Updated Inspection Plan Inspection Report 05000334/2018005 and 05000412/2018005
ML18226A078
Person / Time
Site: Beaver Valley  FirstEnergy icon.png
Issue date: 08/28/2018
From: Matt Young
NRC/RGN-I/DRP/PB6
To: Bologna R
FirstEnergy Nuclear Operating Co
References
IR 2018005
Download: ML18226A078 (6)


Text

ust 28, 2018

SUBJECT:

BEAVER VALLEY POWER STATION, UNIT NOS. 1 AND 2 UPDATED INSPECTION PLAN INSPECTION REPORT 05000334/2018005 AND 05000412/2018005

Dear Mr. Bologna:

The enclosed inspection plan lists the inspections scheduled through June 30, 2020, for Beaver Valley Power Station, Units 1 and 2. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at 610-337-5205 with any questions you have regarding this letter.

Sincerely,

/RA/

Matthew R. Young, Chief Reactor Projects Branch 6 Division of Reactor Projects Docket Nos. 50-334 and 50-412 License Nos. DPR-66 and NPF-73 Enclosure:

Beaver Valley Inspection Plan cc: Distribution via ListServ

ML18226A078 SUNSI Review Non-Sensitive Publicly Available Sensitive Non-Publicly Available OFFICE RI/DRP RI/DRP NAME SShaffer MYoung DATE 8/1/18 8/2/18

IP 22 Inspection Activity Plan Report Beaver Valley 07/01/2018 - 06/30/2020 Unit Start End Activity CAC Title Staff Count 3rd Quarter Site Support 10 1, 2 07/01/2018 09/30/2018 IP 71111.19 000711 Post Maintenance Testing 1, 2 07/01/2018 09/30/2018 IP 71153 000749 Followup of Events and Notices of Enforcement Discretion TRIENNIAL FIRE PROTECTION 4 1, 2 07/23/2018 07/27/2018 IP 71111.05XT 000697 Fire Protection - NFPA 805 (Triennial)

1, 2 08/06/2018 08/10/2018 IP 71111.05XT 000697 Fire Protection - NFPA 805 (Triennial)

Annual Sample - Isophase Duct Inspections for License Renewal 1 1, 2 07/30/2018 08/03/2018 IP 71152 000748 Problem Identification and Resolution BEAVER VALLEY 1 INITIAL OL EXAM 4 1 08/20/2018 08/24/2018 OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)

1 09/17/2018 09/28/2018 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)

RAD INSTRUMENTATION 1 1, 2 09/10/2018 09/14/2018 IP 71124.05 000729 Radiation Monitoring Instrumentation Unit 2 Inservice Inspection 1 2 10/29/2018 11/09/2018 IP 71111.08P 000702 Inservice Inspection Activities - PWR Rad Safety Inspection 1 1, 2 10/29/2018 11/02/2018 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2 10/29/2018 11/02/2018 IP 71124.02 000726 Occupational ALARA Planning and Controls 1, 2 10/29/2018 11/02/2018 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 10/29/2018 11/02/2018 IP 71124.04 000728 Occupational Dose Assessment RADWASTE 1 1, 2 11/05/2018 11/09/2018 IP 71124.08 000732 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation RAD SAFETY INSPECTION 1 1, 2 12/10/2018 12/14/2018 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2 12/10/2018 12/14/2018 IP 71124.02 000726 Occupational ALARA Planning and Controls 1, 2 12/10/2018 12/14/2018 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 12/10/2018 12/14/2018 IP 71124.04 000728 Occupational Dose Assessment This report does not include INPO and OUTAGE activities. Page 1 of 4 This report shows only on-site and announced inspection procedures.

8/29/2018 11:28:40 AM

IP 22 Inspection Activity Plan Report Beaver Valley 07/01/2018 - 06/30/2020 Unit Start End Activity CAC Title Staff Count RAD SAFETY INSPECTION 1 1, 2 12/10/2018 12/14/2018 IP 71151 000746 Performance Indicator Verification PI&R BIENNIAL 4 1, 2 03/04/2019 03/08/2019 IP 71152B 000747 Problem Identification and Resolution 1, 2 03/18/2019 03/22/2019 IP 71152B 000747 Problem Identification and Resolution RAD SAFETY 01,02,03,04 1 1, 2 03/18/2019 03/22/2019 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2 03/18/2019 03/22/2019 IP 71124.02 000726 Occupational ALARA Planning and Controls 1, 2 03/18/2019 03/22/2019 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 03/18/2019 03/22/2019 IP 71124.04 000729 Occupational Dose Assessment FORCE-ON-FORCE PLANNING AND EXERCISES 8 1, 2 03/25/2019 03/29/2019 IP 71130.03 000735 Contingency Response - Force-On-Force Testing 1, 2 04/15/2019 04/19/2019 IP 71130.03 000735 Contingency Response - Force-On-Force Testing EQ PROGRAM 3 1, 2 04/29/2019 05/03/2019 IP 71111.21N 000714 Design Bases Assurance Inspection (Programs)

1, 2 05/20/2019 05/24/2019 IP 71111.21N 000714 Design Bases Assurance Inspection (Programs)

BV2 REQUAL INSP WITH P/F RESULTS 2 2 05/06/2019 05/10/2019 IP 71111.11A 000703 Licensed Operator Requalification Program and Licensed Operator Performance (Annual)

2 05/06/2019 05/10/2019 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance (Biennial)

EP PROGRAM INSPECTION 2 1, 2 06/10/2019 06/14/2019 IP 71114.02 000717 Alert and Notification System Testing 1, 2 06/10/2019 06/14/2019 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 1, 2 06/10/2019 06/14/2019 IP 71114.05 000720 Correction of Emergency Preparedness Weaknesses and Deficiencies 1, 2 06/10/2019 06/14/2019 IP 71151 001397 Performance Indicator Verification RAD SAFETY REMP 1 1, 2 07/08/2019 07/12/2019 IP 71124.07 000731 Radiological Environmental Monitoring Program 1, 2 07/08/2019 07/12/2019 IP 71151 000746 Performance Indicator Verification This report does not include INPO and OUTAGE activities. Page 2 of 4 This report shows only on-site and announced inspection procedures.

8/29/2018 11:28:40 AM

IP 22 Inspection Activity Plan Report Beaver Valley 07/01/2018 - 06/30/2020 Unit Start End Activity CAC Title Staff Count Triennial Heat Sink 1 1, 2 07/15/2019 07/19/2019 IP 71111.07T 000700 Heat Sink Performance -Triennial ACCESS CONTROL, EQUIP PERF, TRAINING 3 1, 2 07/22/2019 07/26/2019 IP 71130.02 000734 Access Control 1, 2 07/22/2019 07/26/2019 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance 1, 2 07/22/2019 07/26/2019 IP 71130.07 000739 Security Training 1, 2 07/22/2019 07/26/2019 IP 71151 001338 Performance Indicator Verification 50.59 Process 3 1, 2 08/12/2019 08/16/2019 IP 71111.17T 000709 Evaluations of Changes, Tests, and Experiments RAD SAFETY 01,02,03,04 1 1, 2 08/12/2019 08/16/2019 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2 08/12/2019 08/16/2019 IP 71124.02 000726 Occupational ALARA Planning and Controls 1, 2 08/12/2019 08/16/2019 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 08/12/2019 08/16/2019 IP 71124.04 000729 Occupational Dose Assessment BEAVER VALLEY 2 INITIAL OL EXAM 4 2 08/26/2019 08/30/2019 OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)

2 10/07/2019 10/18/2019 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)

INSERVICE INSPECTION - UNIT 1 1 1 10/07/2019 10/18/2019 IP 71111.08P 000702 Inservice Inspection Activities - PWR RAD SAFETY OUT 1 1, 2 10/28/2019 11/01/2019 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2 10/28/2019 11/01/2019 IP 71124.02 000726 Occupational ALARA Planning and Controls 1, 2 10/28/2019 11/01/2019 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 10/28/2019 11/01/2019 IP 71124.04 000729 Occupational Dose Assessment 1, 2 10/28/2019 11/01/2019 IP 71151 000746 Performance Indicator Verification Rad Safety Inspection 1 1, 2 01/27/2020 01/31/2020 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2 01/27/2020 01/31/2020 IP 71124.02 000726 Occupational ALARA Planning and Controls 1, 2 01/27/2020 01/31/2020 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation This report does not include INPO and OUTAGE activities. Page 3 of 4 This report shows only on-site and announced inspection procedures.

8/29/2018 11:28:40 AM

IP 22 Inspection Activity Plan Report Beaver Valley 07/01/2018 - 06/30/2020 Unit Start End Activity CAC Title Staff Count Rad Safety Inspection 1 1, 2 01/27/2020 01/31/2020 IP 71124.04 000729 Occupational Dose Assessment BV1 Requal Inspection with P/F Results 2 1 04/13/2020 04/18/2020 IP 71111.11A 000703 Licensed Operator Requalification Program and Licensed Operator Performance (Annual)

1 04/13/2020 04/18/2020 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance (Biennial)

Rad Safety Refuel 1 1, 2 04/13/2020 04/17/2020 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2 04/13/2020 04/17/2020 IP 71124.02 000726 Occupational ALARA Planning and Controls 1, 2 04/13/2020 04/17/2020 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 04/13/2020 04/17/2020 IP 71124.04 000729 Occupational Dose Assessment ISI - UNIT 2 1 2 04/20/2020 05/01/2020 IP 71111.08P 000702 Inservice Inspection Activities - PWR BEAVER VALLEY EP EXERCISE INSPECTION 5 1, 2 06/08/2020 06/12/2020 IP 71114.01 000716 Exercise Evaluation 1, 2 06/08/2020 06/12/2020 IP 71151 001397 Performance Indicator Verification Rad Safety RETS 1 1, 2 06/22/2020 06/26/2020 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment 1, 2 06/22/2020 06/26/2020 IP 71151 000746 Performance Indicator Verification This report does not include INPO and OUTAGE activities. Page 4 of 4 This report shows only on-site and announced inspection procedures.