Updated Inspection Plan for River Bend Station (Report 05000458/2018005)
ML18234A102
Person / Time
Site: River Bend Entergy icon.png
Issue date: 08/31/2018
From: Jason Kozal
NRC/RGN-IV/DRP/RPB-C
To: Maguire W
Entergy Operations
Kozal J
References
IR 2018005
Download: ML18234A102 (5)


Text

ust 31, 2018

SUBJECT:

UPDATED INSPECTION PLAN FOR RIVER BEND STATION (REPORT 05000458/2018005)

Dear Mr. Maguire:

The enclosed inspection plan lists the inspections scheduled through June 30, 2020, for River Bend Station. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at 817-200-1148 with any questions you have regarding this letter.

Sincerely,

/RA/

Jason W. Kozal, Chief Project Branch C Division of Reactor Projects Docket Nos. 50-458 License Nos. NPF-47 Enclosure: Inspection Plan

IP 22 Inspection Activity Plan Report River Bend 08/01/2018 - 06/30/2020 Unit Start End Activity CAC Title Staff Count BRQ 3 1 08/26/2018 09/01/2018 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance (Biennial)

LOADING INSPECTION (ONE WEEK IN MONTH) 1 1 09/01/2018 09/30/2018 IP 60855.1 000590 Operation of an Independent Spent Fuel Storage Installation at Operating Plants RBS 50.59 CHANGES, TESTS, EXPERIMENTS 3 1 09/10/2018 09/14/2018 IP 71111.17T 000709 Evaluations of Changes, Tests, and Experiments SECURITY SOLO INSPECTION 1 1 09/24/2018 09/28/2018 IP 71130.02 000734 Access Control 1 09/24/2018 09/28/2018 IP 71151 001338 Performance Indicator Verification RAD SAFETY 1,3 2 1 11/05/2018 11/09/2018 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1 11/05/2018 11/09/2018 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation MAT'L CONTROL & ACCOUNTING 1 1 11/05/2018 11/09/2018 IP 71130.11 000742 Material Control and Accounting (MC&A)

Security Access Control .02 1 1 01/07/2019 01/11/2019 IP 71130.02 000734 Access Control 1 01/07/2019 01/11/2019 IP 71151 001338 Performance Indicator Verification BIENNIAL PI&R 4 1 02/11/2019 02/15/2019 IP 71152B 000747 Problem Identification and Resolution 1 02/25/2019 03/01/2019 IP 71152B 000747 Problem Identification and Resolution INSERVICE INSPECTION RF20 1 1 03/18/2019 03/22/2019 IP 71111.08G 000701 Inservice Inspection Activities (BWR)

RP INSPECTION (1,2) - RFO 2 1 04/08/2019 04/12/2019 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1 04/08/2019 04/12/2019 IP 71124.02 000726 Occupational ALARA Planning and Controls Enclosure This report does not include INPO and OUTAGE activities. Page 1 of 3 This report shows only on-site and announced inspection procedures.

8/22/2018 7:59:08 AM

IP 22 Inspection Activity Plan Report River Bend 08/01/2018 - 06/30/2020 Unit Start End Activity CAC Title Staff Count RP TEAM INSPECTION 4 1 07/08/2019 07/12/2019 IP 71124.05 000729 Radiation Monitoring Instrumentation 1 07/08/2019 07/12/2019 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment 1 07/08/2019 07/12/2019 IP 71124.07 000731 Radiological Environmental Monitoring Program 1 07/08/2019 07/12/2019 IP 71124.08 000732 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation RIVER BEND DBA PROGRAMS EQ INSPECTION 3 1 07/15/2019 08/02/2019 IP 71111.21N 000714 Design Bases Assurance Inspection (Programs)

EP PROGRAM INSPECTION 1 1 07/22/2019 07/26/2019 IP 71114.02 000717 Alert and Notification System Testing 1 07/22/2019 07/26/2019 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 1 07/22/2019 07/26/2019 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 1 07/22/2019 07/26/2019 IP 71114.05 000720 Correction of Emergency Preparedness Weaknesses and Deficiencies 1 07/22/2019 07/26/2019 IP 71151 001397 Performance Indicator Verification FORCE-ON-FORCE PLANNING AND EXERCISES 8 1 10/07/2019 10/11/2019 IP 71130.03 000735 Contingency Response - Force-On-Force Testing 1 10/28/2019 11/01/2019 IP 71130.03 000735 Contingency Response - Force-On-Force Testing INITIAL EXAM 5 1 10/20/2019 10/26/2019 OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)

1 11/17/2019 11/30/2019 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)

TRIENNIAL FIRE PROTECTION INSPECTION 4 1 10/21/2019 10/25/2019 IP 71111.05T 000696 Fire Protection (Triennial)

1 11/04/2019 11/08/2019 IP 71111.05T 000696 Fire Protection (Triennial)

RS24 Radiation Safety 2 1 02/10/2020 02/14/2020 IP 71124.02 000726 Occupational ALARA Planning and Controls 1 02/10/2020 02/14/2020 IP 71124.04 000729 Occupational Dose Assessment RS13PI Radiation Safety 2 1 05/18/2020 05/22/2020 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1 05/18/2020 05/22/2020 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation This report does not include INPO and OUTAGE activities. Page 2 of 3 This report shows only on-site and announced inspection procedures.

8/22/2018 7:59:08 AM

IP 22 Inspection Activity Plan Report River Bend 08/01/2018 - 06/30/2020 Unit Start End Activity CAC Title Staff Count EP Exercise and PI Inspection 4 1 06/22/2020 06/26/2020 IP 71114.01 000716 Exercise Evaluation 1 06/22/2020 06/26/2020 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 1 06/22/2020 06/26/2020 IP 71151 001397 Performance Indicator Verification This report does not include INPO and OUTAGE activities. Page 3 of 3 This report shows only on-site and announced inspection procedures.

8/22/2018 7:59:08 AM

ML18234A102 SUNSI Review ADAMS: Non-Publicly Available Non-Sensitive Keyword:

By: CHY/RDR Yes No Publicly Available Sensitive NRC-002 OFFICE C:DRP/C NAME JKozal SIGNATURE /RA/

DATE 8/23/18