Revision to Post-Restart CAL Commitment for Containment Internal Structure Beam 22A and Beam 22B
ML15120A635
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 04/30/2015
From: Cortopassi L
Omaha Public Power District
To: Dapas M
Document Control Desk, NRC Region 4
References
LIC-15-0042
Download: ML15120A635 (3)


Text

~~

UPP

-- - -ii Omaha Public Power Dislrlcl 444South16111 Street Mall Omaha, NE 68102-2247 LI C-15-0042 April 30, 2015 Mr. Marc L. Dapas Regional Administrator, Region IV U.S. Nuclear Regulatory Commission 1600 East Lamar Boulevard Arlington, TX 76011-4511 Fort Calhoun Station, Unit No. 1 Renewed Facility Operating License No. DPR-40 NRC Docket No. 50-285

Subject:

Revision to Post-Restart CAL Commitment for Containment Internal Structure Beam 22A and Beam 22B

Reference:

Letter from OPPD (L. P. Cortopassi) to NRC (M. L. Dapas), "Integrated Report to Support Restart of Fort Calhoun Station and Post-Restart Commitments for Sustained Improvement," dated December 2, 2013 (LIC-13-0164)

(ML13336A785)

Dear Mr. Dapas:

In the Reference letter containing the post-restart commitments for Fort Calhoun Station, Omaha Public Power District (OPPD) in Enclosure 2, Section 4.b. stated:

"Regarding Beam 22A and Beam 22B in the containment internal structures, prior to resuming power operation following the first refueling outage after restart, OPPD will restore full structural design margin as described in the Fort Calhoun Station licensing basis."

Due to complexity of design and the ability to obtain the necessary pre-engineered components in sufficient time to complete the activities for this commitment in the time allotted, OPPD is deferring completion of this commitment from Fort Calhoun Unit 1 Refueling Outage 27 (FC1 R

27) to Refueling Outage 28 (FC1 R 28), which is currently scheduled for the fall of 2016. The revised commitment is:

Mr. Marc L. Dapas LI C-15-0042 Page2 Commitment: OPPD will implement the following commitment regarding structures inside the containment building:

1. Regarding Beam 22A and Beam 22B in the containment internal structures, prior to resuming power operation following Fort Calhoun Station Unit 1 Refueling Outage 28, OPPD will restore full structural design margin as described in the Fort Calhoun Station licensing basis.

If you should have any questions, please contact Terrence W. Simpkin, Manager, Site Regulatory Assurance, at (402) 533-6263.

R?d Louis P. Cortopassi Site Vice President and CNO LPC/ktm

Attachment:

Summary of Regulatory Commitments cc:

C. F. Lyon, NRC Senior Project Manager A. Vegel, NRC Director of Division of Nuclear Materials Safety, Region IV M. C. Hay, NRC Chief of Branch F, Region IV S.M. Schneider, NRC Senior Resident Inspector Document Control Desk

ATTACHMENT Summary of Regulatory Commitments The following list identifies those actions committed to by Omaha Public Power District (OPPD) for Fort Calhoun Station. Any other actions discussed in the submittal represent intended or planned actions by OPPD, are described only for information, and are not regulatory commitments.

COMMITMENT TYPE COMMITTED DATE ONE-TIME PROGRAMMATIC OR "OUTAGE" ACTION (YES/NO)

COMMITMENT (YES/NO)

Regarding Beam 22A and Beam Prior to resuming power Yes No 22B in the containment internal operation following Fort structures, prior to resuming Calhoun Station Unit 1 power operation following Fort Refueling Outage 28 Calhoun Station Unit 1 Refueling Outage 28, OPPD will restore full structural design margin as described in the Fort Calhoun Station licensing basis.