Mid-Cycle Performance Review & Inspection Plan - Shearon Harris Nuclear Power Plant, Inspection/Activity Plan for 09/01/2002 - 09/30/2003
ML022400165
Person / Time
Site: Harris Duke energy icon.png
Issue date: 08/26/2002
From: Plisco L
Division Reactor Projects II
To: Scarola J
Carolina Power & Light Co
Shared Package
ML022400143 List:
References
IMC 0305
Download: ML022400165 (1)


Text

Page 1 of 1 Harris 08/26/2002 11:42:09 Inspection / Activity Plan Report 22 09/01/2002 - 09/30/2003 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type EB1-TFP - TFP - PRE-INSPECTION VISIT 6 1 IP 7111105T Fire Protection 09/30/2002 10/04/2002 Baseline Inspections EB1-TFP - TRIENNIAL FIRE PROTECTION INSP 4 1 IP 7111105T Fire Protection 10/21/2002 10/25/2002 Baseline Inspections 1 IP 7111105T Fire Protection 11/04/2002 11/08/2002 Baseline Inspections OL EP - EMERGENCY EXERCISE 2 1 IP 7111401 Exercise Evaluation 03/03/2003 03/07/2003 Baseline Inspections 1 IP 7111404 Emergency Action Level and Emergency Plan Changes 03/03/2003 03/07/2003 Baseline Inspections 1 IP 71151 Performance Indicator Verification 03/03/2003 03/07/2003 Baseline Inspections OL RQ - REQUAL INSPECTION 2 1 IP 7111111B Licensed Operator Requalification 03/24/2003 03/28/2003 Baseline Inspections EB2-HS - HEAT SINK 2 1 IP 7111107B Heat Sink Performance 04/14/2003 04/18/2003 Baseline Inspections PS-SEC - SECURITY 1 1 IP 7113001 Access Authorization Program (Behavior Observation Only) 04/21/2003 04/25/2003 Baseline Inspections 1 IP 7113002 Access Control (Search of Personnel, Packages, and Vehicles: Identification and Authorization) 04/21/2003 04/25/2003 Baseline Inspections 1 IP 71151 Performance Indicator Verification 04/21/2003 04/25/2003 Baseline Inspections PS-RP - RADIATION PROTECTION 3 1 IP 7112101 Access Control to Radiologically Significant Areas 04/28/2003 05/02/2003 Baseline Inspections 1 IP 7112102 ALARA Planning and Controls 04/28/2003 05/02/2003 Baseline Inspections 1 IP 7112202 Radioactive Material Processing and Transportation 04/28/2003 05/02/2003 Baseline Inspections 1 IP 71151 Performance Indicator Verification 04/28/2003 05/02/2003 Baseline Inspections EB2-ISI - INSERVICE INSPECTION-U1 1 1 IP 7111108 Inservice Inspection Activities 05/12/2003 05/16/2003 Baseline Inspections PS-RP - RADIATION PROTECTION 2 1 IP 7112101 Access Control to Radiologically Significant Areas 05/12/2003 05/16/2003 Baseline Inspections 1 IP 7112102 ALARA Planning and Controls 05/12/2003 05/16/2003 Baseline Inspections 1 IP 7112202 Radioactive Material Processing and Transportation 05/12/2003 05/16/2003 Baseline Inspections 1 IP 71151 Performance Indicator Verification 05/12/2003 05/16/2003 Baseline Inspections PI&R - PROBLEM IDENTIFICATION & RESOLUTION 3 1 IP 71152B Identification and Resolution of Problems 07/07/2003 07/11/2003 Baseline Inspections 1 IP 71152B Identification and Resolution of Problems 07/21/2003 07/25/2003 Baseline Inspections This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.