ENCLOSURE 1 REVISED PAGES OF FACILITY OPERATING LICENSE NO. DPR-59 DOCKET NO. 50-333 JAMES A. FITZPATRICK NUCLEAR POWER PLANT Replace the following page of the Facility Operating License. The revised pages are identified by the date of the letter issuing the page and contain marginal lines indicating the areas of change.

REMOVE INSERT License DPR-59 License DPR-59 Page 7 Page 7


Page 8

Q. ENF shall take all necessary steps to ensure that the decommissioning trust is maintained in accordance with the application for the transfer of this license to ENF and ENO and the requirements of the order approving the transfer, and consistent with the safety evaluation supporting such order.

R. Mitigation Strategy License Condition Develop and maintain strategies for addressing large fires and explosions and that include the following key areas:

(a) Fire fighting response strategy with the following elements:

1. Pre-defined coordinated fire response strategy and guidance
2. Assessment of mutual aid fire fighting assets
3. Designated staging areas for equipment and materials
4. Command and control
5. Training of response personnel (b) Operations to mitigate fuel damage considering the following:
1. Protection and use of personnel assets
2. Communications
3. Minimizing fire spread
4. Procedures for implementing integrated fire response strategy
5. Identification of readily-available pre-staged equipment
6. Training on integrated fire response strategy
7. Spent fuel pool mitigation measures (c) Actions to minimize release to include consideration of:
1. Water spray scrubbing
2. Dose to onsite responders S. The licensee shall implement and maintain all Actions required by Attachment 2 to NRC Order EA-06-137, issued June 20, 2006, except the last action that requires incorporation of the strategies into the site security plan, contingency plan, emergency plan and/or guard training and qualification plan, as appropriate.

Revised by letter dated August 23, 2007

3. This license is effective as of the date of issuance and shall expire at midnight on October 17, 2014.

FOR THE NUCLEAR REGULATORY COMMISSION (ORIGINAL SIGNED BY: ROBERT W. REID)

Robert W. Reid, Chief Operating Reactors Branch #4 Division of Operating Reactors Attachments/Appendices:

1. Appendix A - Technical Specifications
2. Appendix B - Deleted
3. Appendix C - Additional Conditions Date of Issuance: June 3, 1977 Revised by letter dated August 23, 2007