Notice of Meeting with Firstenergy Regarding May 14, 2007 Demand for Information Davis-Besse
ML071620212
Person / Time
Site: Beaver Valley, Davis Besse, Perry  FirstEnergy icon.png
Issue date: 06/13/2007
From: Thomas Wengert
NRC/NRR/ADRO/DORL/LPLIII-2
To: Russell Gibbs
NRC/NRR/ADRO/DORL/LPLIII-2
Wengert, Thomas NRR/DORL 415-4037
References
FOIA/PA-2007-0299
Download: ML071620212 (9)


Text

June 13, 2007 MEMORANDUM TO: Russell Gibbs, Branch Chief Plant Licensing Branch III-2 Division of Operating Reactor Licensing FROM: Thomas Wengert, Project Manager /RA/

Plant Licensing Branch III-2 Division of Operating Reactor Licensing

SUBJECT:

FORTHCOMING MEETING WITH FIRSTENERGY NUCLEAR OPERATING COMPANY REGARDING MAY 14, 2007, DEMAND FOR INFORMATION DATE & TIME: Wednesday, June 27, 2007 9:00 a.m. - 12:00 p.m. (NOON)

LOCATION: U.S. Nuclear Regulatory Commission One White Flint North Commissioners Conference Room (O-1F16/O-1G16) 11555 Rockville Pike Rockville, Maryland 20852 PURPOSE: FirstEnergy Nuclear Operating Company (FENOC) will discuss their response to the NRCs May 14, 2007, Demand for Information (DFI) regarding FENOCs re-analysis of the timeline and root causes for the 2002 Davis-Besse reactor pressure vessel head degradation event.

Background information on the DFI is available via Agencywide Documents Access and Management System Accession No. ML071340325.

CATEGORY 1:

  • This is a Category 1 Meeting. The public is invited to observe this meeting and will have one or more opportunities to communicate with the NRC after the business portion, but before the meeting is adjourned.

The NRC staff is making arrangements for interested members of the public to participate in the meeting via tele-conference and/or via video-conference at the Region III office in Lisle, IL. This meeting notice will be updated as details become available.

MEETING CONTACTS: Thomas Wengert, NRR Doug Starkey,OE 301-415-4037 301-415-3456 tjw2@nrc.gov drs@nrc.gov

  • Commission's Policy Statement on Enhancing Public Participation in NRC Meetings (67 FR 36920), May 28, 2002

R. Gibbs PARTICIPANTS: Participants from the NRC include members of the Office of the Executive Director for Operations (OEDO), Office of Enforcement (OE), Office of Nuclear Reactor Regulation (NRR), Region I and Region III.

NRC FENOC C. Carpenter, OE J. Hagan W. Kane, OEDO D. Pace M. Virgilio, OEDO G. Halnon J. Dyer, NRR C. Price S. Collins, Region I J. Powers J. Caldwell, Region III Docket Nos. 50-346, 50-440, 50-334, and 50-412

Enclosure:

Agenda cc w/encl: See next page

ML071620212 NRR-001 OFFICE LPL3-2/PM LPL3-2/LA LPL3-2/BC NAME TWengert EWhitt RGibbs DATE 06/13/2007 06/13/2007 06/13/2007 Forthcoming Meeting with FirstEnergy Nuclear Operating Company Regarding May 14, 2007, Demand for Information Date: June 13, 2007 Distribution:

PUBLIC R/F LPL3-2 RidsNrrAdro RidsNrrDorl RidsNrrDorlLpl3-2 RidsNrrPMTWengert RidsNrrPMNMorgan RidsNrrLAEWhitt T. Liu, NRR C. Carpenter, OE W. Kane, OEDO M. Virgilio, OEDO J. Dyer, NRR S. Collins, Region I J. Caldwell, Region III L. Chandler, OGC RidsRgn1MailCenter RidsRgn3MailCenter J. Lamb, EDO Region I T. Bloomer, EDO Region III D. Screnci, OPA Region I J. Strasma, OPA Region III PMNS RidsOgcMailCenter RidsAcrsAcnwMailCenter Receptionist OWFN and TWFN [paper copy]

U. S. NUCLEAR REGULATORY COMMISSION AND FIRSTENERGY NUCLEAR OPERATING COMPANY (FENOC)

MEETING REGARDING FENOC RESPONSE TO MAY 14, 2007, DEMAND FOR INFORMATION CONCERNING RE-ANALYSIS OF THE TIMELINE AND ROOT CAUSES FOR 2002 DAVIS-BESSE REACTOR PRESSURE VESSEL HEAD DEGRADATION EVENT JUNE 27, 2007 AGENDA 9:00 a.m. - 9:15 a.m. Introductions and opening remarks 9:15 a.m. - 10:15 a.m. FENOC presentation of Demand for Information response 10:15 a.m. - 11:15 a.m. Questions from NRC 11:15 a.m. - 11:30 a.m. Concluding remarks from FENOC and NRC 11:30 a.m. - 12:00 p.m. Communication with the NRC from members of the public 12:00 p.m. (NOON) Adjourn

Davis-Besse Nuclear Power Station, Unit No. 1 cc:

Manager, Site Regulatory Compliance 30 East Broad Street FirstEnergy Nuclear Operating Company Columbus, OH 43216 Davis-Besse Nuclear Power Station Mail Stop A-DB-3065 President, Board of County 5501 North State Route 2 Commissioners of Ottawa County Oak Harbor, OH 43449-9760 Port Clinton, OH 43252 Director, Ohio Department of Commerce President, Board of County Division of Industrial Compliance Commissioners of Lucas County Bureau of Operations & Maintenance One Government Center, Suite 800 6606 Tussing Road Toledo, OH 43604-6506 P.O. Box 4009 Reynoldsburg, OH 43068-9009 The Honorable Dennis J. Kucinich United States House of Representatives Regional Administrator, Region III Washington, D.C. 20515 U.S. Nuclear Regulatory Commission 2443 Warrenville Road The Honorable Dennis J. Kucinich Lisle, IL 60532-4352 United States House of Representatives 14400 Detroit Avenue Resident Inspector Lakewood, OH 44107 U.S. Nuclear Regulatory Commission 5503 North State Route 2 Joseph J. Hagan Oak Harbor, OH 43449-9760 President and Chief Nuclear Officer FirstEnergy Nuclear Operating Company Stephen Helmer Mail Stop A-GO-14 Supervisor, Technical Support Section 76 South Main Street Bureau of Radiation Protection Akron, OH 44308 Ohio Department of Health 35 East Chestnut Street, 7th Floor David W. Jenkins, Attorney Columbus, OH 43215 FirstEnergy Corporation Mail Stop A-GO-15 Carol OClaire, Chief, Radiological Branch 76 South Main Street Ohio Emergency Management Agency Akron, OH 44308 2855 West Dublin Granville Road Columbus, OH 43235-2206 Danny L. Pace Senior Vice President, Fleet Engineering Zack A. Clayton FirstEnergy Nuclear Operating Company DERR Mail Stop A-GO-14 Ohio Environmental Protection Agency 76 South Main Street P.O. Box 1049 Akron, OH 44308 Columbus, OH 43266-0149 Manager, Fleet Licensing State of Ohio FirstEnergy Nuclear Operating Company Public Utilities Commission Mail Stop A-GO-2 180 East Broad Street 76 South Main Street Columbus, OH 43266-0573 Akron, OH 44308 Attorney General Office of Attorney General

Davis-Besse Nuclear Power Station, Unit No. 1 Perry Nuclear Power Plant, Unit No. 1 cc: cc:

Director, Fleet Regulatory Affairs Resident Inspector's Office FirstEnergy Nuclear Operating Company U.S. Nuclear Regulatory Commission Mail Stop A-GO-2 P.O. Box 331 76 South Main Street Perry, OH 44081-0331 Akron, OH 44308 Sue Hiatt Jeannie M. Rinckel OCRE Interim Representative Vice President, Fleet Oversight 8275 Munson FirstEnergy Nuclear Operating Company Mentor, OH 44060 Mail Stop A-GO-14 76 South Main Street Manager, Site Regulatory Compliance Akron, OH 44308 FirstEnergy Nuclear Operating Company Perry Nuclear Power Plant Richard Anderson Mail Stop A-PY-A200 Vice President, Nuclear Support P.O. Box 97, 10 Center Road FirstEnergy Nuclear Operating Company Perry, OH 44081-0097 Mail Stop A-GO-14 76 South Main Street Mayor, Village of North Perry Akron, OH 44308 North Perry Village Hall 4449 Lockwood Road Mark B. Bezilla North Perry Village, OH 44081 Site Vice President FirstEnergy Nuclear Operating Company Donna Owens, Director Davis-Besse Nuclear Power Station Ohio Department of Commerce Mail Stop A-DB-3080 Division of Industrial Compliance 5501 North State, Route 2 Bureau of Operations & Maintenance Oak Harbor, OH 43449-9760 6606 Tussing Road P.O. Box 4009 James H. Lash Reynoldsburg, OH 43068-9009 Senior Vice President of Operations and Chief Operating Officer Mayor, Village of Perry FirstEnergy Nuclear Operating Company P.O. Box 100 Mail Stop A-GO-14 Perry, OH 44081-0100 76 South Main Street Akron, OH 44308 Chairman Perry Township Board of Trustees 3750 Center Road, Box 65 Perry, OH 44081

Beaver Valley Power Station, Unit Nos. 1 Daniel Z. Fisher and 2 Transportation Department Public Utilities Commission cc:

180 East Broad Street Columbus, OH 43215-3793 Manager, Site Regulatory Compliance FirstEnergy Nuclear Operating Company Barry S. Allen Beaver Valley Power Station Site Vice President Mail Stop A-BV-A FirstEnergy Nuclear Operating Company P.O. Box 4, Route 168 Perry Nuclear Power Plant Shippingport, PA 15077 Mail Stop A-PY-A290 P.O. Box 97, 10 Center Road Commissioner James R. Lewis Perry, OH 44081-0097 West Virginia Division of Labor 749-B, Building No. 6 Capitol Complex Charleston, WV 25305 Director, Utilities Department Public Utilities Commission 180 East Broad Street Columbus, OH 43266-0573 Director, Pennsylvania Emergency Management Agency 2605 Interstate Dr.

Harrisburg, PA 17110-9364 Dr. Judith Johnsrud Environmental Coalition on Nuclear Power Sierra Club 433 Orlando Avenue State College, PA 16803 Director Bureau of Radiation Protection Pennsylvania Department of Environmental Protection Rachel Carson State Office Building P.O. Box 8469 Harrisburg, PA 17105-8469 Mayor of the Borough of Shippingport P.O. Box 3 Shippingport, PA 15077 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406

Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 298 Shippingport, PA 15077 James H. Lash Site Vice President FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop A-BV-SEB1 P.O. Box 4, Route 168 Shippingport, PA 15077