reply to Notice of Violation 05000391/2010603-08 - Failure to Adequately Evaluate and Qualify Molded Case Circuit Breakers - Revised Response ML11105A1502011-04-11011 April 2011 Request for Extension for Time to Respond to Severity Level IV, Non-Cited Violation 05000390-11-008-01 ML1109605912011-03-31031 March 2011 Response to Non-Cited Violations 05000390-10-005-03, Failure to Use Worst Case 6900 Vac Bus Voltage in Design Calculations ML1033002172010-11-24024 November 2010 Reply to Notice of Violation 05000391/2010603-08 - Failure to Adequately Evaluate and Qualify Molded Case Circuit Breakers ML1028804932010-10-15015 October 2010 Denial of Notice of Violation (NOV) 05000391-2010603-08, Failure to Adequately Evaluate and Qualify Molded Case Circuit Breakers - Additional Information ML1025204352010-09-0707 September 2010 Denial of Notice of Violation, 05000391/2010603-08, Failure to Adequately Evaluate and Qualify Molded Case Circuit Breakers ML0908306622009-03-23023 March 2009 Denial of Non-Cited Violation 05000390-08-05-04, Carbon Dioxide System in Fire Area 48 Failed to Meet Design Criterion ML0416002752004-06-0303 June 2004 & Watts Bar Nuclear Plant - Interim Safeguards and Security Compensatory Measures Reports & Notices of Violation - Reply to Notices of Violation ML0322000402003-07-25025 July 2003 National Pollutant Discharge Elimination System Permit No.TN0020158 - Response to Notice of Violation ML0316701792003-06-0404 June 2003 National Pollutant Discharge Elimination System (NPDES) Permit No. TN0020168 - Response to Notice of Violation 2020-07-08
[Table view] |
Text
Tennessee Valley Authority, Post Office Box 2000, Spring City, Tennessee 37381-2000 June 7, 2012 10 CFR 2.201 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001 Watts Bar Nuclear Plant, Unit 2 NRC Docket No. 50-391
SUBJECT:
WATTS BAR NUCLEAR PLANT (WBN) UNIT 2 - REPLY TO NOTICE OF VIOLATION 391/2012612 FAILURE TO CORRECT A CONDITION ADVERSE TO QUALITY ASSOCIATED WITH CONTAINMENT SPRAY PUMP LAYUP AND PREVENTIVE MAINTENANCE
References:
- 1. NRC letter dated May 9, 2012, "Watts Bar Nuclear Plant Unit 2 Construction
- NRC Problem Identification and Resolution Inspection Report"
- 2. NRC letter dated December 16, 2011, "Watts Bar Nuclear Plant Unit 2 Construction - NRC Integrated Inspection Report 05000391/2011609" The purpose of this letter is to provide a reply to Notice of Violation 391/2012612-01. provides TVA's reply to this violation. Enclosure 2 provides the list of commitments made in this letter.
Because this violation is cited against Appendix B, Criterion XVI, "Corrective Action," it should be noted that general improvements to the corrective action program are being addressed in response to issues identified both internally by TVA and externally by NRC (i.e., NCV 391/2012612-02, "Failure to Correct Longstanding CAP Deficiencies").
U.S. Nuclear Regulatory Commission Page 2 June 7, 2012 If you have any questions, please contact me at (423) 365-2351.
Respectfully, Raymond A. Hruby, Jr.
General Manager, Technical Services Watts Bar Unit 2
Enclosures:
- 1. Reply to Notice of Violation
- 2. List of Commitments cc (Enclosures):
U. S. Nuclear Regulatory Commission Region II Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, Georgia 30303-1257 NRC Resident Inspector Unit 2 Watts Bar Nuclear Plant 1260 Nuclear Plant Road Spring City, Tennessee 37381
ENCLOSURE I WATTS BAR NUCLEAR PLANT REPLY TO NOTICE OF VIOLATION 391/2012612-01 Description of the Violation "10 CFR 50, Appendix B, Criterion XVI, "Corrective Actions," states that measures shall be established to assure that conditions adverse to quality, such as failures, malfunctions, deficiencies, deviations, defective material and equipment, and nonconformances are promptly identified and corrected.
Contrary to the above, the applicant did not promptly correct an NRC identified condition adverse to quality. NCV 05000391/2011609-01 identified four vendor recommended layup and preventive maintenance activities that were not being performed on safety-related containment spray pumps. This discrepancy initially was reported to the applicant on October 5, 2011, and entered into the applicant's corrective action program on October 6, 2011. This discrepancy was identified as an NCV in NRC Inspection Report 05000391/2011609, dated December 16, 2011. On January 12, 2012, the applicant closed its corrective action document associated with the NCV, however, two of the four vendor recommendations (coat the exposed portions of the shafts with rust preventative and store the mechanical seal packages separately after one year of layup) were neither completed nor evaluated.
This is a Severity Level IV violation (Enforcement Policy 6.5.d)"
TVA Response:
TVA admits that this violation occurred.
Reason for the Violation:
The problems identified in this violation were the result of a failure to properly research the vendor requirements once the NRC. inspector identified several Layup and Preventative Maintenance (LUPM) items as having not been performed. Although TVA Procedure 25402-000-GPP-0000-N 1304, "System/Component Layup," requires that vendor recommendations be considered, this was not followed in this instance.
During TVA's investigation of this violation, it was found that a procedural weakness exists in that the data sheet used in performance of the System/Component Layup procedure only requires listing of the tasks to be performed, with no specific reference to the procedural step that requires vendor manual consultation. Thus, when the immediate actions of Problem Evaluation Report (PER) 444516 were developed, it was believed that for pumps, the only vendor requirements were the filling of the pump bearing housing with rust-inhibiting lubricating turbine oil and rotating the pump shaft every three months to recoat bearings with lubricant. Had the vendor manual been consulted, then PER 444516 would have referred to all four LUPM items, and closure of the PER would have been contingent upon evidence that all four items had been addressed, rather than the two items that were completed.
Contributing to the delay in implementing thorough corrective action was the fact that TVA did not compare the NRC Inspection Report 05000391/2011609, which TVA received on December 16, 2011, with the PER to ensure all issues had been addressed until March 5, 2012. Had this comparison taken place earlier, the remaining two items E1-1
ENCLOSURE I WATTS BAR NUCLEAR PLANT REPLY TO NOTICE OF VIOLATION 39112012612-01 that had not been completed may have been identified and corrected. The remaining two items were subsequently addressed by PER 517102.
Corrective Steps That Have Been Taken And The Results Achieved:
- 1. To address the initial four specific hardware issues associated with Containment Spray Pumps, TVA has performed the following:
For Item 1, Work Orders 10616425 and 10616439 were implemented on September 26, 2011, to add the required rust-inhibiting lubricating turbine oil to each of the pump bearing housings. Work Orders 112794808 and 112794832 have been initiated to perform an annual oil inspection for Containment Spray Pumps 2A-A and 2B-B, respectively.
For Item 2, TVA has chosen to leave the mechanical seal packages with the pumps.
This decision is based upon engineering evaluation after discussions with a vendor representative. The purpose of this separate storage requirement is to prevent the long-term distortion of the seal package due to pump inactivity, which could lead to damage resulting in seal leakage. Since the pumps must pass startup testing and must demonstrate operability via a surveillance requirement prior to being placed into service upon unit startup, any seal leakage would be identified at that time. If leakage is identified at startup, the seal package will be replaced. Alternatively, if no leakage is found and the pump passes the above testing, then no replacement will be needed.,
For Item 3, TVA has generated both LUPM items LUPM0084C and LUPM0083C and Work Orders 113327293 and 113327218 to coat shaft sleeve and exposed portions of shaft with rust preventative for each of the Containment Spray Pumps 2A-A and 2B-B, respectively.
For Item 4, Work Orders 112793258 and 112793362 have been initiated to perform quarterly shaft rotations for Containment Spray Pumps 2A-A and 2B-B, respectively.
- 2. Interim measures have been taken for TVA's corrective action program and have been incorporated into Nuclear Construction Project Procedure (NC PP) 3, "Watts Bar Unit 2 Corrective Action Program."
- 3. TVA has revised NC PP-18, "NRC Inspection Preparation and Support," to implement a process to track and document timely review of incoming NRC Inspection Reports to ensure that non-cited violations (NCVs) and unresolved items (URIs) are adequately addressed in the corrective action program. To determine the extent of condition, TVA conducted a review of the remaining outstanding NCVs and URIs to determine if any other items have not been documented with the correction action program. No other issues were identified. In addition, expectations were added to PP-1 8 to ensure that inspector concerns are properly documented prior to the inspector completing the inspection.
- 4. TVA is reviewing key safety-related component vendor manuals to determine LUPM requirements and transpose them into work documents and implementation schedules.
E1-2
ENCLOSURE I WATTS BAR NUCLEAR PLANT REPLY TO NOTICE OF VIOLATION 391/2012612-01 Corrective Steps That Will Be Taken
- 1. To address LUPM weaknesses initially suggested by the NCV 05000391/2011609-01 from Inspection Report dated December 16, 2011, TVA will issue a revision to existing Procedure 25402-000-GPP-0000-N 1304, "System/Component Layup."
- 2. TVA will conduct briefings for those employees using the revised Procedure 25402-000-GPP-0000-N1304, "System/Component Layup," to ensure that each employee is aware of the requirements and the changes made to this procedure.
- 3. TVA will continue to review safety-related component vendor manuals to determine LUPM requirements and transpose them into work documents and implementation schedules.
Date When Full Compliance Will Be Achieved.
TVA will be in full compliance by September 21, 2012.
- 4. General improvements to the corrective action program are being addressed in response to issues identified both internally by TVA and externally by NRC (i.e., NCV 391/2012612-02, "Failure to Correct Longstanding CAP Deficiencies"). These improvements are being tracked by PER 522107 within TVA's corrective action program.
The corrective action program updates will be completed in early 2013.
E1-3
ENCLOSURE 2 LIST OF COMMITMENTS
- 1. To address LUPM weaknesses initially suggested by the NCV 05000391/2011609-01 from Inspection Report dated December 16, 2011, TVA will issue a revision to existing Procedure 25402-000-GPP-0000-N 1304, "System/Component Layup."
- 2. TVA will conduct briefings for those employees using the revised Procedure 25402-000-GPP-0000-N1304, "System/Component Layup," to ensure that each employee is aware of the requirements and the changes made to this procedure.
- 3. TVA will continue to review safety-related component vendor manuals to determine LUPM requirements and transpose them into work documents and implementation schedules.
TVA will be in full compliance with the above actions by September 21, 2012.
- 4. General improvements to the corrective action program are being addressed in response to issues identified both internally by TVA and externally by NRC (i.e., NCV 391/2012612-02, "Failure to Correct Longstanding CAP Deficiencies"). These improvements are being tracked by PER 522107 within TVA's corrective action program.
The corrective action program updates will be completed in early 2013.
E2-1