Grand Gulf Nuclear Station - NRC Emergency Preparedness Annual Inspection Report 05000416/2011501
ML120590981
Person / Time
Site: Grand Gulf Entergy icon.png
Issue date: 02/28/2012
From: Hay M C
Plant Support Branch-1
To: Mike Perito
Entergy Operations
References
IR-11-501
Download: ML120590981 (2)


See also: IR 05000416/2011501

Text

February 28, 2012

Michael Perito Site Vice President Operations Entergy Operations, Inc.

Grand Gulf Nuclear Station P.O. Box 756 Port Gibson, MS 39150

SUBJECT: GRAND GULF NUCLEAR STATION - NRC EMERGENCY PREPAREDNESS ANNUAL INSPECTION REPORT 05000416/2011501

Dear Mr. Perito:

On December 31, 2011, the Nuclear Regulatory Commission (NRC) staff completed its annual inspection of the Emergency Preparedness Program at the Grand Gulf Nuclear Station. This inspection began on January 1, 2011. Issuance of this letter closes NRC Inspection Report 05000416/2011501. Observations and findings in these areas were provided in the quarterly integrated reports for your site.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,/RA/

Michael C. Hay, Chief Plant Support Branch 1 Division of Reactor Safety

Docket: 50-416 License: NPF-29

cc via Electronic Distribution Entergy Operations, Inc. - 2 -

Electronic distribution by RIV:

Regional Administrator (Elmo.Collins@nrc.gov) Deputy Regional Administrator (Art.Howell@nrc.gov)

DRP Director (Kriss.Kennedy@nrc.gov)

DRP Deputy Director (Troy.Pruett@nrc.gov)

DRS Director (Anton.Vegel@nrc.gov)

DRS Deputy Director (Tom.Blount@nrc.gov)

Senior Resident Inspector (Rich.Smith@nrc.gov)

Resident Inspector (Blake.Rice@nrc.gov)

Branch Chief, DRP/C (Vincent.Gaddy@nrc.gov)

Senior Project Engineer, DRP/C (Bob.Hagar@nrc.gov)

Project Engineer, DRP/C (Rayomand.Kumana@nrc.gov)

Project Engineer, DRP/C (Jonathan.Braisted@nrc.gov)

GG Administrative Assistant (Alley.Farrell@nrc.gov)

Public Affairs Officer (Victor.Dricks@nrc.gov) Public Affairs Officer (Lara.Uselding@nrc.gov)

Project Manager (Alan.Wang@nrc.gov)

Acting Branch Chief, DRS/TSB (Ryan.Alexander@nrc.gov)

RITS Coordinator (Marisa.Herrera@nrc.gov)

Regional Counsel (Karla.Fuller@nrc.gov)

Congressional Affairs Officer (Jenny.Weil@nrc.gov)

OEMail Resource ROPreports RIV/ETA: OEDO (Lydia.Chang@nrc.gov)

DRS/TSB STA (Dale.Powers@nrc.gov)

ADAMS: No x Yes x SUNSI Review Complete Reviewer Initials: MCH x Publicly Available x Non-Sensitive Non-publicly Available Sensitive C:PSB-1 MCHay /RA/ 2/28/12 OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax