MONTHYEARIR 05000373/20230042024-01-24024 January 2024 County Station - Integrated Inspection Report 05000373/2023004 and 05000374/2023004 IR 05000373/20230122024-01-18018 January 2024 County Station - Biennial Problem Identification and Resolution Inspection Report 05000373/2023012 and 05000374/2023012 IR 05000373/20234022023-12-20020 December 2023 County Station - Security Baseline Inspection Report 05000373/2023402 and 05000374/2023402 IR 05000373/20230032023-11-0909 November 2023 County Station Integrated Inspection Report 05000373/2023003, 05000374/2023003, and 07200070/2023001 IR 05000373/20234012023-11-0707 November 2023 County Station Security Baseline Inspection Report 05000373/2023401 and 05000374/2023401 IR 05000374/20230102023-10-11011 October 2023 NRC Inspection Report 05000374/2023010 IR 05000373/20233012023-09-15015 September 2023 Errata to NRC Initial License Examination Report 05000373/2023301; 05000374/2023301 IR 05000373/20230022023-08-0101 August 2023 County Station - Integrated Inspection Report 05000373/2023002 and 05000374/2023002 IR 05000373/20230112023-06-26026 June 2023 County Station - Quadrennial Fire Protection Team Inspection Report 05000373/2023011 and 05000374/2023011 IR 05000373/20230012023-05-10010 May 2023 County Station - Integrated Inspection Report 05000373/2023001 and 05000374/2023001 IR 05000373/20220062023-03-0101 March 2023 Annual Assessment Letter for LaSalle County Station, Units 1 and 2 (Report 05000373/2022006 and 05000374/2022006) IR 05000373/20220042023-01-31031 January 2023 County Station - Integrated Inspection Report 05000373/2022004 and 05000374/2022004 IR 05000373/20224042022-12-21021 December 2022 County Station - Material Control and Accounting Program Inspection Report 05000373/2022404 and 05000374/2022404 IR 05000373/20225012022-12-0505 December 2022 County Station - Emergency Preparedness Biennial Exercise Inspection Report 05000373/2022501 and 05000374/2022501 IR 05000373/20224022022-11-17017 November 2022 County Station - Security Baseline Inspection Report 05000373/2022402 and 05000374/2022402 IR 05000373/20220112022-11-0101 November 2022 County Station Design Basis Assurance Inspection (Teams) Inspection Report 05000373/2022011 and 05000374/2022011 IR 05000373/20220032022-11-0101 November 2022 County Station - Integrated Inspection Report 05000373/2022003 and 05000374/2022003 IR 05000373/20224032022-09-15015 September 2022 County Station - Cyber Security Inspection Report 05000373/2022403 and 05000374/2022403 IR 05000373/20220052022-08-22022 August 2022 Updated Inspection Plan for Lasalle County Station (Report 05000373/2022005; 05000374/2022005) IR 05000373/20220022022-08-10010 August 2022 County Station - Integrated Inspection Report 05000373/2022002 and 05000374/2022002 IR 05000373/20224012022-05-18018 May 2022 County Station - Security Baseline Inspection Report 05000373/2022401 and 05000374/2022401 IR 05000373/20220012022-04-26026 April 2022 County Station - Integrated Inspection Report 05000373/2022001 and 05000374/2022001 ML22108A2802022-04-19019 April 2022 Information Request for an NRC Triennial Baseline Design Bases Assurance Inspection (Team) Inspection Report 05000373/2022011 05000374/20220 IR 05000373/20220102022-03-15015 March 2022 County Station License Renewal Phase 2 Report 05000373/2022010 IR 05000373/20210062022-03-0202 March 2022 Annual Assessment Letter (Report 05000373/2021006 and 05000374/2021006) IR 05000373/20210042022-02-0707 February 2022 County Station Integrated Inspection Report 05000373/2021004 and 05000374/2021004 IR 05000373/20210132022-01-20020 January 2022 County Station Biennial Problem Identification and Resolution Inspection Report 05000373/2021013 and 05000374/2021013 IR 05000373/20214022021-12-15015 December 2021 County Station - Security Baseline Inspection Report 05000373/2021402 and 05000374/2021402 IR 05000373/20210032021-11-0808 November 2021 County Station Integrated Inspection Report 05000373/2021003; 05000374/2021003 and 07200070/2021001 IR 05000373/20210022021-11-0101 November 2021 County Station Integrated Inspection Report 05000373/2021002 and 05000374/2021002 IR 05000373/20210122021-10-28028 October 2021 County Station- 50.59 Team Inspection Report 05000373/2021012 and 05000374/2021012 IR 05000373/20210052021-09-0101 September 2021 Updated Inspection Plan for Lasalle County Station, Units 1 and 2; Report 05000373/2021005 and 05000374/2021005 IR 05000373/20210112021-08-23023 August 2021 County Station - Design Basis Assurance Inspection (Programs) Inspection Report 05000373/2021011 and 05000374/2021011 IR 05000373/20215012021-06-16016 June 2021 County Station - Emergency Preparedness Biennial Exercise Inspection Report 05000373/2021501 and 05000374/2021501 IR 05000373/20214012021-05-18018 May 2021 County Station - Security Baseline Inspection Report 05000373/2021401 and 05000374/2021401 IR 05000373/20210012021-05-0404 May 2021 Lssalle County Station - Integrated Inspection Report 05000373/2021001 and 05000374/2021001 IR 05000374/20210102021-04-0505 April 2021 County Station - Post-Approval Site Inspection for License Renewal (Phase I) Report 05000374/2021010 IR 05000373/20200042021-03-0505 March 2021 Reissue - Lasalle County Station - Integrated Inspection Report 05000373/2020004; 05000374/2020004; 05000373/2020501; 05000374/2020501; 05000373/2020011 and 05000374/2020011 IR 05000373/20200062021-03-0404 March 2021 Annual Assessment Letter for Lasalle County Station Units 1 and 2 (Report 05000373/2020006 and 05000374/2020006) ML21043A1982021-02-12012 February 2021 County Station - Integrated Inspection Report 05000373/2020004; 05000374/2020004; 05000373/2020501 and 05000374/2020501 IR 05000373/20204022021-01-0505 January 2021 County Station - Security Baseline Inspection Report 05000373/2020402 and 05000374/2020402 IR 05000373/20203012020-12-17017 December 2020 NRC Initial License Examination Report 05000373/2020301; 05000374/2020301 IR 05000373/20200032020-12-11011 December 2020 County Station - Integrated Inspection Report 05000373/2020003 and 05000374/2020003 IR 05000373/20200052020-09-0101 September 2020 Updated Inspection Plan for Lasalle County Station, Units 1 and 2 (Report 05000373/2020005 and 05000374/2020005) IR 05000373/20200022020-08-11011 August 2020 County Station - Integrated Inspection Report 05000373/2020002 and 05000374/2020002 IR 05000373/20200122020-06-0505 June 2020 County Station - Triennial Fire Protection Inspection Report 05000373/2020012 and 05000374/2020012 IR 05000373/20200012020-05-11011 May 2020 County Station - Integrated Inspection Report 05000373/2020001 and 05000374/2020001 IR 05000373/20204012020-03-16016 March 2020 Security Baseline Inspection Report 05000373/2020401 and 05000374/2020401 IR 05000373/20190062020-03-0303 March 2020 Annual Assessment Letter for LaSalle County Station, Units 1 and 2 (Report 05000373/2019006 and 05000374/2019006) IR 05000373/20200102020-02-25025 February 2020 Post-Approval Site Inspection for License Renewal (Phase I) Report 05000373/2020010 2024-01-24
[Table view] Category:Letter
MONTHYEARIR 05000373/20230042024-01-24024 January 2024 County Station - Integrated Inspection Report 05000373/2023004 and 05000374/2023004 ML24024A1332024-01-24024 January 2024 Confirmation of Initial License Examination IR 05000373/20230122024-01-18018 January 2024 County Station - Biennial Problem Identification and Resolution Inspection Report 05000373/2023012 and 05000374/2023012 ML23354A2902024-01-0505 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0028 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23360A6082023-12-27027 December 2023 County Station Request for Information for NRC Commercial Grade Dedication Inspection: Inspection Report 05000373/2024010 and 05000374/2024010 ML23278A1292023-12-14014 December 2023 Units 1 & 2; Limerick, Units 1 & 2; Nine Mile Point, Units 1 & 2; and Peach Bottom, Units 2 & 3 -Revision to Approved Alternatives to Use Boiling Water Reactor Vessel and Internals Project Guidelines ML23305A1402023-12-13013 December 2023 Units 1 & 2; Nine Mile Point, Unit 2; Peach Bottom, Units 2 & 3; and Quad Cities, Units 1 and 2 - Issuance of Amendments to Adopt Traveler TSTF-580 ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums RS-23-120, Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information2023-11-10010 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information IR 05000373/20230032023-11-0909 November 2023 County Station Integrated Inspection Report 05000373/2023003, 05000374/2023003, and 07200070/2023001 ML23286A2602023-11-0808 November 2023 Issuance of Amendment Nos. 260 and 245 to Renewed Facility Operating Licenses Relocation of Pressure and Temperature Limit Curves to the Pressure Temperature Report IR 05000373/20234012023-11-0707 November 2023 County Station Security Baseline Inspection Report 05000373/2023401 and 05000374/2023401 RS-23-103, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-10-13013 October 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans IR 05000374/20230102023-10-11011 October 2023 NRC Inspection Report 05000374/2023010 IR 05000373/20233012023-09-15015 September 2023 Errata to NRC Initial License Examination Report 05000373/2023301; 05000374/2023301 RS-23-080, Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs2023-08-30030 August 2023 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs RS-23-087, Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor2023-08-0404 August 2023 Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor ML23212A9012023-08-0303 August 2023 Regulatory Audit Report to Support the Review of the Amendments to Relocation of the Pressure Temperature Limit Curves to the Pressure and Temperature Limits Report IR 05000373/20230022023-08-0101 August 2023 County Station - Integrated Inspection Report 05000373/2023002 and 05000374/2023002 ML23208A3182023-07-27027 July 2023 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and RFI RS-23-084, Response to Request for Additional Information Regarding the Application to Revise Design Basis to Allow Use of Plastic Section Properties in Lower Downcomer Braces Analysis2023-07-24024 July 2023 Response to Request for Additional Information Regarding the Application to Revise Design Basis to Allow Use of Plastic Section Properties in Lower Downcomer Braces Analysis ML23192A5272023-07-12012 July 2023 NRC Initial License Examination Report 05000373/2023301; 05000374/2023301 ML23186A2062023-07-0606 July 2023 Information Request for a NRC Post-Approval Site Inspection for License Renewal 05000374/2023010 ML23181A1502023-06-30030 June 2023 Combined Response to Request for Additional Information and Supplemental Information in Support of LAR to Relocate Pressure and Temperature Limit Curves to the Pressure and Temperature Limits Report ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III IR 05000373/20230112023-06-26026 June 2023 County Station - Quadrennial Fire Protection Team Inspection Report 05000373/2023011 and 05000374/2023011 RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23167A0352023-06-16016 June 2023 Registration of Use of Cask to Store Spent Fuel ML23171A9562023-06-12012 June 2023 Post Exam Ltr RS-23-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-05-25025 May 2023 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling IR 05000373/20230012023-05-10010 May 2023 County Station - Integrated Inspection Report 05000373/2023001 and 05000374/2023001 ML23123A2202023-05-0303 May 2023 Relief Request I4R-14 for Alternative Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection ML23118A3472023-05-0101 May 2023 County, 1 & 2; Nine Mile Point, 2; and Quad Cities, 1 & 2 - Correction of Amendment No. 193 Adoption of TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration EPID L-2022-LLA-0143 ML23121A1612023-05-0101 May 2023 Information Meeting (Open House) with a Question-and-Answer Session to Discuss NRC 2022 End-of-Cycle Plant Performance Assessment of LaSalle County Station, Units 1 and 2 ML23114A2522023-04-28028 April 2023 Request to Use a Provision of a Later Edition of the ASME Boiler & Pressure Vessel Code, Section XI ML23081A0382023-04-25025 April 2023 County, 1 & 2; Nine Mile Point, 2; and Quad Cities, 1 & 2 - Issuance of Amendments to Adopt TSTF-306, Rev. 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration ML23110A3202023-04-21021 April 2023 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML23107A1822023-04-18018 April 2023 Operator Licensing Examination Approval Lasalle County Station, May 2023 RS-23-049, Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-23023 March 2023 Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML23073A2182023-03-22022 March 2023 Issuance of Amendment No. 258 to Renewed Facility Operating Licenses Exigent Amendment to Revise Design Basis Related to Seismic Requirements RS-23-048, Exigent Amendment Request to Revise Design Basis Related to Seismic Requirements2023-03-0707 March 2023 Exigent Amendment Request to Revise Design Basis Related to Seismic Requirements ML23061A1632023-03-0303 March 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch 3 IR 05000373/20220062023-03-0101 March 2023 Annual Assessment Letter for LaSalle County Station, Units 1 and 2 (Report 05000373/2022006 and 05000374/2022006) RS-23-045, Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.2032023-02-28028 February 2023 Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.203 RS-23-037, Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors for LaSalle County Station2023-02-22022 February 2023 Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors for LaSalle County Station ML23024A1372023-02-0303 February 2023 Request for Withholding Information from Public Disclosure for LaSalle County Station, Unit Nos. 1 and 2 ML23031A1972023-01-31031 January 2023 Notification of NRC Fire Protection Team Inspection Request for Information, Inspection Report Nos. 05000373/2023011 and 05000374/2023011 IR 05000373/20220042023-01-31031 January 2023 County Station - Integrated Inspection Report 05000373/2022004 and 05000374/2022004 RS-23-003, Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-102023-01-31031 January 2023 Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-10 2024-01-05
[Table view] |
Text
ust 22, 2018
SUBJECT:
LASALLE COUNTY STATION, UNITS 1 AND 2NRC EMERGENCY PREPAREDNESS INSPECTION REPORT 05000373/2018503 AND 05000374/2018503
Dear Mr. Hanson:
On August 9, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed an Emergency Preparedness inspection at your LaSalle County Station, Units 1 and 2. The NRC inspectors discussed the results of this inspection with Mr. Trafton and other members of your staff.
The results of this inspection are documented in the enclosed report.
The NRC Inspectors did not identify any finding or violation of more-than-minor significance.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations, Part 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA Nathan Egan Acting for/
Steven K. Orth, Chief Plant Support Branch Division of Reactor Safety Docket Nos. 50-373; 50-374 License Nos. NPF-11; NPF-18 Enclosure:
IR 05000373/2018503; 05000374/2018503 cc: Distribution via ListServ
Letter to Bryan
SUMMARY
The U.S. Nuclear Regulatory Commission continued monitoring licensees performance by conducting an Emergency Preparedness Inspection at LaSalle County Station, Units 1 and 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the U.S. Nuclear Regulatory Commissions program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations No findings or violations were identified.
Additional Tracking Items None.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter 2515, Light-Water Reactor Inspection Program -
Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
REACTOR SAFETY
71114.01Exercise Evaluation
Main article: IP 71114.01
The inspectors evaluated the August 7, 2018, Biennial Emergency Plan Exercise.
The exercise scenario simulated an event at LaSalle County Station that initiated with the declaration of an Unusual Event in response to a malfunction of plant equipment. The scenario conditions simulated the escalation of the significance of the event, requiring the declaration and notification of an Alert, a Site Area Emergency, and then a General Emergency, as well as the development of Protective Action Recommendations that were communicated to the required state and local government agencies.
71114.08Exercise EvaluationScenario Review
Main article: IP 71114.08
The inspectors reviewed and evaluated the proposed scenario for the Biennial Emergency Plan Exercise on July 2,
OTHER ACTIVITIES
BASELINE
71151Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below.
- (1) EP01: Drill/Exercise Performance (DEP) -1 Sample (1st Quarter of 2017 through 1st Quarter of 2018);
- (2) EP02: Emergency Response Organization (ERO) Drill Participation-1 Sample (1st Quarter of 2017 through 1st Quarter of 2018); and
- (3) EP03: Alert And Notification System (ANS) Reliability-1 Sample (1st Quarter of 2017 through 1st Quarter of 2018).
INSPECTION RESULTS
No findings or violations were identified.
EXIT MEETINGS AND DEBRIEFS
The inspectors confirmed that proprietary information was controlled to protect from public disclosure. No proprietary information was documented in this report.
- On August 9, 2018, the inspectors presented the Emergency Preparedness inspection results to Mr. B. Trafton, Site Vice President, and other members of the licensee staff.
DOCUMENTS REVIEWED
71114.01Exercise Evaluation
- EP-AA-1005; Radiological Emergency Plan Annex for LaSalle Station; Revision 40
- LaSalle PI Drill Reports; 3rd Quarter of 2016 through 1st Quarter of 2018
- AR 02709108; 2016 3rd Quarter Drill Objective Failure; 08/24/2016
- AR 02728275; EP Drill Obj Failure PI Drill Team B; 08/24/2016
- AR 02735479 3rd Quarter of 2016 Drill Lessons Learned - August; 08/24/2016
- AR 03961949; Drill Report Discrepancies; 01/11/2017
- AR 04012485; 2nd Quarter of 2017 LORT/PI Drill Exercise MGMT and Scenario Issues;
05/18/2017
- AR 04012486; 2nd Quarter of 2017 LORT/PI Drill Facilities and Equipment Issues; 06/17/2017
- AR 04047803; LAS-EP-2017-OYE-TSC-FAILED DCS; 08/30/2017
- AR 04047828; LAS-EP-2017-OYE-SIM-FAILED DC; 08/30/2017
- AR 04047824; LAS-EP-2017-OYE-OSC-FAILED DC; 08/31/2017
- AR 04086120; Demonstration Criteria Failure for 4th Quarter of 2017 Paper Driven Drills;
2/06/2017
- AR 04053640; 3rd Quarter of 2017 August Drill Set Failed Demonstration Criteria; 02/16/2018
- AR 04047904; EP-LAS-2017 OYE Issues; 02/23/2018
- AR 04109571; 1st Quarter of 2018 Drill Set Demonstration Criteria Failures; 02/28/2018
71114.08Exercise EvaluationScenario Review
- LaSalle County Station 2018 NRC Graded Exercise Manual; 06/04/2018
71151Performance Indicator Verification
- NRC Performance Indicator Data, Emergency Preparedness - Alert and Notification System
Reliability; 1st Quarter of 2017 through 1st Quarter of 2018
- NRC Performance Indicator Data, Emergency Preparedness - Drill/Exercise Performance;
1st Quarter of 2017 through 1st Quarter of 2018
- NRC Performance Indicator Data, Emergency Preparedness - ERO Readiness; 1st Quarter
of 2017 through 1st Quarter of 2018
4