MONTHYEARIR 05000327/20230052023-08-29029 August 2023 Updated Inspection Plan for Sequoyah Nuclear Plant, Units 1 and 2 - Report 05000327/2023005 and 05000328/2023005 IR 05000327/20220062023-03-0101 March 2023 Annual Assessment Letter for Sequoyah Nuclear Plant, Units 1 and 2 Report 05000327/2022006 and 05000328/2022006 ML23026A0282023-01-12012 January 2023 001 Radiation Safety Baseline Inspection Information Request IR 05000327/20220052022-08-30030 August 2022 Updated Inspection Plan for Sequoyah Nuclear Plant, Units 1 and 2 - Report 05000327 2022005 and 05000328 2022005 - Final IR 05000327/20210062022-03-0202 March 2022 Annual Assessment Letter for Sequoyah Nuclear Plant, Units 1 and 2 - (Report No. 05000327/2021006 and 05000328/2021006) ML21160A0352021-06-0303 June 2021 Document Request for Sequoyah Nuclear Plant - Radiation Protection Inspection - Inspection Report 2021-03 ML21092A0972021-04-0202 April 2021 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML20259A4782020-09-15015 September 2020 Emergency Preparedness Program Inspection Request for Information IR 05000327/20200052020-08-18018 August 2020 Updated Inspection Plan for Sequoyah Nuclear Plant, Units 1 and 2 - Report 05000327/2020005 and 05000328/2020005 ML20227A0082020-08-14014 August 2020 Requalification Program Inspection - Sequoyah Nuclear Plant ML19324E9992019-11-20020 November 2019 2020 SQN - POV Inspection Information Request - Rev. 1 ML19235A1972019-08-23023 August 2019 ISI 2019004 RFI Ajb IR 05000327/20180062019-03-0404 March 2019 Annual Assessment Letter for Sequoyah Nuclear Plant, Units 1 and 2 - Report 05000327/2018006 and 05000328/2018006 ML19063D0842019-03-0404 March 2019 Annual Assessment Letter for Sequoyah Nuclear Plant, Units 1 and 2 - Report 05000327/2018006 and 05000328/2018006 ML18283A6232018-09-25025 September 2018 04 RP Inspection Document Request ML18240A3602018-08-24024 August 2018 Requalification Program Inspection ML18172A1182018-06-21021 June 2018 Notification of Inspection and Request for Information ML18059A1432018-02-28028 February 2018 EOC Assessment Letter ML18058B1632018-02-27027 February 2018 Emailed U1 ISI 2018002 RFI - Bcc IR 05000327/20170052017-08-24024 August 2017 Updated Inspection Plan for Sequoyah Updated Inspection Plant Units 1 and 2, Report 05000327/2017005 and 05000328/2017005 ML17146A1002017-05-25025 May 2017 Notification of Inspection and Request for Documents Dated May 25, 2017 ML17107A2602017-04-17017 April 2017 Notification of Inspection and Request for Information for NRC PI&R ML17115A4452017-04-17017 April 2017 Emergency Preparedness Inspection and Request for Information ML17067A4792017-03-0707 March 2017 Notification of Inspection and Request for Documents IR 05000327/20160062017-03-0101 March 2017 Annual Assessment Letter for Sequoyah Nuclear Plant, Units 1 & 2 (Report 05000327/2016006 and 05000328/2016006) ML16286A0622016-10-0606 October 2016 Notification of Inspection and Request for Information IR 05000327/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Sequoyah Nuclear Plant Units 1 and 2, NRC Inspection Report 05000327/2016005, 05000328/2016005 ML16076A0612016-03-15015 March 2016 Notification of Sequoyah Nuclear Plant - Component Design Bases Inspection - NRC Inspection Report 05000327/2016007, 05000328/2016007 ML16062A2622016-03-0202 March 2016 Annual Assessment Letter IR 05000327/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for the Sequoyah Nuclear Plant Units 1 and 2, NRC Inspection Report 005000327/2015005, 005000328/2015005 ML15084A4022015-03-25025 March 2015 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000327/20140012015-03-0404 March 2015 Annual Assessment Letter for Sequoyah Nuclear Plant Units 1 and 2, NRC Inspection Report 05000327/2014001, 05000328/2014001 IR 05000327/20140062014-09-0202 September 2014 Mid-Cycle Assessment Letter for Sequoyah, Units 1 and 2, Inspection Report 05000327/2014006, 05000328/2014003 ML14245A1212014-09-0202 September 2014 Mid-Cycle Assessment Letter for Sequoyah, Units 1 and 2, Inspection Report 05000327/2014006, 05000328/2014003 ML14072A0352014-03-10010 March 2014 Notification of Inspection and Request for Information ML14063A2472014-03-0404 March 2014 2013 Annual Assessment Letter for Sequoyah Nuclear Plant Units 1 and 2 ML13297A0732013-10-23023 October 2013 IR 05000327-14-007 & 05000328-14-007.Sequoyah Nuclear Plant, Units 1 & 2, Notification of a Triennial Fire Protection Baseline Inspection ML13246A1952013-09-0303 September 2013 Mid Cycle Assessment Letter IR 05000327/20120012013-03-0404 March 2013 Annual Assessment Letter for Sequoyah Nuclear Plant Units 1 and 2 (Report 05000327/2012001 and 05000328/2012001) ML12248A1042012-09-0404 September 2012 Mid Cycle Assessment Letter Sequoyah 2012 IR 05000327/20120062012-09-0404 September 2012 Mid Cycle Assessment Letter Sequoyah 2012 ML12065A3292012-03-0505 March 2012 RPT 22, Inspection/Activity Plan IR 05000382/20120012012-03-0505 March 2012 Annual Assessment Letter for Waterford Steam Electric Station-Unit 3 (Report 05000382-12-001) ML1124401842011-09-0101 September 2011 Inspection/Activity Report 22, 09/01/2011 - 12/31/2012 ML1106303542011-03-0404 March 2011 Inspection / Activity Plan, Report 22 ML1024408442010-09-0101 September 2010 Report 22 Inspection/Activity Plan 09/01/2010 - 12/31/2011 ML1006209872010-03-0303 March 2010 Inspection/Activity Plan 03/01/2010 - 06/30/2011 ML0924406512009-09-0101 September 2009 Inspection/Activity Plan 03/01/2009 - 12/31/2010 ML0906304382009-03-0404 March 2009 Inspection/Activity Plan 03/01/2009 - 06/30/2010 ML0824610082008-09-0202 September 2008 Inspection/Activity Plan, 09/02/2008 - 12/31/2009, Report 22 2023-08-29
[Table view] Category:Letter
MONTHYEARML24032A0202024-01-31031 January 2024 NPDES Biocide/Corrosion Treatment Plan Annual Report, Cy 2023 ML23319A2452024-01-29029 January 2024 Issuance of Amendment Nos. 366 and 360; 164 and 71 Regarding the Adoption of TSTF-567, Revision 1, Add Containment Sump TS to Address GSI-191 Issues CNL-24-017, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions2024-01-17017 January 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions ML24018A0142024-01-17017 January 2024 Engine Systems, Inc., Report No. 10CFR21-0137, Rev. 1, 56913-EN 56913 ML24011A3182024-01-11011 January 2024 Submittal of Discharge Monitoring Report (Dmr), October 2023 ML24011A3172024-01-11011 January 2024 Submittal of Discharge Monitoring Report (Dmr), September 2023 ML24011A3202024-01-11011 January 2024 Submittal of Discharge Monitoring Report (Dmr), December 2023 ML24011A3162024-01-11011 January 2024 Submittal of Discharge Monitoring Report (Dmr), August 2023 ML24011A3192024-01-11011 January 2024 Submittal of Discharge Monitoring Report (Dmr), November 2023 IR 05000327/20234422024-01-11011 January 2024 95001 Supplemental Inspection Report 05000327/2023442 and 05000328/2023442 and Follow-Up Assessment Letter ML24010A2132024-01-10010 January 2024 CFR 21.21 Final Report Regarding Siemens Medium Voltage Circuit Breakers ML24018A0952024-01-0404 January 2024 Engine Systems, Inc., 10CFR21 Reporting of Defects and Non-Compliance Report No. 10CFR21-0137, Rev. 0 ML24004A0332024-01-0303 January 2024 Interim Report of a Deviation or Failure to Comply Crompton Instruments Type 077 Ammeter ML24004A0402024-01-0303 January 2024 Response to NRCs November 8, 2023, Request for Additional Information - Related to Independent Spent Fuel Storage Installation CNL-23-068, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-21021 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation CNL-23-036, Application to Revise Function 5 of Technical Specification Table 3.3.2-1, Engineered Safety Feature Actuation System Instrumentation, for the Sequoyah Nuclear Plant and Watts Bar Nuclear Plant (SQN-TS-23-02 and WBN-TS-23-08)2023-12-18018 December 2023 Application to Revise Function 5 of Technical Specification Table 3.3.2-1, Engineered Safety Feature Actuation System Instrumentation, for the Sequoyah Nuclear Plant and Watts Bar Nuclear Plant (SQN-TS-23-02 and WBN-TS-23-08) ML23346A1222023-12-12012 December 2023 Annual Non-Radiological Environmental Operating Report - 2023 IR 05000327/20234202023-11-28028 November 2023 Security Baseline Inspection Report 05000327/2023420 and 05000328/2023420 CNL-23-067, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-11-27027 November 2023 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML23324A4362023-11-0909 November 2023 Exam Corporate Notification Letter Aka 210-day Letter ML23307A0822023-11-0808 November 2023 Request for Additional Information August 4, 2022, Exemption Request for Deviating from the Conditions of Certificate of Compliance No. 1032, Amendment No. 3, Related to Sequoyah Nuclear Plant Independent Spent Fuel Storage Installation IR 05000327/20230032023-11-0303 November 2023 Integrated Inspection Report 05000327/2023003 and 05000328/2023003 ML23306A1592023-11-0202 November 2023 Enforcement Action EA-22-129 Inspection Readiness Notification ML23292A0792023-10-19019 October 2023 Tennessee Valley Authority - Emergency Plan Implementing Procedure Revision, Includes EPIP-5, Revision 58, General Emergency IR 05000327/20230112023-10-16016 October 2023 Triennial Fire Protection Inspection Report 05000327/2023011 and 05000328/2023011 ML23285A0882023-10-12012 October 2023 Submittal of Sequoyah Nuclear Plant, Units 1 and 2, Submittal of Updated Final Safety Analysis Report Amendment 31 ML23284A4252023-10-11011 October 2023 10 CFR 50.59 and 10 CFR 72.48 Changes, Tests, and Experiments Summary Report; Commitment Summary Report; and Update to the Fire Protection Report ML23283A2792023-10-10010 October 2023 Revisions to the Sequoyah Nuclear Plant Units 1 and 2 Technical Requirements Manual ML23279A0612023-10-0505 October 2023 Paragon Energy Solutions LLC, Part 21 Final Report Re Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) ML23277A0462023-10-0404 October 2023 Revisions to the Sequoyah Nuclear Plant Units 1 and 2 Technical Specification Bases ML23275A0272023-09-29029 September 2023 Submittal of Discharge Monitoring Report (DMR) Quality Assurance Study 43 Final Report 2023 ML23271A1662023-09-28028 September 2023 Registration of Spent Fuel Storage Cask Pursuant to 10 CFR 72.212(b)(2) CNL-23-059, Supplement to Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-2023-09-20020 September 2023 Supplement to Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 CNL-23-061, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision2023-09-20020 September 2023 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision IR 05000327/20234032023-09-14014 September 2023 Cyber Security Inspection Report 05000327/2023403 and 05000328/2023403 (Cover Letter) ML23257A0062023-09-14014 September 2023 Enforcement Action EA-22-129 Inspection Postponement Request ML23254A2192023-09-11011 September 2023 Emergency Plan Implementing Procedure Revisions ML23254A0652023-09-0707 September 2023 Registration of Spent Fuel Storage Cask Pursuant to 10 CFR 72.212(b)(2) CNL-23-057, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC-EPIP-1, Revision 76 and CECC-EPIP-9, Revision 642023-09-0505 September 2023 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC-EPIP-1, Revision 76 and CECC-EPIP-9, Revision 64 IR 05000327/20230052023-08-29029 August 2023 Updated Inspection Plan for Sequoyah Nuclear Plant, Units 1 and 2 - Report 05000327/2023005 and 05000328/2023005 ML23233A0122023-08-17017 August 2023 Unit 1 Cycle 25 Refueling Outage - 90-Day Inservice Inspection Summary Report - Supplement ML23233A0142023-08-15015 August 2023 Discharge Monitoring Report (Dmr), July 2023 ML23215A1212023-08-0303 August 2023 301 Exam Administrative Items (2B) Normal Release ML23215A1572023-08-0303 August 2023 Enforcement Action EA-22-129 Inspection Readiness Notification CNL-23-028, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 and WBN-TS-23-06)2023-08-0202 August 2023 Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 and WBN-TS-23-06) ML23192A4472023-07-31031 July 2023 Staff Assessment of Updated Seismic Hazards at TVA Sites Following the NRC Process for the Ongoing Assessment of Natural Hazards Information 2024-01-04
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION ber 1, 2015
SUBJECT:
MID-CYCLE ASSESSMENT LETTER FOR THE SEQUOYAH NUCLEAR PLANT UNITS 1 AND 2, NRC INSPECTION REPORT 005000327/2015005, 005000328/2015005
Dear Mr. Shea:
On August 13, 2015, the NRC completed its mid-cycle performance review of Sequoyah Nuclear Plant. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2014 through June 30, 2015.
This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.
The NRC determined that overall, Sequoyah Nuclear Plant operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at Sequoyah Nuclear Plant during the most recent quarter was within the Licensee Response Column of the NRCs Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.
The enclosed inspection plan lists the inspections scheduled through June 30, 2017. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the second half of the inspection plan are tentative and may be revised at the end-of-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence.
In addition to the routine ROP baseline inspections at your facility, we also plan on conducting infrequently performed inspections which include: Inspection Procedure (IP) 43004, Inspection of Commercial-Grade Dedication Programs, and an initial operator license examination. In response to the accident at Fukushima, the Commission issued Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events. This Order requires licensees to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities following a beyond-design-basis external event. Additionally, the Commission issued Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation. This Order requires licensees to have a reliable means of remotely monitoring wide-range Spent Fuel Pool levels to support effective prioritization of event mitigation and recovery actions in the event of a beyond-design-basis external event. The NRC is conducting audits of licensee efforts towards compliance with these Orders. The audit was completed for Sequoyah Nuclear Plant, and the information gathered will aid staff in development of the Safety Evaluation for the site. After the NRC staff receives the Final Compliance letter for the site, the Final Safety Evaluation will be issued. Then, the NRC staff will confirm through inspections the full implementation of the orders mentioned above performing TI 191: Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi-Unit Dose Assessment Plans.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at 404-997-4415 with any questions you have regarding this letter.
Sincerely,
/RA/
Alan Blamey, Chief Reactor Projects Branch 6 Division of Reactor Projects Docket Nos.: 50-327, 50-328 License Nos. DPR-77, DPR-79 Enclosure: Sequoyah Inspection/Activity Plan (7/01/2015 - 06/30/2017)
cc distribution via ListServ
_________________________ XSUNSI REVIEW COMPLETE OFFICE RII:DRP RII:DRP RII:DRP SIGNATURE BDB3 CRK1 AJB3 NAME BBISHOP CKONTZ ABLAMEY DATE 8/26/2015 8/25/2015 8/31/2015 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO Letter to Joseph Shea from Alan Blamey dated September 1, 2015 SUBJECT: MID-CYCLE ASSESSMENT LETTER FOR THE SEQUOYAH NUCLEAR PLANT UNITS 1 AND 2, NRC INSPECTION REPORT 005000327/2015005, 005000328/2015005 DISTRIBUTION:
D. Gamberoni, RII L. Gibson, RII OE Mail RIDSNRRDIRS PUBLIC A. Adams, NRR RidsNrrPMSequoyah Resource ROP Assessment ROP Reports Institute of Nuclear Power Operations (INPO)
Page 1 of 2 Sequoyah 09/01/2015 10:29:19 Inspection / Activity Plan Report 22 09/01/2015 - 06/30/2017 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site EP - EP PROGRAM INSPECTION 4 1, 2 10/12/2015 10/16/2015 IP 7111402 Alert and Notification System Testing 1, 2 10/12/2015 10/16/2015 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 1, 2 10/12/2015 10/16/2015 IP 7111404 Emergency Action Level and Emergency Plan Changes 1, 2 10/12/2015 10/16/2015 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 1, 2 10/12/2015 10/16/2015 IP 71151 Performance Indicator Verification RP - RAD HAZARDS ANALYSIS AND TRANSPORTATION 2 1, 2 11/16/2015 11/20/2015 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 11/16/2015 11/20/2015 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 1, 2 11/16/2015 11/20/2015 IP 71151 Performance Indicator Verification ISI - UNIT 2 IN-SERVICE INSPECTION 1 2 11/23/2015 11/27/2015 IP 7111108P Inservice Inspection Activities - PWR OL EXAM - INITIAL LICENSE EXAM PREP 3 1 02/08/2016 02/12/2016 V23466 SEQUOYAH MARCH 2016 INITIAL EXAM AT POWER FACILITIES OL EXAM - INITIAL LICENSE EXAM 3 1 03/07/2016 03/18/2016 V23466 SEQUOYAH MARCH 2016 INITIAL EXAM AT POWER FACILITIES CDBI - COMPONENT DESIGN BASES INSPECTION 7 1, 2 04/25/2016 04/29/2016 IP 7111121 Component Design Bases Inspection 1, 2 05/09/2016 05/13/2016 IP 7111121 Component Design Bases Inspection 1, 2 05/23/2016 05/27/2016 IP 7111121 Component Design Bases Inspection 1, 2 06/13/2016 06/17/2016 IP 7111121 Component Design Bases Inspection EP - EP EXERCISE INSPECTION 6 1, 2 09/12/2016 09/16/2016 IP 7111401 Exercise Evaluation 1, 2 09/12/2016 09/16/2016 IP 7111404 Emergency Action Level and Emergency Plan Changes 1, 2 09/12/2016 09/16/2016 IP 7111408 Exercise Evaluation - Scenario Review 1, 2 09/12/2016 09/16/2016 IP 71151 Performance Indicator Verification RP - RP OCCUPATIONAL INSPECTION WEEK 1 2 1, 2 10/31/2016 11/04/2016 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 10/31/2016 11/04/2016 IP 71124.02 Occupational ALARA Planning and Controls 1, 2 10/31/2016 11/04/2016 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 10/31/2016 11/04/2016 IP 71124.04 Occupational Dose Assessment 1, 2 10/31/2016 11/04/2016 IP 71124.05 Radiation Monitoring Instrumentation 1, 2 10/31/2016 11/04/2016 IP 71151 Performance Indicator Verification This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures. Enclosure
Page 2 of 2 Sequoyah 09/01/2015 10:29:19 Inspection / Activity Plan Report 22 09/01/2015 - 06/30/2017 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site ISI - UNIT 1 IN-SERVICE INSPECTION 1 1 11/07/2016 11/11/2016 IP 7111108P Inservice Inspection Activities - PWR RP - RP OCCUPATIONAL INSPECTION WEEK 2 3 1, 2 11/14/2016 11/18/2016 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 11/14/2016 11/18/2016 IP 71124.02 Occupational ALARA Planning and Controls 1, 2 11/14/2016 11/18/2016 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 11/14/2016 11/18/2016 IP 71124.04 Occupational Dose Assessment 1, 2 11/14/2016 11/18/2016 IP 71124.05 Radiation Monitoring Instrumentation 1, 2 11/14/2016 11/18/2016 IP 71151 Performance Indicator Verification SGISI - UNIT 1 SG IN-SERVICE INSPECTION 1 1 11/14/2016 11/18/2016 IP 7111108P Inservice Inspection Activities - PWR TFPI - TRIENNIEL FIRE PROTECTION INSPECTION 5 1, 2 03/20/2017 03/24/2017 IP 7111105T Fire Protection [Triennial]
1, 2 04/03/2017 04/07/2017 IP 7111105T Fire Protection [Triennial]
ISI - UNIT 2 IN-SERVICE INSPECTION 1 2 05/01/2017 05/05/2017 IP 7111108P Inservice Inspection Activities - PWR RP - RAD HAZARDS AND PIV 1 1, 2 05/01/2017 05/05/2017 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 05/01/2017 05/05/2017 IP 71151 Performance Indicator Verification PI&R - PROBLEM IDENTIFICATION AND RESOLUTION 5 1, 2 06/05/2017 06/09/2017 IP 71152B Problem Identification and Resolution 1, 2 06/19/2017 06/23/2017 IP 71152B Problem Identification and Resolution This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures. Enclosure