Category:Letter
MONTHYEARL-2024-010, Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3)2024-01-25025 January 2024 Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3) NG-23-0010, Supplement to Duane Arnold Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule2023-12-0606 December 2023 Supplement to Duane Arnold Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule NG-23-0009, Part 73 Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule2023-11-16016 November 2023 Part 73 Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule ML23201A0872023-08-0303 August 2023 Audit Plan in Support of Review of License Amendment NG-23-0006, Independent Spent Fuel Storage Installation (ISFSI) Financial Assurance Update2023-05-23023 May 2023 Independent Spent Fuel Storage Installation (ISFSI) Financial Assurance Update ML23137A1672023-05-11011 May 2023 Submittal of 2022 Annual Radiological Environmental Operating Report NG-23-0004, 2022 Annual Radioactive Material Release Report2023-04-25025 April 2023 2022 Annual Radioactive Material Release Report NG-23-0003, 2022 Annual Exposure Report - Form 5s2023-04-21021 April 2023 2022 Annual Exposure Report - Form 5s NG-23-0002, 10 CFR 50.59 Report, Commitment Changes, 10 CFR 72.48 Report, Quality Assurance Program Changes, Technical Specification Basis Changes, and Revision of the DAEC Defueled Safety Analysis Report2023-03-27027 March 2023 10 CFR 50.59 Report, Commitment Changes, 10 CFR 72.48 Report, Quality Assurance Program Changes, Technical Specification Basis Changes, and Revision of the DAEC Defueled Safety Analysis Report NG-23-0001, 2023 Annual Decommissioning and Spent Fuel Management Funding Status Report2023-03-27027 March 2023 2023 Annual Decommissioning and Spent Fuel Management Funding Status Report L-2023-029, and Point Beach Units 1 and 2 Nuclear Property Insurance - 10 CFR 50.54(w)(3)2023-03-10010 March 2023 and Point Beach Units 1 and 2 Nuclear Property Insurance - 10 CFR 50.54(w)(3) ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities ML22339A0012022-12-22022 December 2022 Acceptance of Requested Licensing Action Amendment Request for Common Emergency Plan IR 05000331/20220032022-12-13013 December 2022 NRC Inspection Report No. 05000331/2022003 (Drss) ML22285A0072022-10-13013 October 2022 NRC Analysis of NextEra Energy Duane Arnold'S Decommissioning Funding Status Report, Docket No. 50-331 IR 05000331/20220022022-07-13013 July 2022 NRC Inspection Report Nos. 05000331/2022002(DNMS) and 07200032/2022002(DNMS) ML22090A1922022-05-26026 May 2022 Letter to B. Coffey, FPL from M. Doell - Duane Arnold Post Shutdown Activities Report Review Letter ML22132A2872022-05-24024 May 2022 ISFSI DQAP Approval Letter ML22111A0332022-05-20020 May 2022 Operating License Page Correction Letter to B. Coffey, Florida Power and Light, from M. Doell NG-22-0055, Revision to Duane Arnold Energy Center (DAEC) ISFSI-Only Emergency Plan2022-05-20020 May 2022 Revision to Duane Arnold Energy Center (DAEC) ISFSI-Only Emergency Plan ML22089A0492022-05-12012 May 2022 Sfmp Review Letter NG-22-0053, 2021 Annual Radiological Environmental Operating Report2022-05-0606 May 2022 2021 Annual Radiological Environmental Operating Report NG-22-0052, Regulatory Issue Summary 2000-11. NRC Emergency Telecommunications System, Statement of Intent to Implement the Proposed Voluntary Initiative2022-05-0404 May 2022 Regulatory Issue Summary 2000-11. NRC Emergency Telecommunications System, Statement of Intent to Implement the Proposed Voluntary Initiative IR 05000331/20224012022-04-27027 April 2022 Decommissioning Security Inspection Report 05000331/2022401 NG-22-0050, Revised Response to Request for Additional Information Relating to Decommissioning Quality Assurance Program, Revision 02022-04-26026 April 2022 Revised Response to Request for Additional Information Relating to Decommissioning Quality Assurance Program, Revision 0 NG-22-0049, 2021 Annual Radioactive Material Release Report2022-04-26026 April 2022 2021 Annual Radioactive Material Release Report L-2022-068, NextEra Energy Duane Arnold Quality Assurance Topical Report (FPL-3) Revision 22022-04-25025 April 2022 NextEra Energy Duane Arnold Quality Assurance Topical Report (FPL-3) Revision 2 ML22066A7632022-04-25025 April 2022 ISFSI-Only Emergency Plan License Amendment Approval NG-22-0035, Response to Request for Additional Information Relating to Decommissioning Quality Assurance Program. Revision 02022-04-13013 April 2022 Response to Request for Additional Information Relating to Decommissioning Quality Assurance Program. Revision 0 NG-22-0047, Registration of Independent Spent Fuel Installation Storage Cask and Notification of Permanent Removal of All Spent Fuel Assemblies from the Spent Fuel Pool2022-04-11011 April 2022 Registration of Independent Spent Fuel Installation Storage Cask and Notification of Permanent Removal of All Spent Fuel Assemblies from the Spent Fuel Pool NG-22-0042, Registration of Independent Spent Fuel Installation Storage Casks2022-04-0808 April 2022 Registration of Independent Spent Fuel Installation Storage Casks NG-22-0041, and Independent Spent Fuel Storage Installation, 2022 Annual Decommissioning and Spent Fuel Management Funding Status Report2022-03-31031 March 2022 and Independent Spent Fuel Storage Installation, 2022 Annual Decommissioning and Spent Fuel Management Funding Status Report NG-22-0031, 2021 Annual Exposure Report - Form 5s2022-03-23023 March 2022 2021 Annual Exposure Report - Form 5s NG-22-0030, Registration of Independent Spent Fuel Installation Storage Casks2022-03-23023 March 2022 Registration of Independent Spent Fuel Installation Storage Casks ML22080A1822022-03-22022 March 2022 Letter to B. Coffey from M. Doell - Duane Arnold ISFSI QAPD RAI Letter L-2022-012, Florida Power & Light Company Nuclear Property Insurance - 10 CFR 50.54(w)(3)2022-03-16016 March 2022 Florida Power & Light Company Nuclear Property Insurance - 10 CFR 50.54(w)(3) ML22059A7462022-03-10010 March 2022 ISFSI-Only Physical Security Plan License Amendment Approval NG-22-0025, Registration of Independent Spent Fuel Installation Storage Casks2022-03-0808 March 2022 Registration of Independent Spent Fuel Installation Storage Casks IR 05000331/20220012022-03-0404 March 2022 Subject: NRC Inspection Report Nos. 05000331/2022001(DNMS) and 07200032/2022001(DNMS) NG-22-0021, Registration of Independent Spent Fuel Installation Storage Casks2022-02-24024 February 2022 Registration of Independent Spent Fuel Installation Storage Casks ML22007A2722022-02-11011 February 2022 Cover Letter - NRC Duane Arnold Exemption Issuance NG-22-0014, Registration of Independent Spent Fuel Installation Storage Casks2022-02-10010 February 2022 Registration of Independent Spent Fuel Installation Storage Casks ML22028A2822022-02-0303 February 2022 Defueled Physical Security Plan License Amendment Approval ML22033A0802022-02-0202 February 2022 Supplement to License Amendment Request (TSCR-188): Proposed Change to the Physical Security Plan for the Post-Shutdown and Permanently Defueled Condition IR 05000331/20210012022-01-25025 January 2022 NRC Inspection Report Nos. 05000331/2021001(DNMS); 07200032/2021001(DNMS); and 07200032/2021002(DNMS) - Duane Arnold Energy Center ML21172A2172022-01-21021 January 2022 Issuance of License Amendment to Adopt ISFSI-Only Technical Specifications NG-22-0009, Registration of Independent Spent Fuel Installation Storage Casks2022-01-20020 January 2022 Registration of Independent Spent Fuel Installation Storage Casks NG-22-0001, Supplement to Exemption Request for Failed Fuel Can Weight in a Certificate of Compliance 1004 Renewed Amendment 17 61BTH Type 2 Dry Shielded Canister2022-01-0606 January 2022 Supplement to Exemption Request for Failed Fuel Can Weight in a Certificate of Compliance 1004 Renewed Amendment 17 61BTH Type 2 Dry Shielded Canister NG-21-0038, Registration of Independent Spent Fuel Installation Storage Casks2021-12-22022 December 2021 Registration of Independent Spent Fuel Installation Storage Casks NG-21-0035, Supplement to Exemption Request for Failed Fuel Can Weight in a Certificate of Compliance 1004 Renewed Amendment 17 61 Bth Type 2 Dry Shielded Canister2021-12-10010 December 2021 Supplement to Exemption Request for Failed Fuel Can Weight in a Certificate of Compliance 1004 Renewed Amendment 17 61 Bth Type 2 Dry Shielded Canister 2024-01-25
[Table view] Category:License-Operating (New/Renewal/Amendments) DKT 50
MONTHYEARML22111A0332022-05-20020 May 2022 Operating License Page Correction Letter to B. Coffey, Florida Power and Light, from M. Doell ML22028A2822022-02-0303 February 2022 Defueled Physical Security Plan License Amendment Approval ML21067A6422021-05-13013 May 2021 Cyber Security License Amendment Approval ML20219A0882020-08-0707 August 2020 Correction Letter for Amendment No. 312 Removal of License Condition 2.C.(3), Fire Protection Program ML20184A0032020-07-30030 July 2020 Issuance of Amendment No. 312 Removal of License Condition 2.C.(3), Fire Protection Program ML20134J1042020-07-10010 July 2020 Issuance of Amendment No. 311 to Revise Operating License and Technical Specifications for Permanently Defueled Conditions ML20083G0082020-04-29029 April 2020 Issuance of Amendment No. 310 Changes to the Post-Shutdown Emergency Plan for Duane Arnold Energy Center ML19310C2042020-01-0202 January 2020 Issuance of Amendment No. 309 to Align Technical Specifications Staffing and Administrative Requirements ML18292A5662018-11-30030 November 2018 Issuance of Amendment 308 to Upgrade Emergency Action Level Scheme for Duane Arnold Energy Center (DAEC) ML18241A3832018-10-31031 October 2018 Issuance of Amendment 307 to Revise Technical Specifications to Adopt TSTF-551, Revision 3 ML18179A1842018-08-16016 August 2018 Issuance of Amendment 306 to Revise Technical Specification 3.5.1, ECCS-Operating ML18081A0742018-05-0707 May 2018 Correction of Error to Implementation Date Associated with License Amendment No 303 ML18016A6272018-03-0909 March 2018 Issuance of License Amendment No. 304 Revision to Technical Specification 3.1.2, Reactor Anomalies ML18011A0592018-03-0707 March 2018 Issuance of License Amendment No. 303 Revision to Technical Specification Table 3.3.2.1-1, Control Rod Block Instrumentation ML18032A4832018-03-0101 March 2018 Correction of Errors in Safety Evaluation Associated with License Amendment No. 301 ML17212A6462017-10-18018 October 2017 Issuance of Amendment to Modify the Plume Exposure Pathway Emergency Planning Zone Boundary ML17220A0262017-09-21021 September 2017 Issuance of Amendment 301 to Revise Emergency Plan ML17027A0782017-04-0707 April 2017 Issuance of Amendments Regarding Technical Specifications for Inservice Testing Programs (CAC Nos. MF8202 Through MF8209) ML17072A2322017-03-30030 March 2017 Issuance of Amendment to Revise Technical Specifications Fuel Storage Requirements ML16263A2452016-10-17017 October 2016 Issuance of Amendment to Technical Specifications Section 5.5.6 for the Inservice Testing Program ML16211A5142016-09-12012 September 2016 Issuance of Amendment to Revise Technical Specifications 2.1.1.2, Safety Limit Minimum Critical Power Ratio ML16210A0082016-08-30030 August 2016 Issuance of Amendment to Extend Containment Leakage Test Frequency ML16153A0912016-08-18018 August 2016 Issuance of Amendment to Revise the Value of Reactor Steam Dome Pressure ML16180A0862016-07-25025 July 2016 Issuance of Amendment to Revise and Relocate Pressure and Temperature Limit Curves to a Pressure and Temperature Limits Report ML16174A2812016-07-13013 July 2016 Issuance of Amendment (TSCR-154) to Correct Examples in Technical Specifications Section 1.4, Frequency ML15310A0822015-12-22022 December 2015 Issuance of Amendment to Adopt Technical Specifications Task Force (TSTF)-501, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control ML15169A2612015-08-18018 August 2015 Issuance of Amendment Concerning Extension of Cyber Security Plan Milestone 8 Completion Date ML15014A2002015-02-10010 February 2015 Issuance of Amendment to Revise Technical Specifications to Adopt Technical Specifications Task Force - 523 Generic Letter 2008-01, Managing Gas Accumulation (Tac No. MF4358) ML13301A7052013-11-27027 November 2013 Issuance of Amendment Adopting TSTF-535, Revise Shutdown Margin Definition to Address Advanced Fuel Designs. ML13192A4232013-10-0707 October 2013 Issuance of Amendment to Change Renewed Facility Operating License Condition C.12 ML13210A4492013-09-10010 September 2013 Issuance of Amendment Regarding Transition to a Risk-Informed Performance-Based Fire Protection Program in Accordance with 10 CFR 50.48(c) ML13189A0712013-07-25025 July 2013 Issuance of Amendment to Revise Technical Specifications to Adopt TSTF-522 ML12321A2662012-11-28028 November 2012 Issuance of Amendment Revised Cyber Security Plan Implementation Schedule Milestone 6 ML12249A3172012-09-27027 September 2012 Issuance of Amendment One-Time Technical Specification Change Regarding Core Spray Operability During Shutdown ML1219803602012-08-27027 August 2012 Issuance of Amendment Technical Specification Changes Regarding Alternative Testing of Safety/Relief Valves ML12125A3152012-06-0101 June 2012 Issuance of Amendment Concerning Approval of Upgrade of Emergency Action Level Scheme ML1201102822012-02-24024 February 2012 Issuance of Amendment Adoption of Technical Specifications Task Force Traveler (TSTF-425) to Relocate Specific Surveillance Frequencies to a Licensee-Controlled Program ML1115202312011-09-0808 September 2011 Issuance of Amendment Pertaining to Deletion of Decommissioning Funding Parent Guarantee License Condition ML1119402242011-07-29029 July 2011 Issuance of Amendment Pertaining to Cyber Security Plan (TAC No. 4287) ML1104104552011-02-28028 February 2011 Issuance of Amendment Pertaining to Technical Specification Changes to Add LCO 3.0.9 on the Unavailability of Barriers (TSTF-427) ML1029305862010-12-16016 December 2010 Nextera Energy Duane Arnold, LLC Central Iowa Power Cooperative Corn Belt Power Cooperative, Duane Arnold Energy Center Renewed Facility Operating License ML0530503092010-12-16016 December 2010 Current Facility Operating License DPR-49, Tech Specs, Revised 03/17/2018 ML1029305242010-12-16016 December 2010 Issuance of Renewed Facility Operating License No. DPR-49 for Duane Arnold Energy ML1006211692010-03-31031 March 2010 License Amendment, Issuance of Amendment Pertaining to Changes to Technical Specifications 5.5.12 (Primary Containment Leakage Rate Testing Program) & 3.6.1.3 (Primary Containment Isolation Values), Associated with Main .. ML0930301132009-11-13013 November 2009 Issuance of Amendment Pertaining to Name Chance of Licensee and Co-Owner ML0919003812009-09-18018 September 2009 Issuance of Amendment Pertaining to Adoption of TSTF-511, Revision 0, Eliminate Working Hour Restrictions from Technical Specification 5.2.2 to Support Compliance with 10 CFR Part 26. ML0912605512009-05-15015 May 2009 License Amendment, Revision of the 4160 Volt Bus Undervoltage (Degraded Voltage) Maximum Allowed Value ML0831901082008-12-0303 December 2008 License Amendment, Issuance of Amendment to Change Surveillance Requirements of the Cedar River Depth to Assure Ultimate Heat Sink Operability ML0826908352008-11-0606 November 2008 Issuance of License Amendment Regarding Control Rod Notch Testing Frequency and Clarification of a Frequency Example ML0822601162008-09-0909 September 2008 Issuance of Amendment Regarding License Amendment Request to Remove the Emergency Diesel Generator Surveillance Requirement for Preplanned Preventive Maintenance and Testing 2022-05-20
[Table view] Category:Safety Evaluation
MONTHYEARML22132A2872022-05-24024 May 2022 ISFSI DQAP Approval Letter ML22089A0492022-05-12012 May 2022 Sfmp Review Letter ML22066A7632022-04-25025 April 2022 ISFSI-Only Emergency Plan License Amendment Approval ML22028A2822022-02-0303 February 2022 Defueled Physical Security Plan License Amendment Approval ML21067A6422021-05-13013 May 2021 Cyber Security License Amendment Approval ML21098A1662021-04-28028 April 2021 PDEP and EAL License Amendment Approval ML21097A1412021-04-13013 April 2021 EP Exemption Issuance Letter and SE ML20225A0002020-08-27027 August 2020 Approval of Quality Assurance Topical Report (FPL-3), Revision 0 (EPID-L-2020-LLQ-0002) ML20184A0032020-07-30030 July 2020 Issuance of Amendment No. 312 Removal of License Condition 2.C.(3), Fire Protection Program ML20134J1042020-07-10010 July 2020 Issuance of Amendment No. 311 to Revise Operating License and Technical Specifications for Permanently Defueled Conditions ML20083G0082020-04-29029 April 2020 Issuance of Amendment No. 310 Changes to the Post-Shutdown Emergency Plan for Duane Arnold Energy Center ML20015A1232020-02-0606 February 2020 Proposed Alternative to Use Encoded Phased Array Ultrasonic Examination Techniques ML19310C2042020-01-0202 January 2020 Issuance of Amendment No. 309 to Align Technical Specifications Staffing and Administrative Requirements ML19204A2872019-08-28028 August 2019 Approval of a Certified Fuel Handler Training and Retraining Program ML19198A0102019-07-23023 July 2019 Approval of Change in the BWRVIP Integrated Surveillance Program Capsule Test Schedule to Accommodate Early Closure ML19168A1302019-06-21021 June 2019 Safety Evaluation Regarding Implementation of Hardened Containment Vents Capable of Operation Under Severe Accident Conditions Related to Order EA-13-109 (CAC No. MF4391; EPID No. L-2014-JLD-0039) ML18292A5662018-11-30030 November 2018 Issuance of Amendment 308 to Upgrade Emergency Action Level Scheme for Duane Arnold Energy Center (DAEC) ML18241A3832018-10-31031 October 2018 Issuance of Amendment 307 to Revise Technical Specifications to Adopt TSTF-551, Revision 3 ML18179A1842018-08-16016 August 2018 Issuance of Amendment 306 to Revise Technical Specification 3.5.1, ECCS-Operating ML18192C1832018-07-24024 July 2018 Fifth 10-Year Inservice Relief Request RR-05 ML18145A1942018-06-15015 June 2018 Relief Request No. NDE R017 Fourth Inservice Inspection Interval Duane Arnold Energycenter (EPID-L-2017-LLR-0135) ML18106B1212018-04-25025 April 2018 Proposed Alternative to Use Encoded Phased Array Ultrasonic Examination Techniques ML18053A2092018-04-16016 April 2018 Request for Relief No. 03 Proposed Use of Alternative Requirements for Nozzle Inner Radius and Nozzle-to-Shell Weld Inspection for Fifth Inservice Inspection Interval (CAC No. MF9374; EPID L-2017-LLR-0110) ML18016A6272018-03-0909 March 2018 Issuance of License Amendment No. 304 Revision to Technical Specification 3.1.2, Reactor Anomalies ML18011A0592018-03-0707 March 2018 Issuance of License Amendment No. 303 Revision to Technical Specification Table 3.3.2.1-1, Control Rod Block Instrumentation ML17353A6822018-01-19019 January 2018 Request for Relief No. RR 01, Regarding Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds for the Renewed Operating License Term ML17347A1112018-01-17017 January 2018 Safety Evaluation for Request for Relief from Seal Weld Procedure Qualification, Relief Request No. RR-04 ML17272A0182017-12-19019 December 2017 Relief Request No. RR-02- Proposed Alternative to ASME Code Examination Requirements for Buried Piping Related to Fifth Inservice Inspection Interval Program Plan ML17212A6462017-10-18018 October 2017 Issuance of Amendment to Modify the Plume Exposure Pathway Emergency Planning Zone Boundary ML17220A0262017-09-21021 September 2017 Issuance of Amendment 301 to Revise Emergency Plan ML17129A0372017-05-26026 May 2017 Safety Evaluation Regarding Implementation of Mitigation Strategies and Reliable Spent Fuel Pool Instrument Related to Orders EA-12-049 and EA-12-051 ML17027A0782017-04-0707 April 2017 Issuance of Amendments Regarding Technical Specifications for Inservice Testing Programs (CAC Nos. MF8202 Through MF8209) ML17072A2322017-03-30030 March 2017 Issuance of Amendment to Revise Technical Specifications Fuel Storage Requirements ML16313A4752016-11-30030 November 2016 Correction of Errors in Safety Evaluation Associated with License Amendment No. 298 ML16263A2452016-10-17017 October 2016 Issuance of Amendment to Technical Specifications Section 5.5.6 for the Inservice Testing Program ML16211A5142016-09-12012 September 2016 Issuance of Amendment to Revise Technical Specifications 2.1.1.2, Safety Limit Minimum Critical Power Ratio ML16210A0082016-08-30030 August 2016 Issuance of Amendment to Extend Containment Leakage Test Frequency ML16153A0912016-08-18018 August 2016 Issuance of Amendment to Revise the Value of Reactor Steam Dome Pressure ML16180A0862016-07-25025 July 2016 Issuance of Amendment to Revise and Relocate Pressure and Temperature Limit Curves to a Pressure and Temperature Limits Report ML16174A2812016-07-13013 July 2016 Issuance of Amendment (TSCR-154) to Correct Examples in Technical Specifications Section 1.4, Frequency ML16053A4262016-04-29029 April 2016 Correction of Typographical Errors in Safety Evaluation Associated with License Amendment No. 292 ML16008A0862016-01-21021 January 2016 Relief Request No. PR-01, PR-02, VR-01, VR-02, and VR-03 Related to the Inservice Testing Program for the Fifth 10-Year Interval ML15310A0822015-12-22022 December 2015 Issuance of Amendment to Adopt Technical Specifications Task Force (TSTF)-501, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control ML15169A2612015-08-18018 August 2015 Issuance of Amendment Concerning Extension of Cyber Security Plan Milestone 8 Completion Date ML15014A2002015-02-10010 February 2015 Issuance of Amendment to Revise Technical Specifications to Adopt Technical Specifications Task Force - 523 Generic Letter 2008-01, Managing Gas Accumulation (Tac No. MF4358) ML14144A0022014-06-0909 June 2014 Relief Request No. VR-03 Related to the Inservice Testing Program for the Fourth 10-Year Interval ML14099A3352014-04-29029 April 2014 Relief for 2nd Period Limited Weld Examinations ML13301A7052013-11-27027 November 2013 Issuance of Amendment Adopting TSTF-535, Revise Shutdown Margin Definition to Address Advanced Fuel Designs. ML13323B4432013-11-26026 November 2013 Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation ML13192A4232013-10-0707 October 2013 Issuance of Amendment to Change Renewed Facility Operating License Condition C.12 2022-05-24
[Table view] |
Text
November 27, 2006 Mr. Gary Van Middlesworth Vice President Duane Arnold Energy Center 3277 DAEC Road Palo, Iowa 52324-9785
SUBJECT:
DUANE ARNOLD ENERGY CENTER - ISSUANCE OF AMENDMENT REGARDING REVISION TO THE REACTOR PRESSURE VESSEL MATERIAL SURVEILLANCE PROGRAM (TAC NO. MC9313)
Dear Mr. Van Middlesworth:
The U.S. Nuclear Regulatory Commission has issued the enclosed Amendment No.262 to Facility Operating License No. DPR-49 for the Duane Arnold Energy Center (DAEC). This amendment revises the DAEC licensing basis, as described in the Updated Final Safety Analysis Report (UFSAR), to replace the current plant-specific reactor pressure vessel material surveillance program with the Boiling Water Reactor Vessel and Internals Project Integrated Surveillance Program as the basis for demonstrating compliance with the requirements of Appendix H to Part 50 of Title 10 of the Code of Federal Regulations, Reactor Vessel Material Surveillance Program Requirements.
The changes to the DAEC UFSAR shall be as stated in the Nuclear Management Company, LLC (NMC, the former licensee) application dated December 22, 2005. Amendment No. 260, issued on January 27, 2006, transferred the DAEC license from NMC to FPL Energy Duane Arnold, LLC (FPL Energy). By letter dated February 6, 2006, FPL Energy adopted all previous docketed requests before the NRC for review and approval.
A copy of the Safety Evaluation is also enclosed. A Notice of Issuance will be included in the Commission's next biweekly Federal Register notice.
Sincerely,
/RA/
Richard B. Ennis, Senior Project Manager Plant Licensing Branch III-1 Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-331
Enclosures:
- 1. Amendment No. 262 to License No. DPR-49
- 2. Safety Evaluation cc w/encls: See next page
ML062830019 OFFICE LPL3-1/PM LPL3-1/PM LPL3-1/LA SBWB/BC CVIB/BC OGC LPL3-1/BC NAME KFeintuch REnnis THarris GCranston MMitchell TCampbell LRaghavan DATE 10/30/06 10/24/06 10/31/06 10/31/06 11/14/06 11/22/06 11/27/06 Duane Arnold Energy Center cc:
Mr. J. A. Stall Mr. M. Warner Senior Vice President, Nuclear and Chief Vice President, Nuclear Operations Nuclear Officer Support Florida Power & Light Company Florida Power & Light Company P. O. Box 14000 P. O. Box 14000 Juno Beach, FL 33408-0420 Juno Beach, FL 33408-0420 Mr. M. S. Ross Mr. D. A. Curtland Managing Attorney Plant Manager Florida Power & Light Company Duane Arnold Energy Center P. O. Box 14000 3277 DAEC Rd.
Juno Beach, FL 33408-0420 Palo, IA 52324-9785 Mr. R. E. Helfrich Mr. R. S. Kundalkar Senior Attorney Vice President, Nuclear Engineering Florida Power & Light Company Florida Power & Light Company P. O. Box 14000 P. O. Box 14000 Juno Beach, FL 33408-0420 Juno Beach, FL 33408-0420 Mr. W. E. Webster Daniel K. McGhee Vice President, Nuclear Operations Iowa Department of Public Health Florida Power & Light Company Bureau of Radiological Health P. O. Box 14000 321 East 12th Street Juno Beach, FL 33408-0420 Lucas State Office Building, 5th Floor Des Moines, IA 50319-0075 John Bjorseth Site Director Chairman, Linn County Duane Arnold Energy Center Board of Supervisors 3277 DAEC Road 930 1st Street SW Palo, IA 52324 Cedar Rapids, IA 52404 Steven R. Catron Manager, Regulatory Affairs Duane Arnold Energy Center 3277 DAEC Road Palo, IA 52324 U. S. Nuclear Regulatory Commission Resident Inspectors Office Rural Route #1 Palo, IA 52324 Regional Administrator, Region III U.S. Nuclear Regulatory Commission Suite 210 2443 Warrenville Road Lisle, IL 60532-4351 October 12, 2006
FPL ENERGY DUANE ARNOLD, LLC DOCKET NO. 50-331 DUANE ARNOLD ENERGY CENTER AMENDMENT TO FACILITY OPERATING LICENSE Amendment No. 262 License No. DPR-49
- 1. The U.S. Nuclear Regulatory Commission (the Commission) has found that:
A. The application for amendment by Nuclear Management Company, LLC1 dated December 22, 2005, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's rules and regulations set forth in 10 CFR Chapter I; B. The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D. The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.
1 The application was submitted by Nuclear Management Company, LLC (NMC, the former licensee). Amendment No. 260, issued on January 27, 2006, transferred license DPR-49 from NMC to FPL Energy Duane Arnold, LLC (FPL Energy, the current licensee). By letter dated February 6, 2006, FPL Energy adopted all previous docketed requests before the NRC for review and approval.
- 2. Accordingly, the license is amended to authorize changes to the Updated Final Safety Analysis Report (UFSAR) to allow implementation of the Boiling Water Reactor Vessel and Internals Project Integrated Surveillance Program as the basis for demonstrating complance with Appendix H to 10 CFR Part 50, Reactor Vessel Material Surveillance Program Requirements. The changes to the UFSAR shall be as set forth in Exhibit B to the licensees application dated December 22, 2005.
- 3. This license amendment is effective as of its date of issuance and shall be implemented within 90 days of the date of issuance. Implementation of the amendment is the incorporation into the UFSAR of the program description set forth in the licensees application dated December 22, 2005, and evaluated in the Safety Evaluation enclosed with this amendment. The licensee shall submit the changes authorized by this amendment with the next update of the UFSAR in accordance with 10 CFR 50.71(e).
FOR THE NUCLEAR REGULATORY COMMISSION
/RA/
L. Raghavan, Chief Plant Licensing Branch III-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Date of Issuance: November 27, 2006
SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO AMENDMENT NO. 262 TO FACILITY OPERATING LICENSE NO. DPR-49 FPL ENERGY DUANE ARNOLD, LLC DUANE ARNOLD ENERGY CENTER DOCKET NO. 50-331
1.0 INTRODUCTION
By letter dated December 22, 2005 (Reference 1), Nuclear Management Company, LLC (NMC, the former licensee) requested a license amendment to revise the Updated Final Safety Analysis Report (UFSAR) for the Duane Arnold Energy Center (DAEC). Amendment No. 260, issued on January 27, 2006, transferred the DAEC license from NMC to FPL Energy Duane Arnold, LLC (FPL Energy, the current licensee). By letter dated February 6, 2006, FPL Energy adopted all previous docketed requests before the NRC for review and approval.
The proposed amendment would revise the DAEC licensing basis to replace the current plant-specific reactor pressure vessel (RPV) material surveillance program with the Boiling Water Reactor Vessel and Internals Project (BWRVIP) Integrated Surveillance Program (ISP) as the basis for demonstrating compliance with the requirements of Appendix H to Part 50 of Title 10 of the Code of Federal Regulations, (10 CFR Part 50, Appendix H), Reactor Vessel Material Surveillance Program Requirements.
The BWRVIP ISP was submitted for Nuclear Regulatory Commission (NRC) staff review and approval in Topical Reports BWRVIP-78, BWR Vessel and Internals Project, BWR Integrated Surveillance Program Plan, and BWRVIP-86, BWR Vessel and Internals Project, BWR Integrated Surveillance Program Implementation Plan, (References 2 and 3). Additional information necessary to establish the technical basis for, and proposed implementation of, the BWRVIP ISP was provided in letters from the BWRVIP to the NRC dated December 15, 2000, and May 30, 2001, (References 4 and 5). The NRC staff approved the proposed BWRVIP ISP in a safety evaluation (SE), which was provided to the BWRVIP by letter dated February 1, 2002 (Reference 6). However, the NRC staffs SE specified that certain plant-specific information must be provided by BWR licensees who wish to implement the BWRVIP ISP for their facilities. The licensees December 22, 2005, submittal, addressed the plant-specific information specified in the NRC staffs February 1, 2002, BWRVIP ISP SE.
2.0 REGULATORY REQUIREMENTS The NRC staff determined that the December 22, 2005, submittal, identified the applicable regulatory requirements. The regulatory requirements for which the NRC staff based its review are described below.
Appendix H of 10 CFR Part 50, requires nuclear power plant licensees to implement RPV surveillance programs to monitor changes in the fracture toughness properties of ferritic
materials in the reactor vessel beltline region...which result from exposure of these materials to neutron irradiation and the thermal environment. Two specific alternatives are provided with regard to the design of a facilitys RPV surveillance program which may be used to address the requirements of 10 CFR Part 50, Appendix H.
The first alternative is the implementation of a plant-specific RPV surveillance program consistent with the requirements of American Society for Testing and Materials (ASTM)
Standard Practice E-185, Standard Practice for Conducting Surveillance Tests for Light-Water Cooled Nuclear Power Reactor Vessels. In the design of a plant-specific RPV surveillance program, a licensee may use the edition of ASTM Standard Practice E-185 which was current on the issue date of the American Society of Mechanical Engineers Code to which the reactor vessel was purchased, or later editions through the 1982 Edition.
The second alternative provided in 10 CFR Part 50, Appendix H, is the implementation of an ISP. An ISP is defined in 10 CFR Part 50, Appendix H as occurring when, the representative materials chosen for surveillance for a reactor are irradiated in one or more other reactors that have similar design and operating features. Five specific criteria are stated in Appendix H to 10 CFR Part 50 which must be met to support approval of an ISP:
- a. The reactor in which the materials will be irradiated and the reactor for which the materials are being irradiated must have sufficiently similar design and operating features to permit accurate comparisons of the predicted amount of radiation damage.
- b. Each reactor must have an adequate dosimetry program.
- c. There must be adequate arrangement for data sharing between plants.
- d. There must be a contingency plan to assure that the surveillance program for each reactor will not be jeopardized by operation at reduced power level or by an extended outage of another reactor from which data are expected.
- e. There must be substantial advantages to be gained, such as reduced power outages or reduced personnel exposure to radiation, as a direct result of not requiring surveillance capsules in all reactors in the set.
As noted above in Section 1.0, the NRC staff approved the proposed BWRVIP ISP in an SE issued to the BWRVIP by letter dated February 1, 2002. In Reference 6, all of the criteria cited above for approval of an ISP were addressed either completely or partially. For those criteria which could not be fully addressed in Reference 6, plant-specific information was needed.
The NRC staff identified in Reference 6 the specific information which would be needed from licensees who wished to implement the BWRVIP for their facilities. As stated in Reference 6:
[L]icensees who wish to participate in the BWR ISP must provide, for NRC staff review and approval, information which defines how they will determine RPV and/or surveillance capsule fluences based on the dosimetry data which will be available for their facilities. This information must be submitted concurrently with each licensees submittal to replace their existing plant-specific surveillance program with the BWR ISP as part of their facilitys licensing basis.
The information submitted must be sufficient for the staff to determine that:
(1) RPV and surveillance capsule fluences will be established as based on the use of an NRC-approved fluence methodology that will provide acceptable results based on the available dosimetry data; and (2) If one methodology is used to determine the neutron fluence values for a licensees RPV and one or more different methodologies are used to establish the neutron fluence values for the ISP surveillance capsules which represent that RPV in the ISP, the results of these differing methodologies are compatible (i.e., are within each others levels of uncertainty).
This plant-specific information is required by the NRC staff in order to ensure that Criterion III.C.1.b of 10 CFR Part 50, Appendix H, for an ISP could be met by each facility and to confirm that data which would be shared as part of the BWRVIP ISP could be effectively utilized by each licensee for the monitoring of RPV embrittlement for their facility.
Regulatory Guide (RG) 1.190, Calculational and Dosimetry Methods For Determining Pressure Vessel Neutron Fluence, describes methods and assumptions acceptable to the NRC staff for determining the pressure vessel neutron fluence. The guide is intended to ensure the accuracy and reliability of the fluence determination required by General Design Criteria 14, 30, and 31 of Appendix A, General Design Criteria for Nuclear Power Plants, to 10 CFR Part 50.
3.0 TECHNICAL EVALUATION
The December 22, 2005, submittal for DAEC contained information which addressed the plant-specific information requested in the NRC staffs SE approving the BWRVIP ISP. The licensee proposed to change Section 5.3 of the DAEC UFSAR to include the following information:
A neutron fluence calculation methodology which has been approved by the NRC staff and conforms with U.S. Nuclear Regulatory Commission Regulatory Guide 1.190, Calculational and Dosimetry Methods for Determining Pressure Vessel Neutron Fluence, will be used for the determination of neutron fluence values for the DAEC.
RG 1.190 was developed to provide state-of-the-art calculations and measurement procedures, which are acceptable to the NRC staff for determining pressure vessel fluence. Although the NRC staff would note that the guidance in RG 1.190 is not a regulatory requirement of the NRC, the staff has concluded that the inclusion of this statement in the DAEC UFSAR is
sufficient to address both items (1) and (2) from Reference 6. Regarding item (1), the licensees use of a methodology for determining the DAEC RPV neutron fluence values which is consistent with the attributes of RG 1.190 and has been approved by the NRC staff will provide acceptable results based upon the available dosimetry data. Regarding item (2), RPV surveillance capsules tested under the BWRVIP ISP will have their fluences determined by the use of a methodology which is consistent with the attributes of RG 1.190 and has been approved by the NRC staff. The NRC staff has concluded that any two (or more) different fluence methodologies will provide compatible (as defined in Reference 6) results provided that the best estimate fluence values are within each others uncertainty bounds.
In addition, proposed Section 5.3 of the DAEC UFSAR contained the revised surveillance capsule withdrawal schedule for DAEC. The withdrawal schedule was revised to state that future withdrawal of surveillance capsules will be conducted in accordance with the NRC staff-approved BWRVIP ISP. The proposed UFSAR revision would include the following supplemental paragraph addressing their implementation of the BWRVIP ISP:
The program for implementation of the scheduling, withdrawal, and testing of the material surveillance specimens is governed and controlled by...BWRVIP-78,...BWRVIP-86,... NRC letter dated December 15, 2000, Project No, 704 -
BWRVIP Response to NRC Request for Additional Information Regarding BWRVIP-78, NRC letter dated May 30, 2001, Project No. 704 - BWRVIP Response to Second NRC Request for Additional Information on the BWR Integrated Surveillance Program, and the NRC Safety Evaluation which approved BWRVIP-78 and BWRVIP-86. The BWRVIP...ISP complies with the requirements of 10 CFR [Part] 50, Appendix H. The [surveillance] specimens will be pulled in accordance with the test matrix included in BWRVIP-86, as modified by the NRCs safety evaluation.
The licensee also proposed changes to Section 5.3 of the DAEC UFSAR with references for the documents discussed above.
Based on the above considerations, the NRC staff has determined that the proposed revisions to the DAEC UFSAR adequately document the licensees intent to appropriately implement the NRC staff-approved BWRVIP ISP as the method for demonstrating compliance with the requirements of 10 CFR Part 50, Appendix H. Therefore, the licensee is authorized to revise the UFSAR for DAEC, to allow implementation of the BWRVIP ISP as the basis for demonstrating compliance with the requirements of 10 CFR Part 50, Appendix H. As part of the implementation of this amendment and documentation of the licensees intent to utilize the BWRVIP ISP for this purpose, the licensee shall modify the DAEC UFSAR as stated in the December 22, 2005, submittal. The DAEC UFSAR is controlled in accordance with the requirements of 10 CFR 50.59, Changes, tests, and experiments.
4.0 STATE CONSULTATION
In accordance with the Commissions regulations, the Iowa State official was notified of the proposed issuance of the amendment. The State official had no comments.
5.0 ENVIRONMENTAL CONSIDERATION
S The amendment changes a requirement with respect to installation or use of a facility component located within the restricted area as defined in 10 CFR Part 20. The NRC staff has determined that the amendment involves no significant increase in amounts, and no significant change in the types of any effluents that may be released offsite, and that there is no significant increase in individual or cumulative occupational radiation exposure. The Commission has previously issued a proposed finding that the amendment involves no significant hazards consideration, and there has been no public comment on such finding (71 FR 43533).
Accordingly, the amendment meets the eligibility criteria for categorical exclusion set forth in 10 CFR 51.22(c)(9). Pursuant to 10 CFR 51.22(b), no environmental impact statement or environmental assessment need be prepared in connection with the issuance of the amendment.
6.0 CONCLUSION
The Commission has concluded, based on the considerations discussed above, that: (1) there is reasonable assurance that the health and safety of the public will not be endangered by operation in the proposed manner, (2) such activities will be conducted in compliance with the Commissions regulations, and (3) the issuance of the amendment will not be inimical to the common defense and security or to the health and safety of the public.
7.0 REFERENCES
- 1. G. Van Middlesworth, Nuclear Management Company, LLC, to U.S. NRC Document Control Desk, License Amendment Request Pursuant to 10 CFR 50.90: Revision to the Duane Arnold Energy Center Reactor Pressure Vessel Material Surveillance Program, December 22, 2005
- 2. C. Terry, BWRVIP, to U.S. NRC Document Control Desk, Project No. 704 - BWR Vessel and Internals Project, BWR Integrated Surveillance Program Plan (BWRVIP-78), December 22, 1999.
- 3. C. Terry, BWRVIP, to U.S. NRC Document Control Desk, Project No. 704 -
BWRVIP-86: BWR Vessel and Internals Project, BWR Integrated Surveillance Program Implementation Plan, [Electric Power Research Institute] EPRI Technical Report 1000888, December 22, 2000.
- 4. C. Terry, BWRVIP, to U.S. NRC Document Control Desk, Project No. 704 - BWRVIP Response to NRC Request for Additional Information Regarding BWRVIP-78, December 15, 2000.
- 5. C. Terry, BWRVIP, to U.S. NRC Document Control Desk, Project No. 704 - BWRVIP Response to Second NRC Request for Additional Information on the BWR Integrated Surveillance Program, May 30, 2001.
- 6. W. H. Bateman, NRC, to C. Terry, BWRVIP, Safety Evaluation Regarding EPRI Proprietary Reports BWR Vessel and Internals Project, BWR Integrated Surveillance Program Plan (BWRVIP-78) and BWRVIP-86: BWR Vessel and Internals Project, BWR Integrated Surveillance Program Implementation Plan, February 1, 2002.
Principal Contributors: C. Sydnor K. Feintuch R. Ennis Date: November 27, 2006