MONTHYEARIR 05000397/20230042024-01-29029 January 2024 Integrated Inspection and Independent Spent Fuel Storage Installation Report 05000397/2023004 and 07200035/2023001 IR 05000397/20230122023-11-20020 November 2023 Commercial Grade Dedication Inspection Report 05000397/2023012 IR 05000397/20230102023-11-0909 November 2023 Biennial Problem Identification and Resolution Inspection Report 05000397/2023010 IR 05000397/20230932023-11-0101 November 2023 Final Significance Determination of a White Finding, Notice of Violation and Follow-Up Assessment Letter; NRC Inspection Report 05000397/2023093 ML23299A2072023-10-26026 October 2023 Biennial Requalification Inspection Request for Information IR 05000397/20230032023-10-25025 October 2023 Integrated Inspection Report 05000397/2023003 IR 05000397/20230112023-10-0404 October 2023 License Renewal Phase 2 Report 05000397/2023011 IR 05000397/20234012023-09-11011 September 2023 Security Baseline Inspection Report 05000397/2023401 IR 05000397/20230052023-08-22022 August 2023 Updated Inspection Plan for Columbia Generating Station (Report 05000397/2023005) - Mid Year Letter IR 05000397/20230022023-08-0101 August 2023 Integrated Inspection Report 05000397/2023002 IR 05000397/20230922023-06-0101 June 2023 NRC Inspection Report 05000397/2023092 and Preliminary White Finding IR 05000397/20230902023-06-0101 June 2023 Final Significance Determination of a White Finding, Notice of Violation and Follow-Up Assessment Letter; NRC Inspection Report 05000397/2023090 IR 05000397/20230012023-05-0505 May 2023 Integrated Inspection Report 05000397/2023001 - April 26, 2023 IR 05000397/20233012023-05-0101 May 2023 NRC Examination Report 05000397/2023301 IR 05000397/20220062023-03-0101 March 2023 Annual Assessment Letter for Columbia Generating Station (Report 05000397/2022006) IR 05000397/20234022023-02-23023 February 2023 NRC Security Baseline Inspection Report 050003972023402 (Full Report) IR 05000397/20220042023-01-23023 January 2023 Integrated Inspection Report 05000397/2022004- 4th Quarter IR 05000397/20224062023-01-18018 January 2023 NRC Security Baseline Inspection Report 05000397/2022406 (Cover Letter) IR 05000397/20224042023-01-17017 January 2023 Amended - Columbia Generating Station - Security Baseline Inspection Report 05000397/2022404 (Public) IR 05000397/20224012022-11-12012 November 2022 Cyber Security Inspection Report 05000397/2022401 (Cover Letter Only) IR 05000397/20220032022-10-31031 October 2022 Integrated Inspection Report 05000397/2022003 IR 05000397/20224052022-09-15015 September 2022 Material Control and Accounting Program Inspection Report 05000397 2022405 Cover Ltr Only IR 05000397/20224032022-09-0101 September 2022 NRC Security Inspection Report 05000397/2022403 (Full Report) IR 05000397/20220022022-07-28028 July 2022 and Independent Spent Fuel Storage Installation - Integrated Inspection Report 05000397/2022002 and 07200035/2022001 IR 05000397/20220102022-06-30030 June 2022 Design Basis Assurance Inspection (Team) Inspection Report 05000397/2022010 IR 05000397/20224022022-06-23023 June 2022 Security Baseline Inspection Report 05000397/2022402 IR 05000397/20220012022-04-29029 April 2022 Integrated Inspection Report 05000397/2022001 IR 05000397/20210062022-03-0202 March 2022 Annual Assessment Letter for Columbia Generating Station (Report 05000397/2021006) IR 05000397/20210042022-01-20020 January 2022 Integrated Inspection Report 05000397/2021004 IR 05000397/20214012022-01-19019 January 2022 Security Baseline Inspection Report 05000397/2021401 IR 05000397/20210902022-01-13013 January 2022 NRC Inspection Report 05000397/2021090 and Preliminary White Finding IR 05000397/20214202021-11-0404 November 2021 Security Baseline Inspection Report-Cover Letter - 05000397/2021420 IR 05000397/20210122021-11-0303 November 2021 Design Basis Assurance Inspection (Programs) Inspection Report 05000397/2021012 IR 05000397/20210032021-11-0202 November 2021 Integrated Inspection Report 05000397/2021003 IR 05000397/20210112021-09-21021 September 2021 Triennial Fire Protection Inspection Report 05000397/2021011 IR 05000397/20214022021-09-0909 September 2021 Security Baseline Inspection Report 05000397/2021402 IR 05000397/20210102021-08-29029 August 2021 Biennial Problem Identification and Resolution Inspection Report 05000397/2021010 IR 05000397/20210022021-08-0202 August 2021 Integrated Inspection Report 05000397/2021002 IR 05000397/20210132021-07-20020 July 2021 NRC Post - Approval Site Inspection for License Renewal (Phase I) Inspection Report 05000397/2021013 ML21141A1752021-05-24024 May 2021 Notification of NRC Design Bases Assurance Inspection (Programs) (05000397/2021012) and Initial Request for Information IR 05000397/20210012021-05-0707 May 2021 CGS2021001-IR-NH, Columbia Generating Station - Integrated Inspection Report 05000397/2021001 IR 05000397/20213012021-04-21021 April 2021 NRC Exam Report 05000397/2021301 IR 07200035/20214012021-03-25025 March 2021 Independent Spent Fuel Storage Installation Nrc Security Inspection Report 07200035/2021401 IR 05000397/20200062021-03-0303 March 2021 Annual Assessment Letter for Columbia Generating Station (Report 05000397/2020006) IR 05000397/20200042021-02-0303 February 2021 Integrated Inspection Report 05000397/2020004 IR 05000397/20200032020-12-21021 December 2020 Revised Integrated Inspection Report 05000397/2020003 ML20302A2312020-10-28028 October 2020 Integrated Inspection Report 05000397/2020003 IR 05000397/20204112020-09-28028 September 2020 Security Baseline Inspection Report 05000397/2020411 IR 05000397/20200052020-09-0101 September 2020 Updated Inspection Plan for Columbia Generating Station (Report 05000397/2020005) IR 05000397/20200022020-07-29029 July 2020 Integrated Inspection Report 05000397/2020002 2024-01-29
[Table view] Category:Letter
MONTHYEARGO2-24-004, License Amendment Request to Revise Emergency Plan2024-01-30030 January 2024 License Amendment Request to Revise Emergency Plan IR 05000397/20230042024-01-29029 January 2024 Integrated Inspection and Independent Spent Fuel Storage Installation Report 05000397/2023004 and 07200035/2023001 GO2-24-003, Relief Requests for the Columbia Generating Station Fifth Ten-Year Interval Inservice Testing2024-01-29029 January 2024 Relief Requests for the Columbia Generating Station Fifth Ten-Year Interval Inservice Testing ML24011A1522024-01-10010 January 2024 March 2024 Emergency Preparedness Exercise Inspection-Request for Information GO2-24-005, Docket No. 50-397 Supplement to Reply to a Notice of Violation; EA-21-1702024-01-0808 January 2024 Docket No. 50-397 Supplement to Reply to a Notice of Violation; EA-21-170 GO2-23-136, Guarantee of Payment of Deferred Premium2023-12-20020 December 2023 Guarantee of Payment of Deferred Premium GO2-23-135, Notice of Readiness for Supplemental Inspection2023-12-14014 December 2023 Notice of Readiness for Supplemental Inspection GO2-23-130, Reply to a Notice of Violation; EA-23-0542023-12-14014 December 2023 Reply to a Notice of Violation; EA-23-054 GO2-23-105, Licensing Basis Document Update and Biennial Commitment Change Report2023-12-12012 December 2023 Licensing Basis Document Update and Biennial Commitment Change Report ML23288A0002023-12-0707 December 2023 Issuance of Amendment No. 272 to Adopt TSTF-541, Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position GO2-23-107, Application to Revise Technical Specifications to Adopt TSTS-584, Eliminate Automatic RWCU System Isolation on SLC Initiation2023-12-0505 December 2023 Application to Revise Technical Specifications to Adopt TSTS-584, Eliminate Automatic RWCU System Isolation on SLC Initiation GO2-23-126, Docket No. 50-397 Voluntary Response to Regulatory Issue Summary 2023-012023-11-28028 November 2023 Docket No. 50-397 Voluntary Response to Regulatory Issue Summary 2023-01 GO2-23-121, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-11-27027 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000397/20230122023-11-20020 November 2023 Commercial Grade Dedication Inspection Report 05000397/2023012 ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV IR 05000397/20230102023-11-0909 November 2023 Biennial Problem Identification and Resolution Inspection Report 05000397/2023010 IR 05000397/20230932023-11-0101 November 2023 Final Significance Determination of a White Finding, Notice of Violation and Follow-Up Assessment Letter; NRC Inspection Report 05000397/2023093 ML23299A2072023-10-26026 October 2023 Biennial Requalification Inspection Request for Information IR 05000397/20230032023-10-25025 October 2023 Integrated Inspection Report 05000397/2023003 IR 05000397/20230112023-10-0404 October 2023 License Renewal Phase 2 Report 05000397/2023011 IR 05000397/20234012023-09-11011 September 2023 Security Baseline Inspection Report 05000397/2023401 GO2-23-097, In-Service Inspection Summary Report for the Twenty-Sixth Refueling Outage (R26)2023-09-0606 September 2023 In-Service Inspection Summary Report for the Twenty-Sixth Refueling Outage (R26) ML24032A2182023-09-0101 September 2023 Information Request, Security IR 2024401 GO2-23-100, Technical Specification Section 5.6.4 Post Accident Monitoring Instrumentation 14-Day Report for Inoperable Suppression Pool Level Indication2023-08-31031 August 2023 Technical Specification Section 5.6.4 Post Accident Monitoring Instrumentation 14-Day Report for Inoperable Suppression Pool Level Indication GO2-23-056, Application to Revise Technical Specifications to Adopt TSTF-230, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling2023-08-29029 August 2023 Application to Revise Technical Specifications to Adopt TSTF-230, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling IR 05000397/20230052023-08-22022 August 2023 Updated Inspection Plan for Columbia Generating Station (Report 05000397/2023005) - Mid Year Letter IR 05000397/20230022023-08-0101 August 2023 Integrated Inspection Report 05000397/2023002 GO2-23-093, Supplement to Reply to a Notice of Violation: EA-21-1702023-07-27027 July 2023 Supplement to Reply to a Notice of Violation: EA-21-170 ML23206A2442023-07-25025 July 2023 Energy Northwest Columbia Generating Station, Response to Apparent Violation in NRC Inspection Report 05000397/2023092; EA-23-054 GO2-23-068, Notification of Completion of Commitments Required Prior to Entry Into the Period of Extended Operation2023-07-19019 July 2023 Notification of Completion of Commitments Required Prior to Entry Into the Period of Extended Operation GO2-23-090, Reply to a Notice of Violation2023-07-12012 July 2023 Reply to a Notice of Violation ML23143A1202023-06-27027 June 2023 Request Number 4ISI-11 to the American Society of Mechanical Engineers Boiler and Pressure Vessel Code Regarding Alternate Examination of Reactor Vessel Welds GO2-23-073, Notification of NPDES Permit Issuance2023-06-26026 June 2023 Notification of NPDES Permit Issuance ML23163A2502023-06-12012 June 2023 Summary of Changes and Analysis for Revision 41 of Plant Procedures Manual 13.8.1 Emergency Dose Projection System Operations GO2-23-072, Cycle 27 Core Operating Limits Report2023-06-0505 June 2023 Cycle 27 Core Operating Limits Report ML23157A2702023-06-0101 June 2023 4-2022-011 -022 Letter - OI Closure to Licensee IR 05000397/20230922023-06-0101 June 2023 NRC Inspection Report 05000397/2023092 and Preliminary White Finding IR 05000397/20230902023-06-0101 June 2023 Final Significance Determination of a White Finding, Notice of Violation and Follow-Up Assessment Letter; NRC Inspection Report 05000397/2023090 GO2-23-055, Independent Spent Fuel Storage Installation, 2022 Annual Radiological Environmental Operating Report2023-05-15015 May 2023 Independent Spent Fuel Storage Installation, 2022 Annual Radiological Environmental Operating Report IR 05000397/20230012023-05-0505 May 2023 Integrated Inspection Report 05000397/2023001 - April 26, 2023 GO2-23-006, License Amendment Request to Clean-Up Operating License and Appendix a Technical Specifications2023-05-0101 May 2023 License Amendment Request to Clean-Up Operating License and Appendix a Technical Specifications IR 05000397/20233012023-05-0101 May 2023 NRC Examination Report 05000397/2023301 GO2-23-053, 2022 Annual Environmental Operating Report2023-04-26026 April 2023 2022 Annual Environmental Operating Report GO2-23-057, 2022 Annual Radioactive Effluent Release Report2023-04-25025 April 2023 2022 Annual Radioactive Effluent Release Report ML23110A2642023-04-20020 April 2023 Request for Information License Renewal Phase 2 Inspection GO2-23-012, Application to Revise Technical Specifications to Adopt Tstf-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position2023-03-27027 March 2023 Application to Revise Technical Specifications to Adopt Tstf-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position GO2-23-041, Generation Station - Level of Financial Protection - Annual Reporting Requirement2023-03-15015 March 2023 Generation Station - Level of Financial Protection - Annual Reporting Requirement GO2-23-038, Plant Decommissioning Fund Status Report2023-03-15015 March 2023 Plant Decommissioning Fund Status Report ML23013A0812023-03-15015 March 2023 Issuance of Amendment No. 270 Revision to Technical Specifications to Adopt TSTF 505, Revision 2, Provide Risk-Informed Extended Completion Times-RITSTF Initiative 4B GO2-23-034, Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.462023-03-13013 March 2023 Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.46 2024-01-08
[Table view] |
Text
September 09, 2021
SUBJECT:
COLUMBIA GENERATING STATION - SECURITY BASELINE INSPECTION REPORT 05000397/2021402
Dear Mr. Schuetz:
On August 12, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Columbia Generating Station and discussed the results of this inspection with Mr. Schuetz, Chief Executive Officer, and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Ray L. Digitally signed by Ray L. Kellar Kellar Date: 2021.09.09 10:20:05 -05'00'
Ray L. Kellar, P.E., Chief Plant Support Branch 1 Division of Reactor Safety Docket No. 05000397 License No. NPF-21
Enclosure:
As stated
Inspection Report
Docket Number: 05000397 License Number: NPF-21 Report Number: 05000397/2021402 Enterprise Identifier: I-2021-402-0004 Licensee: Energy Northwest Facility: Columbia Generating Station Location: Richland, Washington Inspection Dates: August 09, 2021 to August 12, 2021 Inspectors: D. Hostetter, Sr Physical Security Inspector C. Jewett, Physical Security Inspector Approved By: Ray L. Kellar, P.E., Chief Plant Support Branch 1 Division of Reactor Safety Enclosure
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a security baseline inspection at Columbia Generating Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
INSPECTION SCOPES
Unless otherwise noted, baseline security inspections were conducted in accordance with the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter 2201, Security Inspection Program for Commercial Nuclear Power Reactors. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards. Publicly available IPs are located at:
http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html.
The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards. Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), inspectors were directed to begin telework. In addition, regional baseline inspections were evaluated to determine if all or a portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on site. The inspections documented below met the objectives and requirements for completion of the IP.
SAFEGUARDS
71130.01 - Access Authorization
The inspectors evaluated the access authorization program. The following elements were evaluated:
Access Authorization
Main article: IP 71130.01
(1)
- Tier II: All requirements
- Tier III: All requirements
71130.02 - Access Control
The inspectors evaluated the access control program through completion of the following
inspection elements: Access Control
Main article: IP 71130.02
(1)
- Tier II: All Requirements
- Tier III: All Requirements
71130.09 - Security Plan Changes
The inspectors evaluated the security plan changes through completion of the following procedure elements:
Review Security Plan Changes (IP Section 02.01) (1 Partial)
(1) (Partial)
The opportunity to apply this procedure was not available in accordance with Inspection Manual Chapter 0306. This sample was not available because the licensee did not conduct the activity covered by this IP. Specifically, the licensee has not initiated a physical security plan change in accordance with 10 CFR 50.54(p)(2)since the implementation of this IP and Physical Security Plan Revision 20 remains current.
OTHER ACTIVITIES - BASELINE
71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:
PP01: Protected Area Security Equipment Performance Index Sample (IP Section 02.17) (1 Sample)
- (1) July 2020 through July
INSPECTION RESULTS
No findings were identified.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On August 12, 2021, the inspectors presented the security baseline inspection results to Mr. Schuetz, Site Vice President, and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection Type Designation Description or Title Revision or
Procedure Date
71130.01 Corrective Action 00372779,
Documents 00382376,
00389707,
00399365,
00399367,
00399369,
00402572,
00410203,
00415342,
00419076,
00420173
Corrective Action 00424225
Documents
Resulting from
Inspection
Miscellaneous BOP/Revalidation Report 07/19/2021
BOP/Revalidation Report 02/21/2021
Security Event Logs 07/12/2020 -
07/11/2021
NANTeL Generic Fitness-for-Duty and Behavior Observation 06/01/2021
21-001 All Clear Screening Services Audit 02/04/2021
MT000204 Fitness For Duty/Behavioral Observation Program for
Supervisors
Procedures 2019 Disaster Recovery Plan for PADS 08/07/2019
ADI-1 Green Badge Process 004
ADI-4 Psychological Evaluations 001
ISDI-TRAP-16 PADS- Technical Recovery Action Plan (TRAP) 000
SPIP-SEC-65 Access Authorization Program 009
SWP-FFD-01 Fitness for Duty Program Requirements 022
SWP-FFD-02 Behavioral Observation Program 007
SWP-SEC-04 Access of
NRC Personnel
006
SWP-SEC-06 Personnel Access Data System 008
Inspection Type Designation Description or Title Revision or
Procedure Date
SWP-SEC-07 Nuclear Power Plant Access Authorization Program 022
71130.02 Corrective Action 00410209,
Documents 00413644,
416840,
00418864,
00420374,
00420425
Corrective Action 00424118,
Documents 00424124,
Resulting from 00424172
Inspection
Miscellaneous Energy Northwest Snap Shot Self-Assessment Report 05/06/2021
Energy Northwest Vital Area Access Log Revision 4
Form 15635
Energy Northwest Vehicle Entry/Exit Logs Revision 5
Form 16090
Energy Northwest Compensatory Posting Log Sheet Revision 3
Form 25505
Security Event Mulitple
Logs Dates
Procedures SPIP-SEC-01 Sergeant & Lieutenant Duties Revision 25
SPIP-SEC-05 Personnel Search Officer, Access Control/Security Revision 37
Communications Center Officer, Protected Area Access
Point
SPIP-SEC-06 Vehicle Escort Officer, Vehicle Search Officer & Protected Revision 25
Area Perimeter Gates
SPIP-SEC-10 Special Purpose Detectors, Operability Test, Inspection, & Revision 18
Maintenance Records
SPIP-SEC-19 Key and Lock Control Revision 7
SPIP-SEC-26 Post 21 CP Procedures Revision 36
SPIP-SEC-48 Itemizer 4D Explosive Detector Revision 07
SPIP-SEC-56 Security Access Point Badge Reader Revision 7
SPIP-SEC-64 Warehouse X-Ray Revision 03
SWP-SEC-01 Vital & Protected Area Key & Lock Control Revision 7
Inspection Type Designation Description or Title Revision or
Procedure Date
SWP-SEC-02 Protection of Safeguards Information Revision 19
SWP-SEC-08 Plant Key & Lock Control Revision 3
SWP-SEC-12 PA/VA Area Personnel & Vehicle Access Controls Revision 8
71130.09 Procedures PSP-01 Physical Security Plan, Security Training & Qualification, Revision 20
Safeguards Contingency Plan, and Independent Spent Fuel
Storage Installation
71151 Miscellaneous SFI-22 IDS/CCTV NRC Performance Indicators Revision 0
Procedures GBP-AM-03 Performance Indicators Revision 01
7