NRC Annual Assessment Meeting
ML061240414
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 05/02/2006
From:
FirstEnergy Nuclear Operating Co
To:
Office of Nuclear Reactor Regulation
References
Download: ML061240414 (6)


Text

NRC Annual Assessment Meeting Davis-Besse Nuclear Power Station May 2, 2006

Participants Q Mark Bezilla - Site Vice President Q Barry Allen - Director, Site Operations Q Bob Schrauder - Director, Performance Improvement Davis-Besse Nuclear Power Station 2

2005 Accomplishments Safe, reliable and eventless operation Union Negotiations (Local 245)

Replenishment (hiring for select needs - e.g., Maintenance/Engineering/Operations)

Steam Generator Inspection/Midcycle Outage Technical Programs INPO Accreditation Renewal NRC/FEMA Evaluated Emergency Plan Exercise 2005 Licensed Operator Candidate Exams INPO Evaluation and Assessment Operator Programs INPO Accreditation Renewal Confirmatory Order independent Assessments (Operations, Engineering, CAP, SC/SCWE)

Cycle 14 Operational Improvement Activities Security Force on Force Inspection 2005-2007 Business Plan 14th Refueling Outage Preps Backlog Reduction - PM /CM/Elective Maintenance/Procedure Change Requests/Condition Report Evaluations and actions/other miscellaneous items - (toward steady state values)

Davis-Besse Nuclear Power Station 3

14th Refueling Outage utage Key Activities RCP (2-1, 2-2) Replacement Core Reload (new fuel design)

Steam Generator Inspections Reactor Vessel Head & Bottom Inspection Turbine Low Pressure Rotor Replacement Service Water System Improvements CAC/SW Water Hammer Issue Resolution Small Bore Piping Support Improvements EDG Voltage Regulator Replacement hallenges RCP 2-1, 2-2 overhaul Overlay weld on RCP 1-1 cold leg drain line Davis-Besse Nuclear Power Station 4

Q Safe, secure, reliable, and eventless operation Q Operations Programs INPO Accreditation Renewal (January)

Q 14th Refueling Outage (March/April)

Q Emergency Preparedness Drills Q Backlog Reductions

- Achieve steady state values Q INPO Mid-Cycle Evaluation (October)

Q Confirmatory Order Independent Assessments

- Operations Performance (June)

- Corrective Action Program Implementation (August)

- Engineering Programs (September)

- Safety Culture/Safety Conscious Work Environment (November)

Q Workforce Replenishment Q Human Performance Initiatives Q 15th Refueling Outage Preparation (Spring 2008)

Q 2006-2010 Business Plan Activities Davis-Besse Nuclear Power Station 5

Looking Forward Safe Plant Operations Reliable Plant Operations Cost-Effective Plant Operations Through effective use of People, Processes and Procedures Davis-Besse Nuclear Power Station 6