Similar Documents at Cook |
---|
Category:Inspection Plan
MONTHYEARML23310A1152023-11-0606 November 2023 Notification of the NRC Baseline Inspection and Request for Information, Inspection Report 05000316/2024002 ML23242A1832023-08-30030 August 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report05000315/2023004 ML23131A3282023-05-11011 May 2023 D.C. Cook Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000315/2023404 and 05000316/2023404 ML23076A0212023-03-20020 March 2023 Request for Information for NRC Commercial Grade Dedication Inspection; Inspection Report 05000315/2023011; 05000316/2023011 ML23066A1882023-03-0707 March 2023 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Donald C. Cook Nuclear Plant IR 05000315/20220062023-03-0101 March 2023 Annual Assessment Letter for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2022006 and 05000316/2022006) IR 05000315/20220052022-08-24024 August 2022 Updated Inspection Plan for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2022005 and 05000316/2022005) ML22130A1722022-05-11011 May 2022 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection IR 05000315/20210062022-03-0202 March 2022 Annual Assessment Letter for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2021006 and 05000316/2021006) ML21309A3322021-11-0505 November 2021 Notification of Nrc Fire Protection Team Inspection Request for Information IR 05000315/20210052021-09-0101 September 2021 Updated Inspection Plan for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2021005 and 05000316/2021005) ML21146A2862021-05-26026 May 2021 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Donald C. Cook Nuclear Plant ML21068A3512021-03-0909 March 2021 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000315/2021002; 05000316/2021002 IR 05000315/20200062021-03-0404 March 2021 Annual Assessment Letter for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2020006 and 05000316/2020006) ML21012A0592021-01-12012 January 2021 Information Request for the Cyber-Seruity Full Implementation Inspection, Notification to Perform Inspection 05000315/2021401; 05000316/2021401 IR 05000315/20200112020-09-17017 September 2020 Information Request to Support Upcoming Temporary Instruction 2515/194 Inspection; Inspection Report 05000315/2020011; 05000316/2020011 IR 05000315/20200052020-09-0101 September 2020 Updated Inspection Plan for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2020005 and 05000316/2020005) ML20133J9722020-05-14014 May 2020 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection IR 05000315/20200202020-04-10010 April 2020 Units 1 and 2 - Information Request for NRC Triennial Evaluation of Changes, Tests, and Experiments (50.59) Baseline Inspection 05000315/2020020 and 05000316/2020020 IR 05000315/20190062020-03-0303 March 2020 Annual Assessment Letter for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2019006 and 05000316/2019006) ML20016A3842020-01-16016 January 2020 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information IR 05000315/20204102019-11-19019 November 2019 Information Request for the Cyber Security Full Implementation Inspection, Notification to Perform Inspection 05000315/2020410; 05000316/2020410 IR 05000315/20190052019-08-28028 August 2019 Updated Inspection Plan for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2019005 and 05000316/2019005) ML19192A1552019-07-11011 July 2019 Ltr. 07/11/19 Donald C. Cook Nuclear Power Plant, Unit 2 - Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000315/2019004; 05000316/2019004 (DRS-M.Holmberg) ML19128A3482019-05-0808 May 2019 Ltr. 05/08/19 Donald C. Cook Nuclear Power Plant, Units 1 and 2 - Notification of NRC Triennial Fire Protection Baseline Inspection Request for Information; Inspection Report 05000315/2019012; 05000316/2019012 (DRS-A.Shaikh) ML19078A3732019-03-19019 March 2019 Information Request to Support Upcoming Problem Identification and Resolution Inspection at the Donald C. Cook Nuclear Power Plant, Units 1 and 2 IR 05000315/20180062019-03-0404 March 2019 Annual Assessment Letter for Donald C. Cook Nuclear Power Plant, Units 1 and 2 (Report 05000315/2018006 and 05000316/2018006) ML19037A3842019-02-0404 February 2019 Ltr. 02/04/19 Donald C. Cook Nuclear Power Plant, Unit 1 - Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000315/2019001; 05000316/2019001 (DRS-E.Fernandez) IR 05000315/20180052018-08-28028 August 2018 Updated Inspection Plan for Donald C. Cook Nuclear Power Plant, Units 1 and 2 (Report 05000315/2018005 and 05000316/2018005) IR 05000315/20170062018-03-0202 March 2018 Annual Assessment Letter for Donald C. Cook Nuclear Power Plant, Units 1 and 2 (Report 05000315/2017006; 05000316/2017006) ML18058B6192018-02-27027 February 2018 Inspection Plan for Donald C. Cook, Unit 2, for Inservice Inspection Activities; Inspection Report 05000316/2018002 (DRS-L.Smith) IR 05000315/20170052017-08-28028 August 2017 Updated Inspection Plan for Donald C. Cook Nuclear Power Plant, Units 1 and 2 (Report 05000315/2017005; 05000316/2017005) ML17076A3592017-03-17017 March 2017 Notification of an NRC Triennial Heat Sink Performance Inspection and Request for Information; Inspection Report 05000315/2017002; 05000316/2017002 (Lnr) IR 05000315/20160062017-03-0101 March 2017 Annual Assessment Letter for Donald C. Cook Nuclear Power Plant, Units 1 and 2 (Report 05000315/2016006; 05000316/2016006) IR 05000315/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Donald C. Cook Nuclear Power Plant, Units 1 and 2 (Report 05000315/2016005; 05000316/2016005) ML16211A0322016-07-28028 July 2016 Request for Inforamtion for an NRC Post-Approval Site Inspection for License Renewal Inspection Report 05000316/2016010 IR 05000315/20150062016-03-0202 March 2016 Annual Assessment Letter for Donald C. Cook Nuclear Power Plant, Units 1 and 2(Report 05000315/2015006 and 05000316/2015006) ML16013A1832016-01-12012 January 2016 Notification of NRC Inspection and Request for Information (Jen) IR 05000315/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Donald C. Cook Nuclear Power Plant, Units 1 and 2 (Report 05000315/2015005; 05000316/2015005) IR 05000315/20140012015-03-0404 March 2015 Annual Assessment Letter for Donald C. Cook Nuclear Power Plant, Units 1 and 2, (Report 05000315/2014001 and 05000316/2014001) ML14317A5892014-11-13013 November 2014 Notification of NRC Triennial Heat Sink Performance Inspection and Request for Information Inspection 05000315/2015002; 05000316/2015002 ML14245A2562014-09-0202 September 2014 Mid-Cycle Assessment Letter for Donald C. Cook Nuclear Power Plant, Units 1 and 2 IR 05000316/20130012014-03-0404 March 2014 Annual Assessment Letter for Donald C. Cook Nuclear Power Plant, Unit 1 and 2 (Report 05000351/2013001; 05000316/2013001) ML14024A4762014-01-23023 January 2014 Information Request for a NRC Post-Approval Site Inspection for License Renewal 05000315-14-007 ML13246A2272013-09-0303 September 2013 2013 Donald C. Cook Mid-Cycle Letter Combined IR 05000315/20120012013-03-0404 March 2013 Annual Assessment Letter for D.C. Cook Nuclear Power Plant, Units 1 and 2, (Report 05000315/2012001 and 05000316/2012001) ML13032A5182013-02-0101 February 2013 IR 05000315-13-009 & 05000316-13-009, on 05/28-29/2013, 05/29-31/2013, 06/10-14/2013, & 06/24-28/2013, Donald C. Cook, Units 1 & 2- Notification to Perform a Triennial Fire Protection Baseline Inspection While Transition to 10 CFR 50.48(C). ML12248A3012012-09-0404 September 2012 Mid-Cycle Assessment Letter for Donald C. Cook Nuclear Power Plant Units 1 and 2 ML12235A2462012-08-21021 August 2012 IR 05000315-12-005 & 05000316-12-005, 11/26-30/2012, D.C. Cook Nuclear Power Plant, Units 1 & 2 - Notification of an NRC Triennial Heat Sink Performance & Review of Implementation of Industry Initiative to Control Degradation of Underground IR 05000315/20110072012-03-0505 March 2012 Annual Assessment Letter for D.C. Cook Nuclear Power Plant, Units 1 and 2 (Report 05000315/2011007 and 05000316/2011007) 2023-08-30
[Table view] Category:Letter
MONTHYEARIR 05000315/20230042024-01-31031 January 2024 Integrated Inspection Report 05000315/2023004 and 05000316/2023004 ML24004A1582024-01-19019 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0039 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) AEP-NRC-2024-01, Emergency Plan Revision 482024-01-0808 January 2024 Emergency Plan Revision 48 AEP-NRC-2023-56, Report Per Technical Specification 5.6.6 for Inoperability of Unit 1 Post Accident Monitoring Reactor Coolant (Loop 3 Cold Leg) Wide Range Temperature Recorder Thermal Sensor2023-12-20020 December 2023 Report Per Technical Specification 5.6.6 for Inoperability of Unit 1 Post Accident Monitoring Reactor Coolant (Loop 3 Cold Leg) Wide Range Temperature Recorder Thermal Sensor ML23352A3502023-12-19019 December 2023 Dc. Cook Nuclear Power Plant, Units 1 Biennial Licensed Operator Requalification Program Inspection and Request for Information ML23338A2642023-12-0505 December 2023 Confirmation of Initial License Examination AEP-NRC-2023-45, Unit 2 - Schedular Exemption for Enhanced Weapons, Firearms, Background Checks, and Security Event Notifications Implementation2023-11-16016 November 2023 Unit 2 - Schedular Exemption for Enhanced Weapons, Firearms, Background Checks, and Security Event Notifications Implementation IR 05000315/20234042023-11-0606 November 2023 Cyber Security Inspection Report 05000315/2023404 and 05000316/2023404 ML23310A1152023-11-0606 November 2023 Notification of the NRC Baseline Inspection and Request for Information, Inspection Report 05000316/2024002 IR 05000315/20234032023-09-19019 September 2023 Security Baseline Inspection Report 05000315/2023403 and 05000316/2023403 IR 05000315/20230112023-08-31031 August 2023 Functional Engineering Inspection - Commercial Grade Dedication Report 05000315/2023011 and 05000316/2023011 ML23242A1832023-08-30030 August 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report05000315/2023004 AEP-NRC-2023-40, Annual Report of Loss-of-Coolant Accident Evaluation Model Changes2023-08-29029 August 2023 Annual Report of Loss-of-Coolant Accident Evaluation Model Changes IR 05000315/20234022023-08-11011 August 2023 Security Baseline Inspection Report 05000315/2023402 and 05000316/2023402 AEP-NRC-2023-34, Supplement to Request for Approval of Change Regarding Neutron Flux Instrumentation2023-08-0202 August 2023 Supplement to Request for Approval of Change Regarding Neutron Flux Instrumentation IR 05000315/20230022023-07-24024 July 2023 Integrated Inspection Report 05000315/2023002 and 05000316/2023002 ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III IR 05000315/20230122023-06-22022 June 2023 Biennial Problem Identification and Resolution Inspection Report 05000315/2023012 and 05000316/2023012 IR 05000315/20235012023-06-21021 June 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000315/2023501 and 05000316/2023501 AEP-NRC-2023-29, Core Operating Limits Report2023-06-19019 June 2023 Core Operating Limits Report ML23159A0192023-06-13013 June 2023 Information Meeting with a Question and Answer Session to Discuss NRC 2022 End-Of-Cycle Plant Performance Assessment of Donald C. Cook Nuclear Plant, Units 1 and 2 AEP-NRC-2023-32, Response to NRC Regulatory Issue Summary 2023-1 Preparation and Scheduling of Operator Licensing Examinations2023-06-0606 June 2023 Response to NRC Regulatory Issue Summary 2023-1 Preparation and Scheduling of Operator Licensing Examinations AEP-NRC-2023-33, Renewable Operating Permit2023-06-0505 June 2023 Renewable Operating Permit AEP-NRC-2023-30, Follow-Up Notification of Ph Non-Compliance for Turbine Room Sump2023-06-0101 June 2023 Follow-Up Notification of Ph Non-Compliance for Turbine Room Sump AEP-NRC-2023-27, Annual Radiological Environmental Operating Report2023-05-15015 May 2023 Annual Radiological Environmental Operating Report ML23131A3282023-05-11011 May 2023 D.C. Cook Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000315/2023404 and 05000316/2023404 IR 05000315/20230012023-05-0303 May 2023 Integrated Inspection Report 05000315/2023001 and 05000316/2023001 AEP-NRC-2023-19, Annual Radioactive Effluent Release Report2023-04-30030 April 2023 Annual Radioactive Effluent Release Report ML23117A0062023-04-27027 April 2023 Review of the Spring 2022 Steam Generator Tube Inspections Report ML23114A1142023-04-25025 April 2023 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection AEP-NRC-2023-23, Annual Report of Individual Monitoring for 20222023-04-24024 April 2023 Annual Report of Individual Monitoring for 2022 AEP-NRC-2023-24, Notification of Ph Non-Compliance for Turbine Room Sump2023-04-12012 April 2023 Notification of Ph Non-Compliance for Turbine Room Sump AEP-NRC-2023-20, Annual Report of Property Insurance2023-04-0303 April 2023 Annual Report of Property Insurance AEP-NRC-2023-15, Decommissioning Funding Status Report2023-03-28028 March 2023 Decommissioning Funding Status Report ML23076A0212023-03-20020 March 2023 Request for Information for NRC Commercial Grade Dedication Inspection; Inspection Report 05000315/2023011; 05000316/2023011 IR 05000315/20234012023-03-16016 March 2023 Security Baseline Inspection Report 05000315/2023401 and 05000316/2023401 ML23066A1882023-03-0707 March 2023 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Donald C. Cook Nuclear Plant IR 05000315/20220062023-03-0101 March 2023 Annual Assessment Letter for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2022006 and 05000316/2022006) IR 05000315/20220042023-02-0101 February 2023 Integrated Inspection Report 05000315/2022004 and 05000316/2022004 and Exercise of Enforcement Discretion AEP-NRC-2023-11, Form OAR-1, Owner'S Activity Report2023-01-31031 January 2023 Form OAR-1, Owner'S Activity Report IR 05000315/20230102023-01-31031 January 2023 Phase 4 Post-Approval License Renewal Inspection Report 05000315/2023010 and 05000316/2023010 AEP-NRC-2023-02, Request for Approval of Change Regarding Neutron Flux Instrumentation2023-01-26026 January 2023 Request for Approval of Change Regarding Neutron Flux Instrumentation ML22363A5622023-01-0404 January 2023 Relief Request ISIR-5-06 Related to ASME Code Case N-729-6 Supplemental Examination Requirements of Reactor Vessel Closure Head Penetration Nozzles AEP-NRC-2022-66, Report Per Technical Specification 5.6.6 for Inoperability of Unit 2 Post Accident Monitoring Neutron Flux Monitoring2022-12-15015 December 2022 Report Per Technical Specification 5.6.6 for Inoperability of Unit 2 Post Accident Monitoring Neutron Flux Monitoring AEP-NRC-2022-46, Notification of Deviation from Electric Power Research Institute (EPRI) Materials Reliability Program 2019-008, Interim Guidance for NEI 03-08 Needed Requirements for Us PWR Plants for Management of Thermal Fatigue in2022-12-12012 December 2022 Notification of Deviation from Electric Power Research Institute (EPRI) Materials Reliability Program 2019-008, Interim Guidance for NEI 03-08 Needed Requirements for Us PWR Plants for Management of Thermal Fatigue in ML22340A1392022-11-30030 November 2022 Submittal of Revision 31 to Updated Final Safety Analysis Report and 10CFR50.71(e) Updated and Related Site Change Reports IR 05000315/20220112022-11-0404 November 2022 Design Basis Assurance Inspection (Teams) Inspection Report 05000315/2022011 and 05000316/2022011 IR 05000315/20220032022-10-28028 October 2022 Integrated Inspection Report 05000315/2022003 and 05000316/2022003 AEP-NRC-2022-58, U1C31 Steam Generator Tube Inspection Report2022-10-24024 October 2022 U1C31 Steam Generator Tube Inspection Report AEP-NRC-2022-61, Request for Relief Related to American Society of Mechanical Engineers (ASME) Code Case N-729-6 Supplemental Examination Requirements, ISIR-5-062022-10-24024 October 2022 Request for Relief Related to American Society of Mechanical Engineers (ASME) Code Case N-729-6 Supplemental Examination Requirements, ISIR-5-06 2024-01-08
[Table view] |
Text
August 30, 2004 Mr. Mano Nazar Executive Vice President and Chief Nuclear Officer Nuclear Generation Group American Electric Power Company 500 Circle Drive Buchanan, MI 49107
SUBJECT:
MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN DONALD C. COOK NUCLEAR POWER PLANT (REPORT 50-315/05-01; 50-316/05-01)
Dear Mr. Nazar:
On August 11, 2004, the NRC staff completed its mid-cycle plant performance assessment of the Donald C. Cook Nuclear Power Plant. The mid-cycle review for the Donald C. Cook Nuclear Power Plant involved the participation of all technical divisions in evaluating performance for the first half of the 2004 assessment cycle. The process included a review of performance indicators (PIs) for the most recent quarter and inspection results over the previous twelve months. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility so that you will have an opportunity to prepare for these inspections and to inform us of any planned inspections that may conflict with your plant activities.
Plant performance for the most recent quarter for Unit 1 was within the Regulatory Response Column of the NRCs Action Matrix based on one White inspection finding in the Public Radiation Safety cornerstone. This White finding was identified in the first quarter of the 2004 assessment cycle and involved the failure to prepare a shipment of radioactive waste such that Department of Transportation radiation limits were not exceeded. A supplemental inspection was conducted for this White finding and concluded that your staff performed an adequate evaluation of the specific performance issues and that comprehensive corrective actions were completed to address each of the specific causes. Otherwise, all inspection findings for Unit 1 were classified as having very low safety significance (Green) and all performance indicators indicated performance at a level requiring no additional oversight (Green).
Plant performance for the most recent quarter for Unit 2 was within the Regulatory Response Column of the NRCs Action Matrix based on the White inspection finding in the Public Radiation Safety cornerstone discussed above and one White PI in the Scrams With Loss of Normal Heat Removal area of the Initiating Events Cornerstone. This PI crossed the Green-to-White threshold in the third quarter of the 2002 assessment cycle. Unit 2 transitioned from the Degraded Cornerstone Column to the Regulatory Response Column of the NRCs Action Matrix in the most recent quarter, as a White PI in the Unplanned Scrams Per 7000 Critical Hours area of the Initiating Events cornerstone transitioned the White-to-Green threshold and was Green.
M. Nazar Otherwise, all inspection findings for Unit 2 were classified as having very low safety significance (Green) and all performance indicators indicated performance at a level requiring no additional oversight (Green).
In our 2002 mid-cycle assessment letter, we advised you of a substantive cross-cutting issue in the area of Problem Identification and Resolution. In particular, weak corrective action program implementation resulted in several findings associated with the failure to promptly and effectively resolve conditions adverse to quality. In our 2002 annual assessment letter, we indicated that this cross-cutting issue would remain open because we continued to identify corrective action implementation issues. In our 2003 mid-cycle assessment letter, this cross-cutting issue remained open due to the continued identification of examples where the corrective action program failed to promptly correct conditions adverse to quality. In our 2003 annual assessment letter, we determined that some positive observations in the implementation of your corrective action program had been noted. However, because some corrective action program improvements had only recently been implemented and their effectiveness could not be fully assessed, and to assure ourselves that positive corrective action program results could be sustained, this cross-cutting issue remained open. During this assessment period, we noted both a decline in the number of findings in the Problem Identification and Resolution area as well as your satisfactory review of issues which were the subject of NRC supplemental inspections. Therefore, this Problem Identification and Resolution substantive cross-cutting issue was closed.
The enclosed inspection plan details the inspections scheduled through March 31, 2006. The inspection plan is provided to minimize the resource impact on your staff and to allow for scheduling conflicts and personnel availability to be resolved in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature.
The inspections in the last 12 months of the inspection plan are tentative and may be revised at the end-of-cycle review meeting.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
M. Nazar If circumstances arise which cause us to change this inspection plan, we will contact you to discuss the change as soon as possible. Please contact Eric Duncan at (630) 829-9628 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
James L. Caldwell Regional Administrator Docket Nos. 50-315; 50-316 License Nos. DPR-58; DPR-74
Enclosure:
D. C. Cook Inspection/Activity Plan See Attached Distribution
M. Nazar If circumstances arise which cause us to change this inspection plan, we will contact you to discuss the change as soon as possible. Please contact Eric Duncan at (630) 829-9628 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
James L. Caldwell Regional Administrator Docket Nos. 50-315; 50-316 License Nos. DPR-58; DPR-74
Enclosure:
D. C. Cook Inspection/Activity Plan See Attached Distribution DOCUMENT NAME: G:\Branch TSS\midcycle2004\Midcycle Ltrs\DCC.wpd To receive a copy of this document, indicate in the box "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RIII RIII RIII NAME EDuncan:rj SReynolds JCaldwell DATE 08/24/04 08/24/04 08/25/04 OFFICIAL RECORD COPY M. Nazar cc w/encl: J. Jensen, Site Vice President M. Finissi, Plant Manager G. White, Michigan Public Service Commission Michigan Department of Environmental Quality Emergency Management Division MI Department of State Police D. Lochbaum, Union of Concerned Scientists
M. Nazar ADAMS Distribution:
WDR DFT JGL1 DWW Project Director, NRR Project Mgr., NRR RidsNrrDipmlipb JLC1 GEG HBC RML2 SRI Cook DRPIII DRSIII PLB1 JRK1
Page 1 of 2 D.C. Cook 08/27/2004 11:17:49 Inspection / Activity Plan Report 22 09/01/2004 - 03/31/2006 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type MOD/5059 - MODIFICATIONS & 50.59 3 1, 2 IP 7111102 Evaluation of Changes, Tests, or Experiments 09/13/2004 09/17/2004 Baseline Inspections 1, 2 IP 7111117B Permanent Plant Modifications 09/13/2004 09/17/2004 Baseline Inspections ISI 2 - INSERVICE INSP/TI-150/TI-152 UNIT 2 3 2 IP 2515/150 Reactor Pressure Vessel Head and Vessel Head Penetration Nozzles (NRC Bulletin 2002-02) 10/04/2004 10/22/2004 Safety Issues 2 IP 2515/152 Reactor Pressure Vessel Lower Head Penetration Nozzles (NRC Bulletin 2003-02) 10/04/2004 10/22/2004 Safety Issues 2 IP 7111108P Inservice Inspection Activities - PWR 10/04/2004 10/22/2004 Baseline Inspections 71121.02 - ALARA (OUTAGE) 1 1, 2 IP 7112102 ALARA Planning and Controls 10/18/2004 10/22/2004 Baseline Inspections 1, 2 IP 71151 Performance Indicator Verification 10/18/2004 10/22/2004 Baseline Inspections RENEWAL - AGING MANAGEMENT PROGRAM INSPECTION 5 1, 2 IP 71002 License Renewal Inspection 11/01/2004 11/19/2004 License Renewal Inspectio PI&R - PI&R INSPECTION 3 1, 2 IP 71152 Identification and Resolution of Problems 11/29/2004 12/17/2004 Baseline Inspections 71122.01 - RADIOLOGICAL EFFLUENT CONTROL 1 1, 2 IP 7112201 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems 01/10/2005 01/14/2005 Baseline Inspections 1, 2 IP 71151 Performance Indicator Verification 01/10/2005 01/14/2005 Baseline Inspections ISI - UNIT 1 ISI/TI-150 INSPECTION 1 1 IP 2515/150 Reactor Pressure Vessel Head and Vessel Head Penetration Nozzles (NRC Bulletin 2002-02) 03/28/2005 04/08/2005 Safety Issues 1 IP 7111108P Inservice Inspection Activities - PWR 03/28/2005 04/08/2005 Baseline Inspections 71121.02 - OUTAGE ALARA 1 1, 2 IP 7112102 ALARA Planning and Controls 04/04/2005 04/08/2005 Baseline Inspections SSDPC - SAFETY SYSTEM DESIGN & PERFORMANCE 5 1, 2 IP 7111121 Safety System Design and Performance Capability 07/25/2005 08/12/2005 Baseline Inspections 71122.03 - REMP & RAD MTL CONTROL 1 1, 2 IP 7112203 Radiological Environmental Monitoring Program 07/11/2005 07/15/2005 Baseline Inspections 1, 2 IP 71151 Performance Indicator Verification 07/11/2005 07/15/2005 Baseline Inspections HEATSKB - BIENNIAL HEAT SINK INSPECTION 1 1, 2 IP 7111107B Heat Sink Performance 10/03/2005 10/07/2005 Baseline Inspections 71114 - EP EXERCISE & EP PI INSP 2 1, 2 IP 7111401 Exercise Evaluation 09/19/2005 09/23/2005 Baseline Inspections 1, 2 IP 71151 Performance Indicator Verification 09/19/2005 09/23/2005 Baseline Inspections 71121.01 - RADIOLOGICAL ACCESS CONTROL 1 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 10/10/2005 10/14/2005 Baseline Inspections This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Page 2 of 2 D.C. Cook 08/27/2004 11:17:49 Inspection / Activity Plan Report 22 09/01/2004 - 03/31/2006 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type 71121.01 - RADIOLOGICAL ACCESS CONTROL 1 1, 2 IP 71151 Performance Indicator Verification 10/10/2005 10/14/2005 Baseline Inspections FY 2006 - D. C. COOK INIT PREP 01/2006 3 1 W90130 OL - INITIAL EXAM - D.C. COOK - JAN/FEB 2006 01/16/2006 01/20/2006 Not Applicable FY 2006 - D. C. COOK INIT EXAM 02/2006 3 1 W90130 OL - INITIAL EXAM - D.C. COOK - JAN/FEB 2006 02/06/2006 02/17/2006 Not Applicable FIREPROT - FIRE PROTECTION INSPECTION TRIENNIAL 1 1, 2 IP 7111105T Fire Protection 03/06/2006 03/24/2006 Baseline Inspections This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.