MONTHYEARML24023A3242024-01-23023 January 2024 Inservice Inspection Request for Information ML23348A3712023-12-14014 December 2023 Notification of an NRC Fire Protection Baseline Inspection (NRC Inspection Report (05000416/2024011) and Request for Information IR 05000416/20230052023-08-21021 August 2023 Updated Inspection Plan for Grand Gulf Nuclear Station (Report 05000416/2023005) IR 05000416/20220062023-03-0101 March 2023 Annual Assessment Letter for Grand Gulf Nuclear Station Report 05000416/2022006 ML22312A5832022-11-0808 November 2022 Notification of Cyber Security Baseline Inspection and Request for Information 05000416/2023401 IR 05000416/20220052022-08-18018 August 2022 Updated Inspection Plan for Grand Gulf Nuclear Station (Report 05000416/2022005) ML22110A1172022-04-19019 April 2022 (GG) 2022 Emergency Preparedness (EP) Program Inspection RFI Sdh 041922 IR 05000416/20210062022-03-0202 March 2022 Annual Assessment Letter for Grand Gulf Nuclear Station (Report 05000416/2021006) ML22075A3682022-02-14014 February 2022 2022 PIR Request for Information.Pdf ML21327A0842021-11-22022 November 2021 ISI RFI IR 05000416/20210052021-09-0101 September 2021 Mid-Cycle Inspection Plan Transmittal Letter for Grand Gulf Nuclear Station (Report 05000416/2021005) ML21179A1202021-06-28028 June 2021 Notification of NRC Supplemental Inspection of Action Matrix Column 3 (Degraded Performance) Inputs and Request for Information ML21158A0822021-06-0707 June 2021 Notification of Inspection (NRC Inspection Report 05000416/2021003) and Request for Information ML21106A2232021-04-16016 April 2021 IR 2021402 Document Request List ML21074A0822021-03-15015 March 2021 Notification of Evaluations of Changes, Tests, and Experiments Inspection (Inspection Report 05000416/2021002) and Request for Information ML21061A3352021-02-25025 February 2021 Request for Information: Grand Gulf Nuclear Station, Dated December 4, 2020; Inspection Report 05000416-2021001, Occupational Radiation Safety Inspection-2, 4 ML20363A1462020-12-22022 December 2020 Request for Information: Grand Gulf EP Exercise Inspection - March 2021 ML20258A0202020-09-0909 September 2020 EP Program Inspection RFI, Request for Information to Support and Prepare for Emergency Preparedness (EP) Program Inspection Scheduled to Occur the Week of November 16, 2020 ML20199M2352020-07-17017 July 2020 Notification of NRC Design Bases Assurance Inspection (Teams) (Inspection Report 05000416/2020012) and Initial Request for Information ML20155K7172020-06-0303 June 2020 Notification of NRC Fire Protection Baseline Inspection (NRC Inspection Report 05000416/2020013) and Request for Information ML20125A3802020-05-0404 May 2020 Request for Information, Inspection Date: July 20-24, 2020 ML20055E1562020-03-0303 March 2020 GG2019006 Annual Assessment Letter ML19346E2892019-12-11011 December 2019 ISI Request for Information ML19302E1102019-10-29029 October 2019 Document Request - GG 95001 - July 15 2019 ML19302E1082019-10-29029 October 2019 Document Request - GG 95001 - August 2 2019 IR 05000416/20190052019-08-30030 August 2019 Updated Inspection Plan for Grand Gulf Nuclear Station, Report 05000416/2019005 ML19148A5252019-05-28028 May 2019 Notification of Nrc Design Bases Assurance Inspection (Programs) ((05000416/2019010) and Initial Request for Information IR 05000416/20180062019-03-0404 March 2019 Annual Assessment Letter for Grand Gulf Nuclear Station (Report 05000416/2018006) ML19063B4882019-03-0404 March 2019 Notification of NRC Triennial Heat Sink Performance Inspection (05000416/2019002) and Request for Information ML19003A3812018-12-31031 December 2018 Notification of Cyber Security Inspection Report 05000416/2019410, and Request for Information ML18283A0622018-10-10010 October 2018 Notification of Evaluations of Changes, Tests, and Experiments Inspection (05000416/2018004) and Request for Information IR 05000416/20180052018-08-31031 August 2018 Updated Inspection Plan for Grand Gulf Nuclear Station (Report 05000416/2018005) IR 05000416/20170062018-03-0101 March 2018 Annual Assessment Letter for Grand Gulf Nuclear Station (Report 05000416/2017006) ML17243A3062017-08-28028 August 2017 Updated Non-Public Security Inspection Plan for Grand Gulf Nuclear Station, Unit 1 IR 05000416/20170052017-08-28028 August 2017 Updated Inspection Plan for Grand Gulf Nuclear Station (Report 05000416/2017005) IR 05000416/20160062017-03-0101 March 2017 Annual Assessment Letter for Grand Gulf Nuclear Station (Report 05000416/2016006) ML16320A2082016-11-14014 November 2016 Notification of an NRC Triennial Fire Protection Baseline Inspection (NRC Inspection Report 05000416/2017008) and Request for Information IR 05000416/20160052016-09-12012 September 2016 Errata for Mid-Cycle Assessment Letter for Grand Gulf Nuclear Station (Report 05000416/2016005) IR 05000416/20164012016-08-31031 August 2016 Non-Public Security Inspection Plan for Grand Gulf Nuclear Station (NRC Physical Security Inspection Report Number 05000416/2016401) ML16242A3352016-08-31031 August 2016 Mid-Cycle Assessment Letter for Grand Gulf Nuclear Station (Report 05000416/2016005) IR 05000416/20150062016-03-0202 March 2016 Annual Assessment Letter for Grand Gulf Nuclear Station (Report 05000416/2015006) IR 05000416/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Grand Gulf Nuclear Station (Report 05000416/2015005) ML15132A7112015-05-11011 May 2015 Notification of NRC Component Design Bases Inspection (05000416/2015007) and Initial Request for Information IR 05000416/20144022014-09-0202 September 2014 Non-Public Security Inspection Plan for Grand Gulf Nuclear Station (NRC Physical Security Inspection Report Number 05000416/2014402) IR 05000416/20140062014-09-0202 September 2014 Mid-Cycle Assessment Letter for Grand Gulf Nuclear Station (Report 05000416/2014006) IR 05000416/20130012014-03-0404 March 2014 IR 05000416-13-001, 02/11/2014, Grand Gulf, Annual Assessment Letter ML13350A0362013-12-11011 December 2013 Notification of NRC Triennial Fire Protection Baseline Inspection (NRC Inspection Report 05000416-14-007) and Request for Information IR 05000416/20130062013-09-0303 September 2013 Mid-Cycle Assessment Letter for Grand Gulf Nuclear Station (Report 05000416/2013006) IR 05000416/20128012013-03-0404 March 2013 Annual Assessment Letter for Grand Gulf Nuclear Station (Report 05000416/2012801) IR 05000416/20120062012-09-0404 September 2012 Letter Mid-Cycle Assessment Letter for Grand Gulf Nuclear Station (Report 05000416-12-006) 2024-01-23
[Table view] Category:Letter
MONTHYEARML24012A1422024-01-31031 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0051 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000416/20230042024-01-25025 January 2024 Integrated Inspection Report 5000416/2023004 ML24018A0222024-01-18018 January 2024 Core Operating Limits Report (COLR) Cycle 24, Revision 2 IR 05000416/20243012024-01-16016 January 2024 NRC Initial Operator Licensing Examination Approval 05000416/2024301 ML24012A1962024-01-12012 January 2024 Response to 2nd Round Request for Additional Information Concerning Relief Request Number EN-RR-22-001 Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and ML23349A1672023-12-21021 December 2023 Request for Withholding Information from Public Disclosure ML23348A3572023-12-14014 December 2023 Application to Revise Technical Specifications to Use Online Monitoring Methodology Slides and Affidavit for Pre-Submittal Meeting ML23348A3712023-12-14014 December 2023 Notification of an NRC Fire Protection Baseline Inspection (NRC Inspection Report (05000416/2024011) and Request for Information ML23340A2222023-12-13013 December 2023 Project Manager Assignment ML23352A0292023-12-13013 December 2023 Entergy - 2024 Nuclear Energy Liability Evidence of Financial Protection ML23340A1592023-12-13013 December 2023 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment ML23333A1362023-11-29029 November 2023 Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23325A1422023-11-21021 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000416/20234032023-11-13013 November 2023 Security Baseline Inspection Report 05000416/2023403 Cover Letter ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV IR 05000416/20230032023-11-0808 November 2023 Integrated Inspection Report 05000416/2023003 ML23270B9932023-09-29029 September 2023 Request to Update ASME Boiler & Pressure Vessel Code Relief Request SE with NRC-Approved Revision of Bwrip Guidelines (GG-ISI-020 & RBS-ISI-019) (EPID L-2022-LLR-0090) - Non-Proprietary ML23270B1892023-09-27027 September 2023 Evacuation Time Estimate Study ML23269A1242023-09-27027 September 2023 Request for Withholding Information from Public Disclosure ML23240A3952023-08-28028 August 2023 Reply to a Notice of Violation; EA-23-019 IR 05000416/20230052023-08-21021 August 2023 Updated Inspection Plan for Grand Gulf Nuclear Station (Report 05000416/2023005) ML23226A1002023-08-18018 August 2023 Regulatory Audit in Support of License Amendment Requests to Adopt TSTF-505, Revision 2, and 10 CFR 50.69 IR 05000416/20230022023-08-0808 August 2023 Integrated Inspection Report 05000416/2023002 and Independent Spent Fuel Storage Installation Inspection Report 07200050/2023001 IR 05000416/20234042023-08-0707 August 2023 Material Control and Accounting Program Inspection Report 05000416/2023404 IR 05000416/20230912023-07-28028 July 2023 Final Significance Determination of a Green Finding and Notice of Violation; NRC Inspection Report 05000416/2023091 ML23208A2112023-07-27027 July 2023 Entergy Operations Inc., Application to Revise Technical Specifications to Adopt TSTF-205, Revision of Channel Calibration, Channel Functional Test, and Related Definitions ML23166B0712023-06-15015 June 2023 Reply to Notice of Violation EA-22-104 and EA-22-115 ML23166B0662023-06-15015 June 2023 Response to NRC Integrated Inspection Report 05000416/2023001 ML23159A2302023-06-0808 June 2023 Response to Request for Additional Information Concerning Request to Update ASME Code Relief Request Safety Evaluations with NRC-Approved Revision of BWRVIP Guidelines (GG-ISI-020, and RBS-ISI-019) GNRO-2023/00014, License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2023-06-0606 June 2023 License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b GNRO-2023/00015, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors2023-06-0606 June 2023 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors ML23122A1632023-05-18018 May 2023 NRC Inspection Report 05000416/2023090 and Preliminary White Finding IR 05000416/20234022023-05-17017 May 2023 Security Baseline Inspection Report 05000416/2023402 ML23110A8002023-05-10010 May 2023 Notice of Violation; Integrated Inspection Report 05000416/2023001 and NRC Investigation Report 4-2022-004 ML23130A2732023-05-10010 May 2023 and Waterford 3 Steam Electric Station - Response to Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000416/20230012023-05-10010 May 2023 Notice of Violation; Integrated Inspection Report 05000416/2023001 and NRC Investigation Report 4-2022-004 ML23117A2172023-05-0101 May 2023 Safety Evaluation for Quality Assurance Program Manual Reduction in Commitment ML23117A0422023-04-27027 April 2023 Annual Radioactive Effluent Release Report (ARERR) ML23111A2132023-04-21021 April 2023 Responses to RAI Concerning Relief Request Number EN-RR-22-001 Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and Treatment for Repair/ Replacement Activities ML23110A1122023-04-20020 April 2023 Annual Report for Entergy Quality Assurance Program Manual Changes Under 10 CFR 50.54(a)(3), 10 CFR 71.106, and 10 CFR 72.140(d). Notification of Application of Approved Appendix B to 10 CFR 72 Subpart G ML23110A0552023-04-20020 April 2023 Annual Radiological Environmental Operating Report (AREOR) ML23103A1022023-04-13013 April 2023 Annual Report of Individual Monitoring - NRC Form 5 for 2022 Per 10 CFR 20.2206 ML23102A1482023-04-12012 April 2023 Notification of NRC Initial Operator Licensing Examination 05000416/2024301 ML23089A0602023-03-30030 March 2023 Entergy Operations, Inc. - Fleet Project Manager Assignment ML23088A3922023-03-29029 March 2023 Nuclear Onsite Property Damage Insurance (10 CFR 50.54(w)(3)) ML23079A2772023-03-21021 March 2023 U.S. Nuclear Regulatory Commission Presentation at the May 1, 2023, Port Gibson City Council Meeting ML23080A2882023-03-21021 March 2023 Decommissioning Funding Status Report Per 10 CFR 50.75(f)(1) Entergy Operations, Inc IR 05000416/20230112023-03-0808 March 2023 Design Basis Assurance Inspection Report 05000416/2023011 2024-01-31
[Table view] |
Text
ust 30, 2019
SUBJECT:
UPDATED INSPECTION PLAN FOR GRAND GULF NUCLEAR STATION, REPORT 05000416/2019005
Dear Mr. Larson:
The enclosed inspection plan lists the inspections scheduled through June 30, 2021, for Grand Gulf Nuclear Station. The U.S. Nuclear Regulatory Commission (NRC) provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues.
Routine inspections performed by resident inspectors are not included in the inspection plan.
You should be aware that the agency is pursuing potential changes to the Reactor Oversight Process (ROP) including changes to engineering inspections (SECY-18-0113, Recommendations for Modifying the Reactor Oversight Process Engineering Inspections), and other changes to the baseline inspection program described in SECY-19-0067, Recommendations for Enhancing the Reactor Oversight Process. Should these changes to the ROP be implemented, the engineering and other region-based inspections are subject to change in scope, as well as schedule, beginning in January 2020. The inspections listed during the last 12 months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
As discussed in the 2018 annual assessment letter dated March 4, 2019 (ADAMS Accession No. ML19064A731), the NRC determined the performance at Grand Gulf Nuclear Station to be in the Regulatory Response Column (Column 2) of the Reactor Oversight Process Action Matrix beginning the third quarter of 2018. Therefore, the NRC plans to conduct a supplemental inspection in accordance with Inspection Procedure 95001, Supplemental Inspection Response to Action Matrix Column 2 Inputs. The objectives of the supplemental inspection are: (1) to assure that the root causes and contributing causes of significant performance issues are understood, (2) to independently assess and assure that the extent of condition and extent of cause of significant performance issues are identified, (3) to assure that corrective actions taken to address and preclude repetition of significant performance issues are prompt and effective, and (4) to assure that corrective plans direct prompt actions to effectively address and preclude repetition of significant performance issues. This inspection commenced during the week of August 26, 2019. From December 9, 2016, through August 14, 2019, the NRC issued 11 Severity Level IV traditional enforcement violations associated with impeding the regulatory process. In April of 2019, the NRC conducted an inspection to assess your evaluations and corrective actions associated with these issues using Inspection Procedure 92723, Follow Up Inspection for Three or More Severity Level IV Traditional Enforcement Violations in the Same Area in a 12-Month Period. Based on the results of this inspection that are documented in NRC Integrated Inspection Report 05000416/2019002 (ADAMS Accession No. ML19226A236) the NRC was not able to conclude that the actions taken were adequate to meet the inspection objectives.
Therefore, the NRC plans to perform an additional inspection that will be scheduled after you notify the NRC of your readiness.
On March 12, 2018, the NRC issued a Confirmatory Order (ADAMS Accession No.
ML18072A191) (EA-17-132 and EA-17-153) to the Entergy fleet that included Grand Gulf Nuclear Station. The NRC plans to conduct a Confirmatory Order follow-up inspection at Entergy Corporate Headquarters in Jackson, MS, of the Confirmatory Order actions required to be completed by the end of calendar year 2019, in accordance with Inspection Procedure 92702, Followup on Traditional Enforcement Actions Including Violations, Deviations, Confirmatory Action Letters, Confirmatory Orders, And Alternative Dispute Resolution Confirmatory Orders. This inspection will be conducted during the first quarter of 2020 on a date to be determined by the NRC and Entergy.
In the 2018 annual assessment letter, the NRC identified a cross-cutting theme in the Human Performance area. Specifically, 20 findings had a cross-cutting aspect in this area during the 2018 end-of-cycle assessment period. Because this theme criterion is no longer met as of the assessment period ending on June 30, 2019, the NRC has determined that a cross-cutting theme in the Human Performance area no longer exists.
In accordance with Title 10 of the Code of Federal Regulations (CFR) 2.390 of the NRCs Agency Rules of Practice and Procedure, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at (817) 200-1250 with any questions you have regarding this letter.
Sincerely,
/RA/
Cale H. Young, Acting Chief Project Branch C Division of Reactor Projects Docket No. 50-416 License No. NPF-29 Enclosure:
Inspection Plan
ML19234A356 SUNSI Review ADAMS: Non-Publicly Available Non-Sensitive Keyword:
By: DLP Yes No Publicly Available Sensitive OFFICE PBC:SPE PBC:C NAME DProulx CYoung SIGNATURE /RA/ /RA/
DATE 08/21/19 08/30/19
IP 22 Inspection Activity Plan Report 07200050 - Grand Gulf (ISFSI)
07/01/2019 - 06/30/2021 Unit Start End Activity CAC Title Staff Count Grand Gulf Loading Inspection (one week in month) 2 1 08/01/2019 10/31/2019 IP 60855 001001 Operation Of An ISFSI 1 08/01/2019 10/31/2019 IP 60857 001004 Review of 10 CFR 72.48 Evaluations This report does not include INPO and OUTAGE activities. Page 1 of 4 This report shows only on-site and announced inspection procedures.
8/23/2019 9:52:37 AM
IP 22 Inspection Activity Plan Report Grand Gulf 07/01/2019 - 06/30/2021 Unit Start End Activity CAC Title Staff Count 95001 Supplemental Inspection - 2 White PIs 4 1 07/08/2019 10/25/2019 IP 71152 000748 Problem Identification and Resolution 1 07/08/2019 11/25/2019 IP 71153 000749 Followup of Events and Notices of Enforcement Discretion 1 07/08/2019 10/11/2019 IP 95001 000938 Supplemental Inspection for One or Two White Inputs in a Strategic Performance Area GG 2019 BRQ 2 1 08/11/2019 08/17/2019 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance GRAND GULF DBA PROGRAM EQ INSPECTION 3 1 09/09/2019 09/27/2019 IP 71111.21N 000714 Design Bases Assurance Inspection (Programs)
Security Protective Strategy .05 2 1 09/09/2019 09/20/2019 IP 71130.05 000737 Protective Strategy Evaluation RP INSPECTION (1,3) 2 1 09/30/2019 10/04/2019 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1 09/30/2019 10/04/2019 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation GG ENTERGY CO FOLLOWUP - 2 3 1 12/01/2019 03/31/2020 IP 92702 CONF 001581 Enforcement Related Order Follow-Up-Only GG 2020 INITIAL EXAM 1 4 1 01/05/2020 01/11/2020 OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)
1 02/02/2020 02/08/2020 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)
Biennial PI&R Inspection 4 1 01/13/2020 01/17/2020 IP 71152B 000747 Problem Identification and Resolution 1 01/27/2020 01/31/2020 IP 71152B 000747 Problem Identification and Resolution Inservice Inspection RF22 - GG 1 1 03/02/2020 03/06/2020 IP 71111.08G 000701 Inservice Inspection Activities (BWR)
RS12PI Radiation Safety 2 1 03/02/2020 03/06/2020 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1 03/02/2020 03/06/2020 IP 71124.02 000726 Occupational ALARA Planning and Controls This report does not include INPO and OUTAGE activities. Page 2 of 4 This report shows only on-site and announced inspection procedures.
8/23/2019 9:52:37 AM
IP 22 Inspection Activity Plan Report Grand Gulf 07/01/2019 - 06/30/2021 Unit Start End Activity CAC Title Staff Count Security Access Control .02 1 1 06/15/2020 06/19/2020 IP 71130.02 000734 Access Control 1 06/15/2020 06/19/2020 IP 71151 001338 Performance Indicator Verification Security Equipment .04 and Training .07 2 1 07/20/2020 07/24/2020 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance 1 07/20/2020 07/24/2020 IP 71130.07 000739 Security Training Fire Protection Inspection - GG 3 1 08/10/2020 08/14/2020 IP 71111.21N.05 Fire Protection Team Inspection (FPTI)
1 08/24/2020 08/28/2020 IP 71111.21N.05 Fire Protection Team Inspection (FPTI)
GG 2020 INITIAL EXAM 2 0 1 09/13/2020 09/19/2020 OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)
1 10/18/2020 10/24/2020 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)
Grand Gulf 1 - Design Bases Assurance Inspection (Teams) 6 1 09/21/2020 10/09/2020 IP 71111.21M 000713 Design Bases Assurance Inspection (Teams)
EP Program Inspection 1 1 11/16/2020 11/20/2020 IP 71114.02 000717 Alert and Notification System Testing 1 11/16/2020 11/20/2020 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 1 11/16/2020 11/20/2020 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 1 11/16/2020 11/20/2020 IP 71114.05 000720 Maintenance of Emergency Preparedness 1 11/16/2020 11/20/2020 IP 71151 001397 Performance Indicator Verification RS5678 Radiation Safety PS Team 4 1 11/16/2020 11/20/2020 IP 71124.05 000729 Radiation Monitoring Instrumentation 1 11/16/2020 11/20/2020 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment 1 11/16/2020 11/20/2020 IP 71124.07 000731 Radiological Environmental Monitoring Program 1 11/16/2020 11/20/2020 IP 71124.08 000732 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation MC&A - Material Control & Accounting 1 1 11/16/2020 11/20/2020 IP 71130.11 000742 Material Control and Accounting (MC&A)
This report does not include INPO and OUTAGE activities. Page 3 of 4 This report shows only on-site and announced inspection procedures.
8/23/2019 9:52:37 AM
IP 22 Inspection Activity Plan Report Grand Gulf 07/01/2019 - 06/30/2021 Unit Start End Activity CAC Title Staff Count RP 2,4 2 1 02/15/2021 02/19/2021 IP 71124.02 000726 Occupational ALARA Planning and Controls 1 02/15/2021 02/19/2021 IP 71124.04 000728 Occupational Dose Assessment Security FFD .08 1 1 02/22/2021 02/26/2021 IP 71130.08 000740 Fitness For Duty Program EP Exercise and PI Inspection 4 1 03/15/2021 03/19/2021 IP 71114.01 000716 Exercise Evaluation 1 03/15/2021 03/19/2021 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 1 03/15/2021 03/19/2021 IP 71151 001397 Performance Indicator Verification FORCE-ON-FORCE PLANNING & EXERCISE 5 1 04/12/2021 04/16/2021 IP 71130.03 000735 Contingency Response - Force-On-Force Testing 1 05/03/2021 05/07/2021 IP 71130.03 000735 Contingency Response - Force-On-Force Testing RP 1,3,PI 2 1 04/19/2021 04/23/2021 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1 04/19/2021 04/23/2021 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 50.59 Inspection 17T - Grand Gulf 3 1 05/17/2021 05/21/2021 IP 71111.17T 000709 Evaluations of Changes, Tests, and Experiments Security Access Authorization .01 and Access Control .02 w/PIV 2 1 05/17/2021 05/21/2021 IP 71130.01 000733 Access Authorization 1 05/17/2021 05/21/2021 IP 71130.02 000734 Access Control 1 05/17/2021 05/21/2021 IP 71151 001338 Performance Indicator Verification This report does not include INPO and OUTAGE activities. Page 4 of 4 This report shows only on-site and announced inspection procedures.
8/23/2019 9:52:37 AM