SOUTH TEXAS PROJECT UNITS 3 & 4 Presentation to the NRC October 18, 2006 1

Agenda o Objectives &

Opening Remarks Mark McBurnett o Project Progress &

Licensing Schedule Greg Gibson o Engineering Steve Thomas o Concluding Remarks Greg Gibson 2

Objectives and Opening Remarks Mark McBurnett Vice President Reg ulatory Affairs and Oversig ht I

3

Objectives o Update progress since the July 27 presentation o Provide status of major activities D Identify issues and initiate discussions 4

Project Organization o Since July, STPNOC has developed infrastructure

" GE - COLA contractor

  • Bechtel - Site characterization work

" MacTec - Geotechnical (core borings)

  • Tetra Tech NUS - Environmental report work

" Baker/Botts - Environmental permits

  • Hitachi - Modularization construction consultant

" TEPCO - Operating experience consultant 5

STP Organization Quality Regulatory Affairs 9 Supervisor Manager Marion Smith Greg Gibson PRA i Supervisor Supervisor Bill Stillwell 6

GE Organization 7

Bechtel Organization Quality Services I Raj Jolly 8

Processes o Procedures on COLA section preparation, review, and approval being finalized by GE and STP o Quality Assurance Program

" Operational Quality Assurance Program and Corrective Action Program

" Station Procedure revisions for U 1, 2, 3, 4 o Project Design Review Board (PDRB) - DCWG procedure approved 9¸

Site Work Commencing o Site characterization

  • ] Meteorology analysis underway
  • Soil and hydrology studies initiated October 9
  • ] Core Boring Plan approved
  • ] Borings under base mats first
  • ] October through January 2007 10

S~ummary o Infrastructure being established o Onsite work initiated 11

Project Progress and Licensing Schedule Greg Gibson Manager I Regulatory Affairs 12

Agenda - Projmect Progress

& Licensing Schedule

" Review

" COLA and Schedule o Licensing Topical Reports o Optimizing the Regulatory Process

" Permits o Anticipated Interactions 13

Review -July 27 Meeting ABWR attributes:

m Design certification approved m FOAKE complete N ABWR Family - Significant Operating Experience o] 4 operating ABWRs o1 3 ABWRs now under construction 0 12 additional ABWRs (including STP Units 3 and 4) planned for operation by 2017 14

Review - July 27 Meeting Strategy:

m Minimize departures from DCD

. Utilize NEI templates m Optimize the application process 15

Maximize Certified Design Percent of FSAR Section Type Sections 25% Match DCD with no changes or additions; 30 % Standard for all ABWR COL applications (identical).

Use NEI templates 13 % Standard with a limited amount of site-specific information 12 %? miiadard withi a mnoderate am110L1ounof site-specific S$>~

20~t% Site Specific; 100%

16

COLA o Submittal of COLA 4Q07 o Critical path is geotechnical analyses

  • Soil characterization
  • Probabilistic seismic hazards analysis o Working to Optimize schedule and reduce critical path 17

COLA Schedule c~1~ Eany ORG Total 2MIN 2007 j Acivt ID.

Activiy Deschiptionl Our Elsoy' Otait 1`1111h .I'.ý.fei

._ II A I:

'M I I I f"I II I 11.t 1 I F I LI I I I I ,A I M I IiI I I I I .II Ii I Il I I pI1 1 r,,,,,,,,

GE423D01D~ Pefiahe Comywentaissue F~il 2~ 05F~B~ T EVW GE .57 K~ J7 I,

FS~AR AIn- Doartltitol Enaror~noii(Genr'ttcomom 4R 1I fO~4eia :On~I ~qx rIBI*c9 I GE42DI031 0 F5AJRI.11- Cpera~iOlaIExcorenoe (GmEneiCrmnm C-E-42041140D GE*1* 111501:1 IPrpia Draft

__W__-_

I 15E' [1 SEP06 11f1MMEFr.,

2U109oS&R:7 2-,9D XRN I

,3mAjrl

,2%AIl GE

_-GE1 IA-L 15 l

1,Ž 15 I

r WalIl I 1I I

.1 II II II II II IC-~1542l J0 Raoloa Carnrr,&su IFw I ;23102AFM7 27Afl PRO Iz a - - I-Il - 4-i- - - + - -,--

91mn1~nt + .1e~ueFbi +

+ 4-.--.'- '-, - - - -

FS.t

- oaPVISDAI-TMA~fi T MalkftluI~ II II II I C-E420132fl- JFSARlA -Reepofte to TMII Re-toad Iftefs 155 15SEP06 j 27APR137 GE IB 1-1

~e~T~IF eIa~.dI GE2I2K12-:1 PrepweDraf!e 11 I SEFO-T rO-.2-ARd,7 GE 1 IýO I .t.4 -~oJ

-to-

.5 p ~I II

  • 1 I

I

--E4201210- CDL Item 1.8 RR Ilures f RS vafres 25 1VSEF05' mo..TOE GE 109 ~olo II II 35 1S5SEPO5 r,5NOVE6 -GE 9- Ite II T

-E42111211fl COL Item 1.10;- RmtorReac.kVenln Ii II GE42312111: C0L Item 1.11 - Te'-t "-V &-Isr:arge- Pine 35j I1SEP05 E3.NOVt6 C-E42M 12112 C-LItem 1. 12 -.RCICB)p3s .arlSy TE-Et 541 ISEF06" -____

rlEQ.E _i E 5 ,l_________________________I tE2E-E81 It41 .*-t I rd~ a?, ';i , I I E42aI210- C31 Item- 1.5 -IErmrg Pro, & TrItngPi GE GE 57 r CW I7EF 'bq C-E4231210E CCDL fler 1.75-RE'NptMn Pmr foT &R Sng 97 1i5SEF0t' 2EV E107 ci w1 tm 91, 1oPeM~o: oF Y GE42012107 C-OL Iteni 1. - M-pamMc Rad ft S-Il S1t e 97 1SSEFCOS E.ZEE07 GE 3' an R90 A~a?4t ling S G-142T12103 001 Item 1.9 - RcpWt on ECCS- Curag~s 97 11SSEFOS- 02FEWO E Cj trf~R rý.S1 n'-s:

  • 1 I I I II G421250M Reviw DraM 2,3Me0 a 20MAR07 ALL I I ~pn RE501-e CaT'rV*e&ItI*&Je FIal 20 IOAPFf7 27APE07 I I 9~n4nI Ia Iu011 1Ftn IGE42312WOfl I I 18

Potential Topical Reports COL Item Closure

" Detailed Design Implementation Process (COL Item 1.1, DCD Section 1.1.11) 1Q07

" Life Cycle Management Program (COL Item 1.1 a, DCD Section 1.2.3) 2Q07

" Onsite Meteorological Measurements Program (COL Item 2.10, DCD Section 2.3.2) TBD

" ABWR Internals Vibration Assessment Program Results (COL Item 3.27, DCD Section 3.9.7) 2Q07

  • Fuel Design Stabiit yopliane(COL Item 4.1,in DCD ýSection4.3.5) 2Q07
  • Surveillance Program (COL Item 5.5, DCD Section 5.3.4) 2Q07
  • Fuel Bundle MAPLHGR, Peak Cladding Temp and Oxidation Fraction (COL Item 6.6, DCD:Section 6.3.6) 4Q06 Fuel Bundle Limiting Break (COL Item 6.7a, DCD SectiOn 6.3.6)

P 4Q06

APRM OscillafionMonitoriLogic (COL Item 7.2 DCD Section 7.6.3) 2Q07
  • Fuel Inspection Stand Installation (COL Item 9.5, DCD Section 9.1.6) 1Q07
  • List and Properties of Cranes, Hoists, Elevators (COL Item 9.6, DCD Section 9.1.6) 1Q07
  • Spent Fuel Racks Structural Evaluation (COL Item 9.7, DCD Section 9.1.6) 1Q07
  • Spent Fuel Rack Thermal-Hydraulic Analysis (COL Item 9.8, DCD Section 9.1.6) 1Q07
  • Plant Operating Procedures Development Plan (COL Item 13.3, DCD Section 13.5.3) TBD
  • Emergency Procedures Writers Guide (COL Item 13.4, DCD Section 13.5.3) TBD
  • Plant Operating Procedures Development Plan Implementation (COL Item 13.5, DCD Section 13.5.3) TBD
  • Preoperational Test Specification, Startup Test Specification, and Test Plan (COL Item 14.1, DCD Section 14.2.13) 2Q07
  • Operational Reliability Assurance Program (COL Item 17.4, DCD Section 17.4) 2Q07 19

Potential Topical Reports Desi2n Acceptance Criteria

" Safety System Logic and Control/Reactor Trip and Isolation Functions Hardware/Software Specification 2Q07

" DCIS Software Management Plan 1Q07

" DCIS Software Configuration Management Plan 4Q06

" DCIS Software Safety Plan 1Q07

" DCIS Software V&V Plan 1Q07

" DCIS Installation Review Plan 2Q07

" Electromagnetic Compliance Implementation Plan 1Q07

" DCIS Factory Acceptance Test Plan 2Q07

" HFE Design Implementation Plan 2Q07 20

Potential Topical Reports DCD Departures/Site-Specific Design Information

GESTAR TBD

'GE**Fuel Assembly.Mechanical DesignReport4Q6

  • GEx Futel Rd Ther~mal-'Mechanical.Design Report 4Q06

" GExx Pressure Drop Chaacteristics 4Q06 2Q07

  • GExx Nucledr Desigf Report ax*

GExCritical -Power Correlation, Uiieertaif and OLMCPRDevelopment 2Q07

.Control Rod Nuclear DesignReport 2007

. Con*trolRod Mechanictl Design Repot 2Q07

  • Weir-Type RCIC Pumps 4Q06

. Hydrogen Recombiner Deletion 2Q07

  • Plant Electrical System 2Q07
  • Fiber Optic Links 1Q07
  • Control Building Annex - Relocation of MG Sets 2Q07
  • Shared Common Equipment (e.g., fire pump) 2Q07 21

Optimize Application Process o Identify issues where application process can be optimized o Quality COLA - Level of Detail; Follow DG-1145 &

SRP o] Early discussion on issues o] RAI responses submitted quickly o Discuss issues, options, and resolutions with NRC Staff in public meetings 22

Example Issue: Fuel Selection o GE P8x8R fuel used in certified design (8 x 8)

" No longer manufactured

  • No longer supported o GE14 fuel (10x 10) currently available but very likely will not be the actual fuel used (we will use fuel design circa 2011) 23

Example Issue: Fuel Selection o Changing COLA fr om GE P8x8R to GE 14 impacts "8% of FSAR and 12 LTRs o Most work from GE P8x8R to GE14 must be redone when GEx is selected, and license amendments performed circa 2012 o Changing COLA from GE P8x8R to GE14 expends resources with little value 24

Example Issue: Fuel Selection o Potential resolution:

  • Use GE P8x8R fuel - no DCD departures for fuel related-issues o1 No departures from DCD Chapters 4, 12, 15, 19 for fuel-related issues at this time o No departures from DCD subsections 1C, 2.3.2.9, 2.3.2.10, 2A, 31, 5.2.2, 6.3, and 11.1 for fuel related issues at this time o] Deferred LTR submittals for fuel-related issues
  • Commit in COLA submittal letter to submit standard fuel change amendment o Benefit: No duplicated NRC review and no wasted STPNOC & NRC resources 25

Permits and Authorizations o Developing permit schedules o Meet with applicable agencies in 4Q06 o Begin application process in 1Q07 o Anticipate involvement of 10 agencies, involving 23 permits and authorizations 26

Anticipated Interactions o NRC to observe site boring work o Continue periodic meetings with next meeting early December o Expect NRC public meeting at site in early 2007 27

Engineering Steve Thomas Manager, Engineering 28

Agenda - Engineering o Site Plan o Boring Plan o Site Work Statu S o Design Ce nter Working G roup -

Project Design Review Board 29

30 31 32 Site Plan 1--

I I j*

33

Boring Plan 34

poring Pian Reactor/Turbine Buildings 35

Borings - Detail BORINGS (125 total) 2 to 600 feet 25 to 200 feet 14 to 150 feet 37 to 100 feet' 11 to 75 feet 3 to 50 feet 2 to 40 feet Observation Wells (30 15 to 125 feet total) 15 to 50 feet CPTs (35 total) 13 to 100 feet, including 5 seismic cones 7 to 50 feet 15 to 40 feet Test Pits (20 total) 20 pits 10 feet Downhole Geophysical Perform borehole logging and suspension P-S logging in both the 600 ft holes and in 8 of the 200 ft holes Field Electrical Resistivity 2 tests - each test has 10 electrode "A" spacing up to 300 ft.

36

Site Work o MacTec onsite

" Work October through.January 37

Site Soil Characterization 38

DCWG/ PDRB o Established DCWG

" STPNOC

" Amarillo Power [Pending]

o Established PDRB

  • ] Charter
  • Two meetings
  • Scheduled to complete review identified Tier 1, Tier 2*,

and significant Tier 2 issues by 12/31/06 39

Potential Design Changes 0 Tier 1 Changes:

" RCIC Weir Turbine Pump [improves reliability]

" STP Flood Level [site requirement]

  • Hydrogen Recombiner Removal [Industry standard]

[improves reliability/safety]

  • ] 110.% Bypass Capability [improves reliability]

40

Potential Design Changes o Tier 2* Changes:

n Fuel m ACI 349 - 1990 edition m Fiber Optic Links (Not formal ANSI FDDI Standard) o Significant Tier 2 Changes o Other Tier 2 changes will be evaluated using process "similar to 50.59" using the criteria in Appendix A to Part 52 41

PDRB Reviewed Changes o Removal of SCRAM and MSIV automatic closure on MSLRM alarm o Weir-type turbine RCIC pump in lieu of Terry turbine pump o 110% Bypass Capability o Provide two 2% RWCU pumps instead of two 1%/

RWCU pumps o Medium voltage electrical distribution 0 Control building addition 42

Concluding Remarks Greg Gibson Manager f Regulatory Affairs 43

Next Meeting o Propose meeting early Dece muber o Possible topics m COLA and LTR schedules

" Resolution of DAC items

" Creating-a quality COLA

" Units 3 & 4 Quality Assu rance n Site characterization work status n Engineering and design- status/schedule m Emerging issues 44

Projmect -overview o Key contracts in place. Major component contracts in 2Q07 to lock in forging slots o Begin site preparations in 2008 D Unit 3 start-up in 2014/2015 o Infrastructure in place o Site characterization work proceeding o COLA 4Q07 and permit applications 1Q07 o DCWG established and PDRB active 45