|
---|
Category:Inspection Report
MONTHYEARIR 05000413/20230042024-02-0202 February 2024 Integrated Inspection Report 05000413-2023004 and 05000414-2023004 RA-23-0288, End of Cycle 27 (C1 R27) Steam Generator Tube Inspection Report2023-11-16016 November 2023 End of Cycle 27 (C1 R27) Steam Generator Tube Inspection Report IR 05000413/20230102023-10-11011 October 2023 NRC Inspection Report 05000413/2023010 and 05000414/2023010 IR 05000413/20230052023-08-25025 August 2023 Updated Inspection Plan for Catawba Nuclear Station Units 1 and 2 (Report 05000413/2023005 and 05000414/2023005) IR 05000413/20230022023-07-25025 July 2023 Integrated Inspection Report 05000413/2023002 and 05000414/2023002 IR 05000413/20230012023-05-0505 May 2023 Integrated Inspection Report 05000413/2023001 and 05000414/2023001 IR 05000413/20230112023-04-25025 April 2023 Focused Engineering Inspection Report 05000413/2023011 and 05000414/2023011 IR 05000413/20220062023-03-0101 March 2023 Annual Assessment Letter for Catawba Nuclear Station, Units 1 and 2 (NRC Inspection Report 05000413/2022006 and 05000414/2022006) IR 05000413/20234012023-03-0101 March 2023 Security Baseline Inspection Report 05000413 2023401 and 05000414 2023401 IR 05000413/20233012023-02-17017 February 2023 Operator Licensing Examination Approval 05000413/2023301 and 05000414/2023301 IR 05000413/20220042023-01-31031 January 2023 Integrated Inspection Report 05000413/2022004 and 05000414/2022004 IR 05000413/20220112022-12-15015 December 2022 Biennial Problem Identification and Resolution Inspection Report 05000413/2022011 and 05000414/2022011 IR 05000413/20224032022-11-17017 November 2022 Cyber Security Inspection Report 05000413/2022403 and 05000414/2022403 (Public) IR 05000414/20220032022-10-31031 October 2022 Integrated Inspection Report 05000414/2022003 and 05000414/2022003 IR 05000413/20224022022-10-28028 October 2022 Security Baseline Inspection Report 05000413 2022402 and 05000414 2022402 IR 05000413/20220052022-08-26026 August 2022 Updated Inspection Plan for Catawba Nuclear Station, Units 1 and 2 - NRC Inspection Report 05000413/2022005 and 05000414/2022005 IR 05000413/20220022022-07-29029 July 2022 Integrated Inspection Report 05000413/2022002 and 05000414/2022002 IR 07200045/20220012022-07-26026 July 2022 Operation of an Independent Spent Fuel Storage Installation Report 07200045/2022001 IR 05000413/20220102022-07-21021 July 2022 Design Basis Assurance Inspection (Programs) Inspection Report 05000413/2022010 and 05000414/2022010 IR 05000414/20220012022-04-28028 April 2022 Integrated Inspection Report 05000413/ 2022001 and 05000414/2022001 IR 05000413/20224202022-04-0707 April 2022 Security Inspection Report 05000413/2022420 and 05000414/2022420 RA-22-0080, Independent Spent Fuel Storage Installation, McGuire, Units 1 & 2, Independent Spent Fuel Storage Installation, Request for an Exemption to the Requirements of Certificate of Compliance No. 1031 for the NAC Magnastor Storage System2022-04-0707 April 2022 Independent Spent Fuel Storage Installation, McGuire, Units 1 & 2, Independent Spent Fuel Storage Installation, Request for an Exemption to the Requirements of Certificate of Compliance No. 1031 for the NAC Magnastor Storage System IR 05000413/20210062022-03-0202 March 2022 Annual Assessment Letter for Catawba Nuclear Station Units 1 and 2 (Report 05000413/2021006 and 05000414/2021006) IR 05000413/20224012022-02-18018 February 2022 Security Baseline Inspection Report 05000413/2022401 and 05000414/2022401 IR 05000413/20210042022-01-26026 January 2022 Integrated Inspection Report 05000413/2021004 and 05000414/2021004 ML22011A1802022-01-18018 January 2022 Review of the Spring 2021 Steam Generator Tube Inspection Report IR 05000413/20213012021-11-0808 November 2021 Operator Licensing Examination Report 05000413/2021301 and 05000414/2021301 IR 05000413/20214022021-11-0303 November 2021 Security Baseline Inspection Report 05000413/2021402 and 05000414/2021402 IR 05000413/20210032021-10-28028 October 2021 Integrated Inspection Report 05000413/2021003 and 05000414/2021003 IR 05000413/20210102021-09-27027 September 2021 Design Basis Assurance Inspection (Teams) Inspection Report 05000413/2021010 and 05000414/2021010 IR 05000413/20214042021-08-26026 August 2021 Material Control and Accounting Program Inspection Report 05000413/2021404 and 05000414/2021404 (OUO Removed) IR 05000413/20210022021-08-0505 August 2021 Integrated Inspection Report 05000413/2021002 and 05000414/2021002 IR 05000413/20210012021-04-29029 April 2021 Integrated Inspection Report 05000413/2021001 and 05000414/2021001 IR 05000413/20210112021-04-23023 April 2021 NRC Fire Protection Team Inspection Report 05000413/2021011 and 05000414/2021011 IR 05000413/20200062021-03-0303 March 2021 Annual Assessment Letter for Catawba Nuclear Station Units 1 and 2 - NRC Inspection Report 05000413/2020006 and 05000414/2020006 IR 05000413/20214012021-02-26026 February 2021 Security Baseline Inspection Report 05000413/2021401 and 05000414/2021401 IR 05000413/20200042021-01-28028 January 2021 Integrated Inspection Report 05000413/2020004 and 05000414/2020004 IR 05000413/20200112020-12-18018 December 2020 Biennial Problem Identification and Resolution Inspection Report 05000413/2020011 and 05000414/2020011 Dated December 18, 2020 IR 05000413/20204012020-11-23023 November 2020 Security Aseline Inspection Report 05000413/2020401 and 05000414/2020401 IR 05000413/20200032020-10-30030 October 2020 Integrated Inspection Report 05000413/2020003, 05000414/2020003 and 07200045/2020002 IR 05000413/20200052020-08-17017 August 2020 Updated Inspection Plan for Catawba Nuclear Station Units 1 and 2 (NRC Inspection Report 05000413/2020005 and 05000414/2020005) IR 05000413/20200022020-08-0303 August 2020 Integrated Inspection Report 05000413/2020002, 05000414/2020002 and 07200045/2020001 IR 05000413/20200012020-04-28028 April 2020 Integrated Inspection Report 05000413/2020001 and 05000414/2020001 IR 05000413/20200102020-03-10010 March 2020 Triennial Inspection of Evaluation of Changes, Tests and Experiments Baseline Inspection Report 05000413/2020010 and 05000414/2020010 IR 05000413/20190062020-03-0303 March 2020 Annual Assessment Letter for Catawba Nuclear Station Units 1 and 2 - NRC Inspection Report 05000413/2019006 and 05000414/2019006 IR 05000413/20190042020-01-27027 January 2020 Integrated Report 05000413/2019004 and 05000414/2019004 IR 05000413/20190102020-01-0909 January 2020 Reissue Catawba - Design Basis Assurance Inspection (Programs) Inspection Report 05000413/2019010 and 05000414/2019010 ML19354A8562019-12-20020 December 2019 Design Basis Assurance Inspection (Programs) Inspection Report 0500413/2019010 and 05000414/2019010 IR 05000413/20194112019-11-26026 November 2019 U.S. Nuclear Regulatory Commission Security Inspection Report 05000413/2019411 and 05000414/2019411 IR 05000413/20190032019-11-0707 November 2019 Integrated Inspection Report 05000413/2019003 and 05000414/2019003 2024-02-02
[Table view] Category:Letter
MONTHYEARIR 05000413/20230042024-02-0202 February 2024 Integrated Inspection Report 05000413-2023004 and 05000414-2023004 ML24005A2512024-01-26026 January 2024 Exemption from Select Requirements of 10 CFR Part 73 - Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting ML23317A3462023-11-14014 November 2023 Duke Fleet - Correction Letter to License Amendment Nos. 312 & 340 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000413/20230102023-10-11011 October 2023 NRC Inspection Report 05000413/2023010 and 05000414/2023010 ML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds ML23195A0782023-08-29029 August 2023 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000413/20230052023-08-25025 August 2023 Updated Inspection Plan for Catawba Nuclear Station Units 1 and 2 (Report 05000413/2023005 and 05000414/2023005) ML23233A1692023-08-17017 August 2023 EN 56683 - Curtiss Wright, Interim Notification Report for PotentialPurt2l IR 05000413/20230022023-07-25025 July 2023 Integrated Inspection Report 05000413/2023002 and 05000414/2023002 ML23207A0762023-07-14014 July 2023 EN 56557 - Update to Part 21 Report Re Potential Defect with Trane External Auto/Stop Emergency Stop Relay Card Pn: XI2650728-06 ML23237A2672023-06-13013 June 2023 June 13, 2002 - Meeting Announcement - McGuire and Catawba Nuclear Stations 50-369, 50-370 and 50-413, 50-414 ML23159A0052023-06-0505 June 2023 56557-EN 56557 - Paragon - Redlined IR 05000413/20230012023-05-0505 May 2023 Integrated Inspection Report 05000413/2023001 and 05000414/2023001 ML23118A0762023-05-0101 May 2023 Approval for Use of Specific Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI IR 05000413/20230112023-04-25025 April 2023 Focused Engineering Inspection Report 05000413/2023011 and 05000414/2023011 ML23107A2542023-04-14014 April 2023 301 Examination Report Letter and Report (Merged) ML22332A4932023-03-10010 March 2023 William States Lee III 1 and 2 - Issuance of Amendments Regarding the Relocation of the Emergency Operations Facility IR 05000413/20234012023-03-0101 March 2023 Security Baseline Inspection Report 05000413 2023401 and 05000414 2023401 IR 05000413/20220062023-03-0101 March 2023 Annual Assessment Letter for Catawba Nuclear Station, Units 1 and 2 (NRC Inspection Report 05000413/2022006 and 05000414/2022006) IR 05000413/20233012023-02-17017 February 2023 Operator Licensing Examination Approval 05000413/2023301 and 05000414/2023301 IR 05000413/20220042023-01-31031 January 2023 Integrated Inspection Report 05000413/2022004 and 05000414/2022004 IR 05000413/20220112022-12-15015 December 2022 Biennial Problem Identification and Resolution Inspection Report 05000413/2022011 and 05000414/2022011 ML22356A0512022-12-14014 December 2022 Curtiss-Wright Nuclear Division, Letter Regarding Potential Efect in a Configuration of the 11/2 Inch Quick Disconnect Connector Cable Assemblies Supplied to Duke Energy (See Attached Spreadsheet) for a Total of 460 of Connectors Only Suppl ML22096A0032022-11-18018 November 2022 McGuire Nuclear Station and Shearon Harris Nuclear Power Plant Authorization of RA-19-0352 Regarding Use of Alternative for RPV Head Closure Stud Examinations IR 05000413/20224032022-11-17017 November 2022 Cyber Security Inspection Report 05000413/2022403 and 05000414/2022403 (Public) ML22256A2532022-11-14014 November 2022 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-541, Rev. 2 ML22319A0942022-11-10010 November 2022 EN 56219 - Flowserve. 10 CFR Part 21 Report 38878-8 Solenoid Valve at Duke, Catawba Flowserve Evaluation 105 IR 05000414/20220032022-10-31031 October 2022 Integrated Inspection Report 05000414/2022003 and 05000414/2022003 IR 05000413/20224022022-10-28028 October 2022 Security Baseline Inspection Report 05000413 2022402 and 05000414 2022402 ML22276A2492022-10-25025 October 2022 Completion of License Renewal Commitment No. 10, Aging Management of Environmentally Assisted Fatigue ML22297A2642022-10-25025 October 2022 Project Manager Assignment ML22303A0052022-10-24024 October 2022 EN 56178 - Tioga Final. LTR-TP-22-29 2021 10CFR Part 21 Improper Notification of NRC ML22258A0302022-09-15015 September 2022 Evacuation Time Estimate Reports ML22242A0022022-09-12012 September 2022 Issuance of Amendments to Adopt TSTF 569, Revision 2, Revise Response Time Testing Definition ML22231B1362022-09-0101 September 2022 Review of the Draft Environmental Assessment and Findings of No Significant Impact for Catawba Nuclear Station, H.B. Robinson Steam Electric Plant, and Oconee Nuclear Station Independent Spent Fuel Storage Installation Decommissioning Fundi ML22303A0042022-08-31031 August 2022 Final Report Notification Pursuant to 10 CFR Part 21.21, Regarding Supply of 6 NPS Sch. 40 Seamless Stainless-Steel Pipe; Manufacturer: Maxim Tubes Company Pvt. Ltd.; Heat No: N200309AW01, SR No: 7; 9 Pcs; 180 Feet Total Procured as Unquali IR 05000413/20220052022-08-26026 August 2022 Updated Inspection Plan for Catawba Nuclear Station, Units 1 and 2 - NRC Inspection Report 05000413/2022005 and 05000414/2022005 ML22217A0792022-08-0303 August 2022 301, Corporate Notification Letter (210-day Ltr) IR 05000413/20220022022-07-29029 July 2022 Integrated Inspection Report 05000413/2022002 and 05000414/2022002 IR 07200045/20220012022-07-26026 July 2022 Operation of an Independent Spent Fuel Storage Installation Report 07200045/2022001 ML22215A2502022-07-25025 July 2022 EN 55960 - Update - Curtiss Wright IR 05000413/20220102022-07-21021 July 2022 Design Basis Assurance Inspection (Programs) Inspection Report 05000413/2022010 and 05000414/2022010 ML22164A0362022-07-19019 July 2022 Mcguire Nuclear Station, Units 1 and 2; Issuance of Amendments to Revise the Conditional Exemption of the End-Of-Cycle Moderator Temperature Coefficient Measurement Methodology (EPID L-2021-LLA-0198) Public ML22195A2432022-07-19019 July 2022 Request for Withholding Information from Public Disclosure Regarding Reactor Vessel Closure Head Repair Alternative ML22199A2552022-07-0606 July 2022 Ds Catawba 2022 RQ Inspection Notification Letter ML22222A0092022-07-0101 July 2022 EN 55974 - Flowserve, Part 21 Report Re Solenoid Coil Failure of Model 38878-8 Solenoid Valve at Catawba Nuclear Station for Use on FWIV Actuator ML22175A0342022-06-28028 June 2022 Information Request for the Cyber-Security Baseline Inspection Notification to Perform Inspection 05000413/2022403 and 05000414/2022403 ML22046A0222022-06-14014 June 2022 Issuance of Amendments to Adopt TSTF-439, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an LCO ML22111A3572022-05-16016 May 2022 Letter Issuing Exemption to Catawba IR 05000414/20220012022-04-28028 April 2022 Integrated Inspection Report 05000413/ 2022001 and 05000414/2022001 2024-02-02
[Table view] |
Inspection Report - Catawba - 2020010 |
---|
|
|
Text
March 10, 2020
SUBJECT:
CATAWBA NUCLEAR STATION - TRIENNIAL INSPECTION OF EVALUATION OF CHANGES, TESTS AND EXPERIMENTS BASELINE INSPECTION REPORT 05000413/2020010 AND 05000414/2020010
Dear Mr. Simril:
On February 6, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Catawba Nuclear Station and discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA/
James B. Baptist, Chief Engineering Branch 1 Division of Reactor Safety Docket Nos. 05000413 and 05000414 License Nos. NPF-35 and NPF-52
Enclosure:
As stated
Inspection Report
Docket Numbers: 05000413 and 05000414 License Numbers: NPF-35 and NPF-52 Report Numbers: 05000413/2020010 and 05000414/2020010 Enterprise Identifier: I-2020-010-0037 Licensee: Duke Energy Carolinas, LLC Facility: Catawba Nuclear Station Location: York, SC Inspection Dates: February 03, 2020 to February 06, 2020 Inspectors: N. Morgan, Reactor Inspector M. Riley, Reactor Inspector A. Ruh, Resident Inspector Approved By: James B. Baptist, Chief Engineering Branch 1 Division of Reactor Safety Enclosure
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a triennial inspection of evaluation of changes, tests and experiments baseline inspection at Catawba Nuclear Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
REACTOR SAFETY
71111.17T - Evaluations of Changes, Tests, and Experiments Sample Selection (IP Section 02.01)
Main article: IP 71111.17
The inspectors reviewed the following evaluations, screenings, and/or applicability determinations for 10 CFR 50.59 from February 3 - 6, 2020.
- (1) Evaluation AR 02104045, Revised SG (Steam Generator) PORV (Power Operated Relief Valve) Flow Rates & Post-MSLB (Main Steam Line Break) Cool-down
- (2) Evaluation AR 02236975, CNS (Catawba Nuclear Station) U1 (Unit 1) Turbine Trip and Feedwater System Pipe Break
- (3) Evaluation AR 02245001, CNS UFSAR (Updated Final Safety Analysis Report)
Chapter 15.4.7 Inadvertent Loading and Operation of a Fuel Assembly
- (4) Evaluation AR 01962944, Revision to Methodology Report DPC-NE-2009-P-A
- (5) Evaluation AR 02047559, Revision to Methodology Report DPC-NE-2009-P-A
- (6) Evaluation AR 02085006, VIPRE Upgrade from Mod. 2r to Mod. 2.5adke
- (7) Evaluation AR 02110981, Update to Catawba Nuclear Station UFSAR Table 15-14
- (8) Evaluation AR 02213061, Addition of an External Constituent to the Control Room
- (9) Screen EC 402534, Optional Hydraulic Accumulator to be installed on 1CF33, 1CF51, 1CF60, 2CF33, 2CF42, 2CF51, and 2CF60
- (10) Screen EC 412812, Generate Test Acceptance Criteria for Reactor Vessel Vents Flow Rate
- (11) Screen EC 411844, Degraded Bus Timer Setpoint
- (12) Screen EC 108311, Replace Valves 2NV202B and 2NV203A to Gain Operating Margin
- (13) Screen EC 94585, Replace D/G (Emergency Diesel Generator) 2A Voltage Regulator/Excitation System
- (14) Screen EC 114179, UNIT 2: Removal of SPV (Single Point Vulnerability) at A518 Pin 24 In SSPS (Solid State Protection System) Logic Cabinets for Train A & B on Unit 2
- (15) Screen EC 408742, NW (Containment Valve Injection Water) Group 2: Convert to Type C Leak Rate Testing
- (16) Screen EC 408429, ESF (Engineered Safety Feature) Backleakage to FWST (Refueling Water Storage Tank) and Leakage in Aux. Bldg.
- (17) Screen EC 415036, Changes to the VQ (Containment Air Release and Addition)
Containment Pressure Annunciator
- (18) Screen EC 411492, Replacement of 2NW8A, 2NW20A, 2NW61B, 2NW69B Valve and Operator due to Solenoid Failures
- (19) Screen EC 413660, Large NC (Reactor Coolant) System Vent - Remove 3 Pressurizer Safety Valves
- (20) Applicability Determination AR 2287956, PT/1/A/4250/006 B - 0000215277 CA (Auxiliary Feedwater) System Flow Verification
INSPECTION RESULTS
No findings were identified.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On February 6, 2020, the inspectors presented the triennial inspection of evaluation of changes, tests and experiments baseline inspection results to Robert T. Simril and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection Type Designation Description or Title Revision or
Procedure Date
71111.17T Calculations CNC-1201.30-00- Determination of NC System Cooldown Time Following a Rev. 3
27 Main Steam Line Break
CNC-1223.03-00- Determination of Unit 2 Reactor Vessel Head Vent Flow Rev. 0
0038
CNC-1223.19-00- NW System Setpoint Calculation Rev. 9
0004
CNC-1223.21-00- Post-Accident FWST In-Leakage Sources Rev. 0
22
CNC-1223.43-01- Main Steam Power Operated Relief Valve Flow Capacity Rev. 0
27
CNC-1227.00-00- Radiological Consequences of a DB LOCA at Catawba Rev. 16
0106 Nuclear Station
CNC-1227.00-00- Radiological Consequences of a DB MSLB at Catawba Rev. 11
0130 Nuclear Station
CNC-1381.05-00- 4160 Volt Essential Auxiliary Power Switchgear Relay Rev. 17
0012 Settings (Type I Changed to Type III)
CNC-2206.02-83- Chemical and Volume Control System Rigorous Stress Rev. 9
2011 Analysis Problem NVI
DPC-1552.08-00- RSG FSAR Analyses - 15.2.3 - Turbine Trip Rev. 8
0134
DPC-1552.08-00- RSG FSAR Analyses - 15.2.8 - Feedwater System Pipe Rev. 4
0140 Break
Corrective Action AR 01962944 Revision to Methodology Report DPC-NE-2009-P-A 11/03/2015
Documents AR 02047559 Revision to Methodology Report DPC-NE-2009-P-A 04/20/2017
AR 02085006 VIPRE upgrade from mod 2r to mod 2.5adke 03/06/2017
AR 02104045 Revised SG PORV Flow Rates & Post-MSLB Cool-down 05/31/2017
AR 02110981 Update to Catawba Nuclear Station UFSAR Table 15-14 01/23/2018
AR 02213061 Addition of an External Constituent to the Control Room 07/18/2018
AR 02236975 CNS U1 Turbine Trip and Feedwater System Pipe Break 01/31/2019
AR 02245001 CNS UFSAR Chapter 15.4.7 Inadvertent Loading and 11/27/2018
Operation of a Fuel Assembly
AR 2287956 PT/1/A/4250/006 B - 0000215277 CA System Flow 08/21/2019
Inspection Type Designation Description or Title Revision or
Procedure Date
Verification Applicability Determination
ARs
1897290
1901154
1949424
1956237
1962944
2047559
2096392
2152427
2159141
25766
25774
251416
287953
287956
2085003
Corrective Action AR 2314794 2020 50.59 EC 408742 UFSAR Update 02/06/2020
Documents
Resulting from
Inspection
Drawings CN-1578-01.00 Flow Diagram of Control Room Area Ventilation System Rev. 31
(VC)
CN-1602-01.00 Flow Diagram of Nitrogen System (GN) Rev. 30
CN-2569-01.00 Flow Diagram of Containment Valve Injection Water Rev. 30
System (NW)
CN-2605-01.00 Flow Diagram of Instrument Air System (VI) Rev. 11
CNM 1205.06- Outline Drawing for CMV-868, 1" FO Fisher Air Oper Rev. 0
0492.001 Globe Valve
CNM 1205.06- Valve and Actuator Instruction Manual for CMV-868 and Rev. 0
0493.001 CMV-869, 1" and 2" FO Fisher Globe Valve
Engineering 108311 Replace Valves 2NV202B and 2NV203A to Gain Rev. 2
Changes Operating Margin
114179 Unit 2 Removal of SPV at A518 Pin 24 in SSPS Logic Rev. 0
Inspection Type Designation Description or Title Revision or
Procedure Date
Cabinets for Train A&B
2534 Optional Hydraulic Accumulator to be Installed on 1CF33, Rev. 0
1CF51, 1CF60, 2CF33, 2CF42, 2CF51, and 2CF60
408429 ESF Backleakage to FWST and Leakage in Aux Bldg. Rev. 0
Revise FW, NV, NI, ND, NS DBD, TS Basis, UFSAR
408429 ESF Backleakage to FWST and Leakage in Aux Building; Rev. 0
Revise FW, NV, NI, ND, NS DBD, TS Basis, UFSAR
408742 Convert the Group 2 containment isolation valves (CIVs) Rev. 0
from NW Testing
to C-Leak Rate Testing (C-LRT)
408742 NW Group 2: Convert to Type C Leak Rate Testing Rev. 0
411844 Degraded Bus Timer Setpoint Change Rev. 0
2812 Generate Test Acceptance Criteria for Reactor Vessel Rev. 0
Vents Flow Rate
413660 Large NC System Vent - Remove 3 PZR Safety Valves Rev. 0
94585 Replace D/G 2A Voltage Regulator/Excitation System Rev. 7
Miscellaneous CNEI-0400-341 Catawba 1 Cycle 25 Core Operating Limits Report Rev. 1
CNEI-0400-355 Catawba 2 Cycle 24 Core Operating Limits Report Rev. 0
CNM 1205.06- Weak Link Analysis for CMV-868 & CMV-869, 1" & 2" FO 12/02/2019
0498.001 Fisher Air Oper Globe Valve
CNM 1205.06- Valve Actuator Sizing for CMV-868. 1" FO Fisher Air Oper 12/02/2019
0499.001 Globe Valve
CNM 1301.00- Failure Mode & Effects Analysis of Voltage Regulator Rev. 1
0449.001 System/Chassis P/N: 72-10800-100-ESI
CNR-1205.06-00- Technical Requirements for Containment Valve Injection Rev. 1
0011 Water (NW) System Surge Tank RN Supply Valves and
Surge Tank Outlet Valves
CNS-1553.NC-00- Reactor Coolant System (NC) Design Basis Specification Rev. 46
0001
CNS-1569.NW-00- Containment Valve Injection Water System (NW) Design Rev. 22
0001 Basis Document
CNS-1578-VC.00- Control Room Ventilation Design Basis Specification Rev. 39
0001
CNTC-1571- Primary Coolant Leakage Sources Outside Containment Rev. 0
Inspection Type Designation Description or Title Revision or
Procedure Date
FW.S001-01
CNTC-2571- Primary Coolant Leakage Sources Outside Containment Rev. 0
FW.S001-01
DPC-NE-2009-PA Duke Power Company Westinghouse Fuel Transition Rev. 3a, b, c
Report
DPC-NE-3002-A UFSAR Chapter 15 System Transient Analysis Rev. 4C
Methodology
DPND-DPC-NE- Thermal-Hydraulic Statistical Core Design Methodology - 10/27/2016
2005-A Non-Proprietary - Replaces DPND-DPC-NE-2005-PA -
Initial Issue
UFSAR Section Inadvertent Loading and Operation of a Fuel Assembly Rev. 20
15.4.7
WCAP-12610-P-A & Optimized ZIRLO(tm) 07/2006
CENPD-404-P-A
Addendum 1-A
WCAP-8963-P-A Safety Analysis for the Revised Fuel Rod Internal Rev. 1-A
Addendum 1-A Pressure Design Basis (Departure from Nucleate Boiling
Mechanistic Propagation Methodology)
Procedures AD-LS-ALL-0007 Applicability Determination Process Rev. 6
EP/1/A/5000/E-0 Reactor Trip or Safety Injection Rev. 44
IP/0/A/4971/005 Degraded Bus Voltage Trip and Alarm Timers Calibration Rev. 8
Procedure
OP/1/A/6200/014 Refueling Water System Rev. 91
OP/2/A/6200/019 Containment Valve Injection Water System Rev. 40
PT/0/A/4150/022 Total Core Reloading Rev. 59
PT/0/A/4550/003 C Core Verification Rev. 20
PT/1/A/4200/001 C As Left Containment Isolation Valve Leak Rate Test Rev. 132
PT/1/A/4200/001 K Summation of Recirculation Backleakage to FWST Rev. 0
PT/1/A/4200/001 L Controlling Procedure For Type B & C Leak Rate Tests Rev. 33
PT/1/A/4200/001 T Containment Penetration Valve Injection Water System Rev. 76
Performance Test
PT/1/A/4200/018 B CF Valve Inservice Test (CS) Rev. 41
PT/1/A/4200/027 NW Valve Inservice Test (QU) Rev. 53
PT/1/A/4250/006 B CA System Flow Verification Test Rev. 24, 25
Inspection Type Designation Description or Title Revision or
Procedure Date
PT/2/A/4200/013 NV Valve Inservice Test (UNK) Rev. 31
PT/2/A/4350/002A Diesel Generator 2A Operability Test 08/27/2019
PT/2/A/4350/012A Diesel Generator 2A Governor and Voltage Regulator 09/27/2019
Test
PT/2/A/4350/015A Diesel Generator 2A Periodic Test 09/27/2019
Pump and Valve Pump and Valve Inservice Testing Program Manual Rev. 33
Inservice
TN/2/A/EC94585/01E Implementation of Diesel Generator 2A Voltage Regulator Rev. 3
Replacement
TT/2/A/9300/081 NV Pump Miniflow Line Verification Rev. 0
TT/2/A/EC94585/01E Test Procedure for Diesel Generator 2A Voltage Rev. 2
Regulatory Replacement
Work Orders 02198745
20189558-01
2560010
290927-01
290968-01
292012-01
294822-01, 02
20311516-01
20329544-01
20344519
9