IR 05000458/2018010

From kanterella
Jump to navigation Jump to search
NRC Inspection of Temporary Instruction 2515/194 - Inspection Report 05000458/2018010
ML18085B197
Person / Time
Site: River Bend Entergy icon.png
Issue date: 03/26/2018
From: Greg Werner
NRC/RGN-IV/DRS/EB-2
To: Maguire W
Entergy Operations
Werner G
References
BL-12-001 IR 2018010
Download: ML18085B197 (31)


Text

March 26, 2018 Mr. William F. Maguire, Site Vice President Entergy Operations, Inc.

River Bend Station 5485 US Highway 61N St. Francisville, LA 70775 SUBJECT: RIVER BEND STATION - NRC INSPECTION OF TEMPORARY INSTRUCTION 2515/194, INSPECTION OF THE LICENSEES IMPLEMENTATION OF INDUSTRY INITIATIVE ASSOCIATED WITH THE OPEN PHASE CONDITION DESIGN VULNERABILITIES IN ELECTRIC POWER SYSTEMS (NRC BULLETIN 2012-01) - INSPECTION REPORT 05000458/2018010

Dear Mr. Maguire:

On February 8, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at the River Bend Station. On February 8, 2018, the inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

The NRC inspectors did not identify any findings or violations of more than minor significance.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Gregory E. Werner, Chief Engineering Branch 2 Division of Reactor Safety Docket No. 50-458 License No. NPF-47 Enclosure:

Inspection Report 05000458/2018010 w/ Attachments: 1. Table 1 - Information Gathered for Temporary Instruction 2515/194 2. TI 2515/194 Inspection Documentation Request

U.S. NUCLEAR REGULATORY COMMISSION

Inspection Report

Docket Number: 05000458 License Number: NPF-47 Report Number: 05000458/2018010 Enterprise Identifier: 000512/05000458/I-2018-010-0019 Licensee: Entergy Operations, Inc.

Facility: River Bend Station Location: Saint Francisville, Louisiana Inspection Dates: February 5, 2018, to February 8, 2018 Inspectors: S. Graves, Team Lead, Senior Reactor Inspector, Region IV S. Makor, Reactor Inspector, Region IV Accompanying G. Matharu, Senior Electrical Engineer, NRR/DE/EEOB Personnel: K. Nguyen, Electrical Engineer, NRR/DE/EEOB J. Quichocho, Chief, NRR/DE/EEOB Approved By: G. Werner, Branch Chief, Engineering Branch 2 Enclosure

SUMMARY

The U.S. Nuclear Regulatory Commission continued monitoring licensees performance by conducting Temporary Instruction 2515/194, Inspection of the Licensees Implementation of Industry Initiative Associated with the Open Phase Condition Design Vulnerabilities in Electric Power Systems (NRC Bulletin 2012-01), at River Bend Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the Nuclear Regulatory Commissions program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations None.

Additional Tracking Items None.

INSPECTION SCOPE

This inspection was conducted using Temporary Instruction 2515/194 (ADAMS Accession No. ML17137A416), dated October 31, 2017. The inspectors reviewed the licensees implementation of Nuclear Energy Institute voluntary industry initiative in compliance with Commission guidance. The team discussed the licensees open phase condition system design and ongoing implementation plans with plant staff, Entergy Corporate staff and vendor staff.

The team reviewed licensee and vendor documentation, and performed system walkdowns to verify that the installed equipment was supported by the design documentation. The team verified that the licensee had completed the installation and testing of equipment (with the exception of the tripping functions), installed and tested alarming circuits both local and in the control room, and analyzed potential impacts associated with the design implementation on the current licensing basis.

OTHER ACTIVITIES

- TEMPORARY INSTRUCTIONS, INFREQUENT AND ABNORMAL Temporary Instruction 2515/194 - Inspection of the Licensees Implementation of Industry Initiative Associated With the Open Phase Condition Design Vulnerabilities in Electric Power Systems (NRC BULLETIN 2012-01)

The objective of Temporary Instruction 2015/194 is to verify that licensees have appropriately implemented the Nuclear Energy Institute voluntary industry initiative including updating their licensing basis to reflect the need to protect against open phase conditions and to gather the information necessary for Office of Nuclear Reactor Regulation staff to determine whether the licensees have adequately addressed potential open phase conditions.

Temporary Instruction 2515/194-03.01 - Voluntary Industry Initiative (Part 1)

River Bend Station selected the open phase detection system designed and manufactured by PCS2000 Solutions, LLC, as the design vendor for the open phase condition system. At the end of this inspection the PCS2000 system was still in the monitoring mode of operation to facilitate continued data gathering of grid perturbations for evaluation of alarm and trip setpoints.

The open phase condition equipment was installed on the preferred station service transformers RTX-XSR1C and RTX-XSR1D which power the station vital busses. The licensee was scheduled to transition the PCS2000 system to full implementation (tripping functions enabled) in December 2018. The licensee was preparing the full implementation engineering changes and associated documents for this transition, however they were not available for review at the time of inspection.

Section 03.01 of the Temporary Instruction required the determination whether the licensee appropriately implemented the voluntary industry initiative, dated March 16, 2015 (ADAMS Accession No. ML15075A454), by verifying the following:

a. Detection Alarms and General Criteria 1. Either open phase conditions are detected and alarmed in the control room, or

(a) The licensee has demonstrated that open phase conditions do not prevent the functioning of important-to-safety systems, structures, and components,
(b) open phase condition detection will occur within a reasonably short period of time (e.g., 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />), and
(c) the licensee has established appropriate documentation regarding open phase condition detection and correction.

2. Either detection circuits are sensitive enough to identify an open phase condition for

credited loading conditions (i.e., high and low loading), or if automatic detection may not be possible in very low or no loading conditions when offsite power transformers are in standby mode, automatic detection must happen as soon as loads are transferred to this standby source. Additionally, the licensee has established appropriate shiftily surveillance requirements to look for evidence of open phase conditions.

3. Open phase condition design/protective schemes minimize misoperation or spurious action in the range of voltage unbalance normally expected in the transmission system that could cause separation from an operable off-site power source.

Licensees have demonstrated that the actuation circuit design does not result in lower overall plant operation reliability.

4. New non-Class-1E circuits are not used to replace existing Class-1E circuits.

5. The updated safety analysis report has been updated to discuss the design features and analyses related to the effects of, and protection for, any open phase condition design vulnerability.

b. Protective Actions 1. If the licensee determines there is no single credible failure that could cause an open phase condition, then verify that the licensee has developed and issued a full engineering evaluation to document the basis for open phase condition as a non-credited event. The Bruce Power and Forsmark operating experience must be considered as part of this analysis.

2. With open phase condition occurrence and no accident condition signal present, either an open phase condition does not adversely affect the function of important-to-safety systems, structures, and components, or

(a) technical specification limiting condition for operation are maintained or the technical specification actions are met without entry into Technical Specification Limiting Condition for Operation 3.0.3 (or equivalent),
(b) important-to-safety equipment is not damaged by the open phase condition, and
(c) shutdown safety is not compromised.

3. With open phase condition occurrence and an accident condition signal present, automatic detection and actuation will transfer loads required to mitigate postulated accidents to an alternate source and ensure that safety functions are preserved as required by the current licensing bases, or the licensee has shown that all design basis accident acceptance criteria are met with the open phase condition, given other plant design features. Accident assumptions must include licensing provisions associated with single failures. Typically, licensing bases will not permit consideration of the open phase condition as the single failure since this failure is in a non-safety system.

4. Periodic tests, calibrations, setpoint verifications, or inspections (as applicable)have been established for any new protective features. The surveillance requirements have been added to the plant Technical Specifications, if necessary to meet the provisions of 10 CFR 50.36.

Temporary Instruction 2515/194-03.02 - Information Gathering for Voluntary Industry Initiative Assessment (Part 2)

Section 03.02 of the Temporary Instruction required information gathering as part of the initial inspections to enable the Nuclear Reactor Regulation staff to determine whether the modifications implemented by the licensee of each unique open phase condition system design for the voluntary industry initiative adequately address potential open phase conditions. The information gathered for this section is tabulated in, Table 1 - Information Gathered for Temporary Instruction 2515/194, to this report.

INSPECTION RESULTS

Based on interviews and discussions with the licensee and the vendor, review of available design, testing, grid data trending results documentation, tour of the vendor facility, and walkdowns of installed equipment, the team had reasonable assurance the licensee appropriately implemented, with noted exceptions discussed below, the voluntary industry initiative.

Temporary Instruction 2515/194-03.01 - Voluntary Industry Initiative (Part 1)a. Detection Alarms and General Criteria

(1) The team determined by walkdowns and observation that open phase conditions will be detected and alarmed in the control room.
(2) The team determined that detection circuits were sensitive enough to identify an open phase condition for all credited loading conditions.
(3) No Class-1E circuits were replaced with non-Class 1E circuits in the design.

b. Protective Actions Criteria

(1) The team determined the licensee identified they were susceptible to an open phase condition and were implementing design changes to mitigate the effects.
(2) The team determined that with an open phase condition present and no accident condition signal, the PCS2000 system would not adversely affect the function of important-to-safety systems, structures, and components.

No findings were identified, however the team identified the following exceptions to the Temporary Instruction criteria resulting from the incomplete design modifications:

c. Detection Alarms and General Criteria Exceptions

(1) The licensees design was operating in the monitoring mode to gather data to ensure the open phase condition design and protective schemes would minimize misoperation, or spurious action in the range of voltage unbalance normally expected in the transmission system. Because actual demonstration of this criterion requires the system to be in operation with final trip setpoints established, the team was not able to fully verify this criterion. After discussions with licensee and vendor staff, and design document and test results reviews, the team had reasonable assurance that the actuation circuit design would not result in lower overall plant operation reliability.

The team did not identify any issues of concern.

(2) The Updated Safety Analysis Report had not been updated at the conclusion of the onsite inspection. The team held discussions with the licensee concerning their interpretation of the guidance in the voluntary industry initiative related to adding open phase condition related entries to their licensing basis documents. The licensee entered this issue into their corrective action program as Condition Report CR-RBS-2018-00891 to determine if the Updated Safety Analysis Report would be updated prior to initiating the full design (trip functions enabled) or during the next normal final safety analysis report (FSAR) update cycle. The team did not identify any issues of concern.

d. Protective Actions Criteria Exceptions

(1) The licensees open phase condition design solution used the existing load transfer scheme for safety-related accident loads; only a new tripping condition (open phase)had been added to the electrical faults which result in safety-related loads being transferred to the onsite emergency power system. Because actual demonstration of this criterion requires the system to be in full operation, the team was not able to fully verify this criterion. Through review of available design documents and discussions with plant engineering and vendor staff, the team had reasonable assurance that with an open phase condition present and an accident condition signal, the PCS2000 system automatic detection and actuation would transfer loads required to mitigate postulated accidents to an alternate source and ensure that safety functions are preserved, as required by the current licensing bases. The team did not identify any issues of concern.
(2) The licensee had not finalized documentation for periodic tests, calibrations, setpoint verifications, or inspection procedures for open phase condition-related components at the time of this inspection. The licensee had initiated action requests to establish these activities. The team reviewed the action requests (AR283793 and AR283795)documents outlining the proposed periodic testing and periodicities for the newly installed equipment, reviewed historical system logs related to system performance, reviewed and discussed planned testing, calibration, and inspections. The team also held discussions on the licensees plans to include open phase condition-related components into the Maintenance Rule (10 CFR 50.65) program. The licensee entered this issue into their corrective action program as Condition Report CR-RBS-2018-00893. Existing plant equipment will continue to be maintained according to the licensees current preventative maintenance program. The licensee planned to use guidance in the North American Electric Reliability Councils Reliability Standard PRC-005 and vendor maintenance guidance to maintain the added switchyard relaying equipment for the PCS2000 design. The team did not identify any issues of concern.

EXIT MEETINGS AND DEBRIEFS

On February 8, 2018, the team presented the Temporary Instruction 2515/194 inspection results to Mr. W. Maguire, Site Vice President and other members of the licensee staff. The inspectors verified no proprietary information was retained or documented in this report.

DOCUMENTS REVIEWED

Inspection Type Designation Description or Title Revision/

Procedure Date

TI 2515/194 Calculations G13.18.3.6-026 River Bend Open Phase with 0

Loss-of-Coolant Accident

Analysis

G13.18.3.6-025 River Bend Open Phase 1

Feasibility Analysis

G13.18.3.6*018 Electrical Transient Analysis 5

Program Database Input

Source Study

E-216 Normal Battery BYS-BAT01 B 1

(ECN 55751) Duty Cycle, Current Profile

and Size Verification

E-222-NJS- E-222-NJS-LDC1 QR, 480 1

LDC1 QR VAC Normal Load Center and

Motor Control Center Load

Tabulation including Cable

Verification

Drawings 0242.112-027- Outline - Type SL

20 Transformer, 230kV/4160V

242.112-027- RTX-XSR1C Power 0

25 Transformer Open Phase

Detection 3-Line AC

Schematic

242.112-027- RTX-XSR1D Power 0

26 Transformer Open Phase

Detection 3-Line AC

Schematic

242.112-027- RTX-XSR1C Power 0

034 Transformer OPD Sensor, and

CT Mounting Layout and

Details

242.112-027- RTX-XSR1D Power 0

035 Transformer OPD Sensor, and

CT Mounting Elevation and

Details

Inspection Type Designation Description or Title Revision/

Procedure Date

242.112-027- RTX-XSR1D Power 0

040 Transformer OPD Sensor, and

CT Mounting Layout and

Details

242.112-027- RTX-XSR1D Power 0

041 Transformer OPD Sensor, and

CT Mounting Elevation and

Details

EE-003ZQ RTX-XSR1D Power 0

Transformer Open Phase

Detection 3-Line AC

Schematic Asset Numbers

EE-030A Arrangement Transformer 10

Yard Unit 1

EE-030E Sections and Details 3

Transformer Yard 2A

EE-040A Conduit Plans and Details 4

Transformer Yard Area

EE-040B Conduit Plans and Details 2

Transformer Yard Area

ESK-08SPR18 Elementary Diagram 125VDC 6

Control Circuit Preferred

Station Service XFMR

Protection

ESK-08SPR19 Elementary Diagram 125VDC 7

Control Circuit Preferred

Station Service XFMR

Protection

EE-001AC Start-Up Electrical Distribution 56

Chart

ESK-08SPR04 Elementary Diagram 125VDC 23

Control Circuit Preferred

Station Service XFMR Backup

Protection

ESK-08SPR07 Elementary Diagram 125VDC 25

Control Circuit Preferred

Station Service XFMR Backup

Protection

Inspection Type Designation Description or Title Revision/

Procedure Date

ESK-08SPR15 Elementary Diagram 125VDC 27

Control Circuit Preferred

Station Service XFMR Backup

Protection

ESK-08SPR17 Elementary Diagram 125VDC 8

Control Circuit Preferred

Station Service XFMR Backup

Protection

EE-003ZS Wiring Diagram Open Phase 0

Detection Panel RTX-XSR1C

EE-003ZT Wiring Diagram RTX-XSR1D 0

Open Phase Detection Panel

242.112-027- Connection Diagram Power 0

048 Transformer System 1 and 2

Open Phase Detection

RTX-XSR1C

242.112-027- Connection Diagram 0

049 RTX-XSR1D Power

Transformer System 1 & 2

Open Phase Detection

ESK-11SPF01 Elementary Diagram Station 9

Protection Reserve Station

Service Line

ESK-11SPF02 Elementary Diagram Station 8

Protection Reserve Station

Service Line

ESK-08SPR20 Elementary Diagram 125VDC 7

Control Circuit Dual Channel

Transfer Trip ACB 06, 07, 11

ESK-08SPR21 Elementary Diagram 125VDC 7

Control Circuit Dual Channel

Transfer Trip ACB 15, 26, 27

Engineering EC 47357 Design Change to Detect 0

Changes Open Phase Condition on

Primary Side of RTX-XSR1C

and RTX-XSR1D (BYRON

EVENT) IER-L2-12-14,

Condition Report

CR-RBS-2012-1000, SIPD

2015

Inspection Type Designation Description or Title Revision/

Procedure Date

EC 47359 RTX-XSR1C, Design Change 0

to Detect Open Phase

Condition

EC 47360 RTX-XSR1D, Design Change 0

to Detect Open Phase

Condition

EC 56100 ECN to Revise PMTP of 0

47360

Engineering RBS-EE-17- RBS Open Phase Detection 0

Reports 00002 Monitoring Period Report

March 2015 - January 2016

RBS-EE-17- RBS Open Phase Detection 0

00003 Monitoring Period Report

January 2015 - July 2017

RBS-EE-18- RBS Open Phase Detection 00

00001 Monitoring Period Report July

2017 - January 2018

Miscellaneous RBG-47430 Letter from River Bend Station January 31,

Response to Request for 2014

Additional Information

Regarding Response to

Bulletin 2012-01, "Design

Vulnerability In Electric Power

System"

RBG-47299 90-Day Response to October 24,

Bulletin 2012-01, Design 2012

Vulnerability in Electric Power

System River Bend Station -

Unit 1

AR 283793 Preventive Maintenance October 16,

Change Request: 2017

RSS1 Open Phase Detection

System Protection Relays and

Current Transformers

RSS2 Open Phase Detection

System Protection Relays and

Current Transformers

Inspection Type Designation Description or Title Revision/

Procedure Date

Preventive Maintenance

AR 283795 October 16,

Change Request:

2017

RSS1 and RSS2 Open Phase

Detection System

Procedures AOP-0064 Degraded Grid 010

OSP-0028 Log Report - Normal 107

Switchgear, Control, and

Diesel Generator Buildings

OSP- Procedure Action Request

28R107CN-E Change Notice for Log Report

- Normal Switchgear, Control,

and Diesel Generator

Buildings

OSP-0031 Log Report - Outside Area 093

OSP-0031 Log Report - Outside Area 064

ARP-680-09 P680-09 Alarm Response 033

SOP-0055 Main and Station 040

Transformers (SYS #311)

Vendor P517-0109 PCS2000 Open Phase 0

Documents Detection System User

Manual

Work Orders 00365542 Install PCS2000 Relay on April 11, 2017

RTX-XSR1C for Open Phase

Detection

00365543 Install PCS2000 Relay on September 15,

RTX-XSR1D for Open Phase 2015

Detection

Corrective Action Documents (CR-RBS-)

2015-08755 2017-08510 2018-00893

2017-01281 2018-00360 2012-01000

2017-00493 2018-00396 2017-05750

2017-00501 2018-00495 2018-00892

2017-01217 2018-00857

2017-02356 2018-00859

2017-02770 2018-00894

2017-03493 2018-00891

Table 1 - Information Gathered for Temporary Instruction 2515/194

A Open Phase Condition Describe Observations/Comments

Detection and Alarm

Scheme

Are all credited offsite power Yes Updated Safety Analysis Report Section 8.1

sources specified in No states that River Bend Station is provided

Updated Safety Analysis power from the 230 kV bays of the Fancy Point

Report Chapters 8.1, 8.2, substation via two physically and electrically

and 8.3 and plant Technical independent lines. Each 230 kV line is

Specifications considered in terminated at a transformer yard. Transformer

the design of open phase yard 1 includes preferred station service

condition detection and transformer RTX-XSR1C and yard 2A includes

protection schemes? RTX-XSR1D. The Updated Safety Analysis

Report section also states that standby 4160 V

buses ENS-SWG1A and ENS-SWG1B are

connected to preferred station service

transformers RTX-XSR1C and RTX-XSR1D,

respectively. The transformers in both

transformer yards support the normal operation

and safe shutdown operation of River Bend

Station Drawings 0242.112-027-025 and

242.112-027-026 show the inputs of the new

open phase detection system being connected

to the high side of preferred station service

transformers RTX-XSR1C and 1D.

References:

Engineering Change 47357

Updated Safety Analysis Report Section 8.1

and 8.2

Drawings: 0242.112-027-025 and

242.112-027-026

Are open phase condition Yes The PCS2000 system overview and user

detection scheme(s) No manual states that the system is capable of

installed to monitor the detecting open phase conditions anywhere on

qualified offsite power paths the direct line between the source breaker and

to the engineered safety the power transformer while in standby mode

feature buses during all and drawing excitation current, lightly loaded or

modes of operation? fully loaded. This also includes the detection of

an open phase and grounded condition, a

double open phase and grounded condition,

and an open phase with line charging current

on the high side of a power transformer.

The system has two modes of monitoring the

power transformer for an open phase condition:

no load excitation current mode and transformer

load mode. Internal logic is used to measure

the power transformer high side current levels

and give alarming/tripping priority to either

mode based on the power transformer current

levels RTX-XSR1C and RTX-XSR1D provide

preferred source of power for the engineered

safety feature buses from Offsite sources. The

licensee stated that Engineering Calculation

G13.18.3.6*025 that performed the feasibility

analysis at River Bend Station considered

various open phase configurations for different

station loading scenarios. The audit team did

not review the feasibility studies.

What is the scope of open The scope of open phase condition scheme

phase conditions considered considered the high voltage side of the

by the licensee? transformers only. Open phase conditions on

Yes the low voltage side are not expected to occur.

Did the licensee exclude No The PCS system is capable of detecting open

certain open phase phase conditions anywhere on the direct line

conditions (e.g., high voltage between the source breaker and the power

or low voltage side of power transformer while in standby mode and drawing

transformers), operating and only excitation current, lightly loaded or fully

loading configurations in loaded. This includes the detection of an open

their analyses? If so, phase and grounded condition, a double open

identify the technical phase and grounded condition, and an open

justifications for any phase with line charging current on the high

exclusion. side of a power transformer. Preventive

maintenances on switchgears include

inspecting the bus for damaged components,

loose parts, corrosion, etc. Thermography tests

are performed on various safety-related

components that include motor control centers,

switchgears, transformers, and distribution

panels. Safety-Related breakers are inspected

and refurbished, motors are inspected and

baker tested on a periodic basis through the

preventive maintenance process. Apart from

various maintenance activities that ensure

expected operation, system engineering and

operations perform frequent walkdowns to

identify any system anomalies. Based on this,

the requirement for a separate system that

monitors for open phase condition on the plant

side is not required.

Are the detection schemes Yes The licensee indicated that Engineering

capable to identify open No Calculation G13.18.3.6*025 performed the

phase conditions under all feasibility analysis at River Bend Station and

operating electrical system considered various open phase configurations

configurations and plant for different station loading scenarios. Report

loading conditions? No. RBS-EE-17-00002, Revision 1 for RTX-

XSR1D open phase detection system provides

monitoring data between March 2015 and

January 2016. The report was revised to add

more detail on plant specific events.

Specifically, the report updated data for events

which includes timestamps, sequence

components, and calculations to estimate

horsepower for each motor start event and load

change event. A review of the revised report

RBS-EE-17-00001, shows the systems

response to motor starts at various estimated

loads, different load changes and transformer

energization. A review of the report indicates

that the detection schemes are capable of

identifying open phase conditions under all

operating electrical system configurations and

plant loading conditions.

If the licensee determined Yes The licensee has determined that open phase

that open phase condition No condition detection and alarm scheme is

detection and alarm scheme needed at its facility.

was not needed, did the

licensee provide adequate

calculational bases or test

data?

Are all open phase Yes The alarms from the open phase detection

conditions detected and No system are tied into common alarms for

alarmed in the main control transformer trouble and annunciated in a panel

room with the existing in the main control room. The alarms signify

relays? Preferred Station Service Transformer Trouble.

Are the detection and alarm Yes Relay contacts in each relay in the system

circuits independent of No provide trip/alarm signals which use circuits that

actuation (protection) are independent of each other.

circuits?

If the detection, alarm, and Yes There are no interfaces with Class 1E systems.

actuation circuits are No

non-Class 1E, was there

any interface with Class 1E

systems?

Did the manufacturer Yes The open phase detection system uses a

provide any information/data No combination of parameters to determine an

for the capability of installed open phase condition. These include specific

relays to detect conditions, differences between phase currents relating to

such as unbalanced voltage magnitudes and phase angles, as well as

and current, negative comparisons of current sequence components.

sequence current, A variety of initial input data is used for each

subharmonic current, or transformer: winding configuration, expected

other parameters used to and actual nominal excitation current, mega volt

detect open phase condition amp and voltage, inrush delay, and time delays

in the offsite power system? for trips. Monitoring data is used to update and

adjust input data and typical levels of

What are the analyses and unbalance. A high-level description of the open

criteria used by the licensee phase condition detection circuit requires the

to identify the power system following conditions: 1. The current(s) drops in

unbalance due to open the phase this is open, drops below a low

phase conditions; and percentage setpoint of the nominal current. This

loading and operating includes both fundamental and root mean

configurations considered square components. 2. The current in the intact

for all loading conditions phase(s) stays above a high percentage

which involve plant trip Yes setpoint of the nominal current. Certain

followed by bus transfer No restraint setpoints also need to be met such as

condition? the ratio of fundamental to root mean square

current, ratios of sequence components, and

If certain conditions cannot holding these conditions for the required

be detected, did the licensee Yes amount of time.

document the technical No River Bend Station performed calculations that

basis for its acceptability? evaluated various loading conditions in

conjunction with the transmission system model

for various open phase condition configurations.

Did the licensee perform

functional testing to validate Failure modes and effects analysis was

limitations specified by the performed and used as an input into

manufacturer of the relays? Engineering Change 47357 and testing

procedures for the engineering change to

ensure misoperation are minimized. Functional

testing including Factory Acceptance and Site

Acceptance testing were performed as part of

Engineering Change 47357 prior to

commissioning the system.

Do open phase condition Yes There are several restraints built into the

detection circuit design No detection logic to prevent spurious detections

features minimize spurious from normal transmission disturbances. These

detections due to voltage restraints with initial setpoints were created

perturbations observed from PCS Lab testing, and were updated and

during events which are expanded based on testing and data collected

normally expected in the from installed systems: Entergy engaged an

transmission system? external consulting company (Sargent & Lundy)

to develop test cases for the River Bend Station

Identify whether the licensee open phase condition detection scheme. The

considered alarm/trip test cases considered different types of

settings coordination with disturbances on the transmission system;

other electric power system monitoring data from the River Bend Station

relays including systems and from other sites open phase

transmission system detection systems include multiple transmission

protection features setup to faults and disturbances used to validate and

avoid false indications or tune restraint setpoints. Engineering

unnecessary alarms. Calculation G13.18.3.6*025 developed and

documented the power system model for the

station auxiliaries, and the transmission network

near River Bend Station for system analyses

using industry-approved software named

electro magnetic transient program. The

calculation provided inputs for testing a relaying

scheme that is able to reliably detect an open

phase event at the high voltage side of the

preferred station service transformers being fed

from offsite power circuits without false

actuation due to various disturbances (e.g.

transformer energization, motor starting, station

faults, transmission system disturbances etc.).

Alarm Circuits: As documented in Engineering

Change 47357, several fuses were installed to

provide adequate protection between the

PCS2000 cabinets and the transformer control

panels. Coordination plots of the fuses with the

upstream protective devices are attached with

Engineering Change 47357. The final alarm

actuation setpoints will be developed after

substantial monitoring periods.

Trip Circuits: Protective coordination of the trip

circuits with offsite and onsite protection system

will be evaluated as part of the future

engineering change that will be performed to

enable trip functionality.

Reference Documents:

RBS-EE-17-00002, RBS-EE-17-00003,

G13.18.3.6*025, and Engineering Change 47357

Identify how the alarm Alarms from the open phase detection system

features provided in the sent to the main control room are managed in

main control room including several ways. The monitoring period and data

setpoints are maintained, are used to adjust alarm setpoints, troubleshoot

calibrated, and controlled. issues that arise, and give operating experience

on alarms. The system has physical (test)

switches that can be used to block specific

alarms once they have been acknowledged,

such as a device problem or loss of power (this

allows the main control room alarm to be

cleared and prevents masking of other alarms).

The switches can also be used to prevent

spurious main control room alarms during

troubleshooting or when setpoints are updated

(in addition to procedures being developed).

The system cabinets are locked and the relays

are (non-default) password protected. Setpoint

control is also accomplished through

as-found/as-left relay settings comparison

procedures used in Entergy Transmission.

North American Electric Reliability Council

standards are utilized to perform preventive

maintenance and calibration of relays. The

relays and other digital components that are

part of the open phase detection system were

evaluated and are controlled by Entergy critical

digital asset procedures.

Does the open phase Yes The open phase detection system considers

condition detection scheme No both fundamental and root mean square

consider subharmonics in components of each phase current as well as

the supply power or offsite the ratio between fundamental and root mean

power system? square. The open phase detection system also

considers instantaneous current magnitudes

along with short- and long-term smoothed

(averaged) magnitudes. The monitoring period

will be used to establish the threshold for

background and transient subharmonics, and

adjust trip or actuation setpoints above the

threshold.

Are open phase condition Yes The Engineering Change required to install the

detection and alarm circuit No trip functionality is a work in progress. The

components scoped into the maintenance rule program applicability/inclusion

licensees maintenance rule will be evaluated in the ongoing engineering

program? change that enables the trip functionality. This

is consistent with the process and procedures

followed by Entergy. Condition Report

CR-RBS-2018-00893 was initiated to document

this question and ensure that the maintenance

rule applicability is evaluated through the

engineering change process.

The components added through the open

phase detection system are scoped into the

preventive maintenance program. These action

requests initiated preventive maintenances and

calibrations for the open phase components.

The actual preventive maintenance will be

processed through the regular work

management schedule. The licensee has

currently implemented a modification that

installed the open phase detection system in

the monitoring and alarm mode. The system

currently does not have the trip functionality

enabled.

B Open Phase Condition Yes/No Describe Observations/Comments

Protection Scheme

Record location of the Location:

sensing of the protection High voltage side of preferred power station

scheme (e.g., high voltage service transformers

or low voltage side of the

transformer, engineered

safety feature bus, etc.).

Record the classification of Classification: Non-Safety

the protection scheme,

safety or non-safety.

Did the licensee consider Yes There are no direct interfaces with safety-

the interface requirements No related systems

for non-safety with safety-

related circuits?

Record the type of the The protection scheme is digital. The open

protection scheme, digital or phase detection system utilizes microprocessor

non-digital. relays, computers, satellite synchronized

clocks, and annunciators. The components are

considered digital.

Are cyber security Yes The cyber security evaluation was performed as

requirements specified for No part of Engineering Change 47357. The

digital detection scheme? N/A components installed by this engineering

change are considered Critical Digital Assets.

The components installed by the engineering

change have software equipped which were

evaluated by the engineering change and

classified as Level B software.

Did the licensee consider Yes The engineering change evaluates the

any design features to No installation of the open phase system that has

prevent protective functional redundant circuits. To enhance reliability, the

failures for open phase two systems communicate by fiber optic

condition protection system? interface to exchange information. Separate

output contacts are provided in redundant

cabinets for the following functions: open

phase detection, ground overcurrent detection,

mode disagreements, and relay failure. The

open phase detection system installed on the

transformer follows a one out of two taken twice

logic. This ensures that a single failure of a

protective relay cannot affect the credited offsite

power source.

Identify the number of Two independent sets of current

channels provided per transformers/sensors are provided per offsite

offsite power source, and if power source. Each sensor provides input to its

there is independence own set of relays that sense current

between channels and imbalances. The relays are connected in such

sensors. a manner that the system requires a one out of

two taken twice logic.

What is the safety The power supply for the protection scheme is

classification of power non-safety related. This is consistent with the

supply for the protection safety classification of the preferred station

scheme? transformer and the open phase detection

systems.

Was a loss of power to the Yes

protection scheme No The impacts of loss of power supply to the

considered? protection scheme have been evaluated in the

failure modes and effects analysis performed as

part of Engineering Change 47357. The loss of

power supply is identified through a relay self-

test and a system alarm is provided that would

notify operations of a loss of power supply.

Moreover, the system relays and other

components are supplied by DC power that is

fed from a non-safety battery system. Upon

loss of charger, the battery is capable of

supplying loads for a 2 hour2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> period as credited

in the system design. AC power is supplied to

the panels space heaters. Loss of AC power

supply is considered in the failure modes and

effects analysis.

Identify if the licensee The PCS2000 system installed at River Bend

considered the Station is built with coincidence logic to add

consequences of a failure or defense-in-depth and reduce spurious

malfunction of a channel. actuations. The open phase detection system

follows a one out of two taken twice logic. The

system has redundant panels that contain two

Schweitzer Engineering Laboratories (SEL)

451 relays each, which take inputs from

independent current sensors. To enhance

reliability, the two panels will communicate by

fiber optic interfaces to exchange information.

The SEL relays that sense open phase

conditions are digital microprocessor relays that

have self-monitoring capabilities. A relay failure

is detected through a relay self-test. A relay

self-test failure is identified by a system alarm.

In a one out of two taken twice logic, the failure

of one relay does not have the potential to

spuriously trip offsite power source. The

second relay in the panel and the two relays on

the redundant panel are relied upon to detect

an open phase condition.

The digital relays fail in as is configuration and

will not actuate a trip signal. It is unlikely that

two out of four relays will fail in an actuated

mode. Therefore, failure of a single channel

current sensor or the entire channel of an open

phase detection system, the coincidence logic

at River Bend Station (one out of two taken

twice) prevents spurious misoperation/spurious

trip of offsite power source.

Did the design consider the Yes The open phase detection is a non-safety

single failure criteria as No related system and may potentially fail during

outlined in the general postulated accidents or plant shutdown

design criteria (GDC) or the resulting from an external event. In the event of

principle design criteria an open phase condition in power source

specified in the Updated related with one safety division, coupled with a

Safety Analysis Report? single failure in the opposite (or redundant)

train, the safe shutdown capability may be

adversely impacted as both trains may not be

available to power the safety-related busses.

Since failures in non-safety systems are

considered to occur when evaluating

conformance to the single failure criterion

(safety systems), the open phase condition

scheme at River Bend Station does not conform

to the single failure criteria as outlined in the

GDC or the principle design criteria specified in

the River Bend Station Updated Safety Analysis

Report (i.e., for an open phase condition, a

non-Class 1E circuit should not preclude the

onsite electrical power system from being able

to perform its safety function given a single

failure of the onsite power system).

Did the licensee identify the Yes Based on the various loads and generating

industry standards and No stations around River Bend Station, the power

criteria to verify power flow from and to the Fancy Point switchyard

quality issues caused by does not see much noise. Additionally,

open phase conditions that Engineering Calculation G13.18.3.6*025

affect redundant engineered modelled the transmission system near River

safety feature buses? Bend Station on EMTP and ran various loading

scenarios for multiple open phase condition.

The monitoring period at River Bend Station will

also enable the site to monitor the offsite source

for general disturbances and noise. The

setpoints will be adjusted accordingly.

What industry standards The trip setpoints will be evaluated with the

were used to develop the associated industry standards in a future

acceptance criteria for open engineering change that will enable the trip

phase condition trip setpoint functionality. The licensee is proposing a trip

or analytical limit? setpoint of less than 5 seconds which will

ensure any heating effects from unbalanced

voltage conditions do not adversely impact plant

motors.

What are the analytical limits The actual setpoints for the actuation circuits

or criteria used for setpoints will be evaluated as part of the future

of the actuation/protection engineering change that will enable the trip

scheme to provide adequate functionality. The licensee is proposing a trip

protection for motors and setpoint of less than 5 seconds which will

sensitive equipment? ensure any heating effects from unbalanced

voltage conditions do not adversely impact plant

motors.

What are the design The PCS2000 system installed at River Bend

features provided to Station is built with coincidence logic to add

preclude spurious trips of defense-in-depth and reduce spurious

the offsite power source actuations. The open phase detection system

(e.g. coincidence logic)? follows a one out of two taken twice logic. The

system has redundant panels that contain two

SEL 451 relays each which take inputs from

independent current sensors. To enhance

reliability, the two panels will communicate by

fiber optic interfaces to exchange information.

The SEL relays that sense open phase

conditions are digital microprocessor relays that

have self-monitoring capabilities. A relay failure

is detected through a relay self-test. A relay

self-test failure is identified by a system alarm.

In a one out of two taken twice logic, the failure

of one relay does not have the potential to

spuriously trip offsite power source. The

second relay in the panel and the two relays on

the redundant panel are relied upon to detect

an open phase condition.

What analyses have been Engineering Calculation G13.18.3.6*026 was

performed by the licensee developed to determine the minimum amount of

which demonstrates that the time an open phase event on the high side of

open phase conditions do the preferred transformer, occurring

not adversely affect the simultaneously with a loss-of-coolant accident,

function(s) of could persist before damage to or tripping of,

important-to-safety medium voltage and low voltage auxiliary power

equipment required for safe system motors would result.

shutdown during anticipated

operational occurrences,

design basis events, and

accidents?

Further analysis including time delays

If an analyses was not associated with bus transfer schemes will be

performed, what justification evaluated by a future engineering change that

was provided? will be performed to enable the trip functions of

Yes the open phase detection system.

Are bus transfer schemes No

and associated time delays

considered?

Are open phase condition Yes The Engineering Change required to install the

protection/actuation circuit No trip functionality is a work in progress. The

components scoped, as maintenance rule program applicability/inclusion

appropriate, into the will be evaluated in the ongoing engineering

licensees maintenance rule change that enables the trip functionality. This

program? is consistent with the process and procedures

followed by Entergy. Condition Report

CR-RBS-2018-00893 was initiated to document

this question and ensure that the maintenance

rule applicability is evaluated through the

Engineering Change.

C Updated Safety Analysis No Describe Observations/Comments

Report Updates to Reflect

the Need to Protect Against

Open phase conditions: The open phase detection system is currently in

Using items 1 to 6 below as monitoring phase and a future engineering will

examples, identify whether be performed to actuate the trip functionality.

the licensee has updated All Updated Safety Analysis Report /Licensing

the Updated Safety Analysis basis changes will be evaluated by the future

Report (and supporting engineering change. Condition Report CR-RBS-

documents such as 2018-00891 was created to track Updated

calculations of record, Safety Analysis Report Changes.

design change

modifications, etc.) to

ensure plant-specific

licensing basis/requirements

include discussions of the

design features and

analyses related to the

effects of, and protection for,

any open phase condition

design vulnerability:

The plant-specific analysis N/A

and documentation that

established the resolution of

the open phase condition

design vulnerability,

including the failure mode

analysis performed.

Description of open phase

condition automatic

detection scheme, including

how offsite power system

open phase conditions are

detected from sensing to

alarm devices (loss of one

or two phases of the three

phases of the offsite power

circuit both with and without

a high-impedance ground

fault condition on the

high-voltage side of all

credited qualified offsite

power sources under all

loading and operating

configurations; and loss of

one or two phases of three

phases of switchyard

breakers that feed offsite

power circuits to

transformers without

ground).

Detection circuit design

features to minimize

spurious indications for an

operable offsite power

source in the range of

voltage perturbations, such

as switching surges,

transformer inrush currents,

load or generation

variations, and lightning

strikes, normally expected in

the transmission system.

Alarm features provided in

the main control room.

Discuss the engineered

safety feature bus alignment

during normal plant

operation and the operating

procedures in place to

address open phase

conditions. If the plant

auxiliaries are supplied from

the main generator and the

offsite power circuit to the

engineered safety feature

bus is configured as a

standby power source, then

open phase conditions

should be alarmed in the

main control room for

operators to take corrective

action within a reasonable

time.

Describe the automatic

protection scheme provided

for open phase conditions

including applicable industry

standards used for

designing the scheme.

Design features to minimize

spurious actuations for an

operable offsite power

source in the range of

voltage perturbations, such

as switching surges,

transformer inrush currents,

load or generation

variations, and lightning

strikes, normally expected in

the transmission system

should be described.

Brief discussion of the

licensees analyses

performed for accident

condition concurrent open

phase conditions which

demonstrate that the

actuation scheme will

transfer engineered safety

feature loads required to

mitigate postulated

accidents to an alternate

source consistent with

accident analyses

assumptions to ensure that

safety functions are

preserved, as required by

the licensing bases.

D Technical specification Describe Observations/Comments

surveillance requirements

and limiting condition for The open phase detection system is currently in

operation for equipment monitoring phase and a future engineering will

used for open phase be performed to actuate the trip functionality.

condition mitigation All Updated Safety Analysis Report / licensing

basis changes will be evaluated by the future

engineering change. Condition Report CR-

RBS-2018-00891 was created to track Updated

Safety Analysis Report Changes. The final

design of the open phase detection scheme will

trip the offsite source emanating from the 230

kV switchyard (Fancy Point) upon detecting an

open phase condition independent of plant

operating mode (start up, normal operation, or

accident condition). The loss of one offsite

source will require entry into appropriate

technical specification related limiting condition

for operation. Technical specification related

surveillance requirements have not been

developed yet.

Are technical specifications Yes The open phase detection system is currently in

surveillance requirements No monitoring phase and a future engineering will

and limiting condition for be performed to actuate the trip functionality.

operation for equipment All Updated Safety Analysis Report /Licensing

used for the mitigation of basis changes will be evaluated by the future

open phase condition engineering change. Condition Report CR-

identified and implemented RBS-2018-00891 was created to track Updated

consistent with the Safety Analysis Report Changes

operability requirements

specified in the plant Yes

technical specifications? No

N/A - see above

If the licensee determined

that technical specifications

are unaffected because

open phase condition is

being addressed by

licensee-controlled

programs, is the technical

justification adequate?

E Provide a brief summary of Engineering Change 47357 involved the installation of an

the open phase condition open phase detection system on the offsite power supply

plant modification performed to preferred station service transformers 1RTX-XSR1C

under and 1RTX-XSR1D. This system will be capable of

CFR 50.59. detecting open phase conditions - including an open-

phase and grounded condition, a double open-phase and

grounded condition, and an open phase with line charging

- anywhere between the Fancy Point substation 230 kV

buses and these transformers. The system will also be

capable of detecting open phase conditions while the

transformers are fully loaded, lightly loaded, or drawing

only excitation current. Upon detection of an open phase

condition, a control room alarm will be actuated.

The initial phase of the activity included data collection

and performance monitoring of the new system. The

open phase detection system will be modified under a

separate activity to trip preferred station service

transformers 1RTX-XSR1C or 1RTX-XSR1D - which will

result in an automatic start of the safety-related

emergency diesel generator to supply the engineered

safety feature buses.

The scope of Engineering Change 47357 involves the

installation of an open phase detection system on the

offsite power supply to preferred station service

transformers 1RTX-XSR1C and

1RTX-XSR1D, and includes:

  • New bushing sensors and new neutral current

transformers will be installed on the high side of the

transformers

  • New open phase detection cabinets and associated

structural components will be installed above the

transformer oil containment pits

  • New cables to connect the new open phase detection

equipment to existing plant equipment will be

installed; AC power will be supplied from new

480/120V transformers located near the new

open phase detection cabinets, and fed from

NHS-MCC-18A and NHS-MCC-20A, while DC power

will be supplied from battery 1BYS-PNL03B via

1CES-PNL1G and 2CESPNL1F

existing transformer alarm circuit will be actuated

REFERENCE: River Bend Station Process Applicability

Determination Engineering Change 47357

TI 2515/194 Inspection Documentation Request

Please provide the following documentation (Items 1 - 6) to the lead inspector prior to the onsite

inspection date, preferably no later than January 22, 2018. Whenever practical, please provide

copies electronically (IMS/CERTREC is preferred). Please provide an index of the requested

documents which includes a brief description of the document and the numerical heading

associated with the request (i.e., where it can be found in the list of documents requested).

Sam Graves, Lead Inspector

RIV/DRS/EB2

1600 E. Lamar Blvd.

Arlington, TX 76011

817-200-1102

samuel.graves@nrc.gov

1. Copies of any calculations, analyses, and/or test reports performed to support the

implementation of your open phase condition (OPC) solution. If, in your implementation,

OPCs are not detected and alarmed in the control room please include documentation that:

a) demonstrates the OPC will not prevent functioning of important-to-safety SSCs; and b)

detection of an OPC will occur within a short period of time (e.g., 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />).

2. Copies of any modification packages, including 10 CFR 50.59 evaluations if performed,

used for or planned for the implementation of your OPC solution.

3. Copies of periodic maintenance, surveillance, setpoint calibration, and/or test procedures

implemented or planned, for your OPC solution.

4. Copies of your licensing basis changes to Updated Final Safety Analysis Report (UFSAR)

and/or Technical Specifications (TS), as applicable, which discuss the design features and

analyses related to the effects of, and protection for, any open phase condition design

vulnerability.

5. Copies of any procurement specifications and acceptance testing documents related to the

installation of your OPC solution.

6. Copies of any site training the team will need to accomplish to gain access to areas with, or

planned, major electrical equipment used in your OPC solution (i.e. switchyard).

Please provide the following documentation to the team when they arrive onsite. Whenever

practical, please provide copies electronically, except for drawings. Drawings should be

provided as paper copies of sufficient size (ANSI C or D) such that all details are legible.

7. A brief presentation describing your electric power system design and typical electrical

transmission and distribution system alignments; OPC design schemes installed to detect,

alarm and actuate; bus transfer schemes; and maintenance and surveillance requirements.

This presentation should be a general overview of your system. Please schedule the

overview shortly after the entrance meeting.

8. Plant layout and equipment drawings for areas that identify: (a) the physical plant locations

of major electrical equipment used in your open phase condition solution; (b) the locations of

detection and indication equipment used in the open phase condition sensing circuits.

9. If OPC actuation circuits are required, provide documentation that demonstrates continued

coordination with the other protective devices in both the offsite electrical system (within

River Bend Station area of responsibility) and the onsite electrical systems.

10. Access to locations in which open phase condition equipment is installed or planned (i.e.

switchyard, transformer yard, etc.)

11. Copies of documentation or testing that demonstrates your OPC solution minimizes spurious

actuation or misoperation in the range of voltage imbalance normally expected in the

transmission system that could cause undesired separation from an operable off-site power

source.

This document does not contain new or amended information collection requirements

subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing

information collection requirements were approved by the Office of Management and

Budget, Control Number 31500011. The NRC may not conduct or sponsor, and a person

is not required to respond to, a request for information or an information collection

requirement unless the requesting document displays a currently valid Office of

Management and Budget control number.

This document will be made available for public inspection and copying at

http://www.nrc.gov/reading-rm/adams.html and at the NRC Public document Room in

accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for

Withholding.

ML18085B197

SUNSI Review: ADAMS: Non-Publicly Available Non-Sensitive Keyword: NRC-002

By: STG Yes No Publicly Available Sensitive

OFFICE SRI: EB2 RI:EB2 C:EB2 C:PBC C:EB2

NAME SGraves SMakor GWerner JKozal GWerner

SIGNATURE /RA/ /RA/ /RA/ /RA/ /RA/

DATE 2/27/2018 2/27/2018 03/13/2018 03/26/2018 03/26/2018