IR 05000315/2019012

From kanterella
Jump to navigation Jump to search
Triennial Fire Protection Inspection Report 05000315/2019012 and 05000316/2019012
ML19301C355
Person / Time
Site: Cook  American Electric Power icon.png
Issue date: 10/28/2019
From: Robert Daley
Engineering Branch 3
To: Gebbie J
Indiana Michigan Power Co
References
IR 2019012
Download: ML19301C355 (13)


Text

ber 28, 2019

SUBJECT:

DONALD C. COOK NUCLEAR PLANT, UNITS 1 AND 2 - TRIENNIAL FIRE PROTECTION INSPECTION REPORT 05000315/2019012 AND 05000316/2019012

Dear Mr. Gebbie:

On September 27, 2019, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Donald C. Cook Nuclear Plant, Units 1 and 2. On September 26, 2019, the NRC inspectors discussed the results of this inspection with you and other members of your staff.

The results of this inspection are documented in the enclosed report.

One finding of very low safety significance (Green) is documented in this report. This finding involved a violation of NRC requirements. We are treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violation or significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; the Director, Office of Enforcement; and the NRC Resident Inspector at D.C. Cook.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; and the NRC Resident Inspector at Donald C. Cook. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Robert C. Daley, Chief Engineering Branch 3 Division of Reactor Safety Docket Nos. 05000315 and 05000316 License Nos. DPR-58 and DPR-74

Enclosure:

As stated

Inspection Report

Docket Numbers: 05000315 and 05000316 License Numbers: DPR-58 and DPR-74 Report Numbers: 05000315/2019012 and 05000316/2019012 Enterprise Identifier: I-2019-012-0027 Licensee: Indiana Michigan Power Company Nuclear Generation Group Facility: Donald C. Cook Nuclear Plant, Units 1 and 2 Location: Bridgman, MI Inspection Dates: August 26, 2019 to September 27, 2019 Inspectors: I. Hafeez, Reactor Inspector G. Hausman, Senior Reactor Inspector A. Shaikh, Senior Reactor Inspector Approved By: Robert C. Daley, Chief Engineering Branch 3 Division of Reactor Safety Enclosure

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a triennial fire protection inspection at Donald C. Cook Nuclear Plant, Units 1 and 2 in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations Failure to Include Appropriate Acceptance Criteria In Fire Protection Water System Flow Test Procedure Cornerstone Significance Cross-Cutting Report Aspect Section Mitigating Green [H.6] - Design 71111.05XT Systems NCV 05000316,05000315/2019012-01 Margins Open/Closed The inspectors identified a finding of very-low safety significance and associated violation of Technical Specification 5.4 Procedures, for the licensees failure to maintain fire protection water system flow test procedure. Specifically, the licensee failed to maintain Procedure 12-FPP-4030-066-006, Three Year Fire Protection System Unobstructed Flow Test, by not including appropriate acceptance criteria in the procedure to demonstrate that adequate fire protection water flow and pressure would be delivered to various fire suppression loads in the plant.

Additional Tracking Items None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.05XT - Fire Protection - NFPA 805 Fire Protection Inspection Requirements (IP Section 02.01a)

The inspectors evaluated fire protection program implementation in the following selected areas and/or fire zones, including analyzed electrical circuits:

(1) AA5/6 (6M) Unit 2 Auxiliary Building (Aux Building Middle West)

Analyzed Circuits: (Include if applicable)

  • West Charging Pump
(2) AA40
(41) Unit 1 ESS and MCC Rooms Analyzed Circuits: (Include if applicable)
  • SG#1 Water Level(Wide Range) Control Rm Indication
(3) AA44 (46A/B/C/D) Unit 2 Emergency Power Area (All zones)

Analyzed Circuits: (Include if applicable)

(4) AA48 (55 & 56) Unit 1 SWGR Cable Vault and Aux Cable Vault

B.5.b Inspection Activities (IP Section 02.03) (1 Sample)

The inspectors evaluated the following B.5.b Mitigating Strategies:

(1)

  • Make up to Refueling Water Storage Tank (RWST)
  • Make up to Condensate Storage Tank (CST)

INSPECTION RESULTS

Failure to Include Appropriate Acceptance Criteria In Fire Protection Water System Flow Test Procedure Cornerstone Significance Cross-Cutting Report Aspect Section Mitigating Green [H.6] - Design 71111.05XT Systems NCV 05000316,05000315/2019012-01 Margins Open/Closed The inspectors identified a finding of very-low safety significance and associated violation of Technical Specification 5.4 Procedures, for the licensees failure to maintain fire protection water system flow test procedure. Specifically, the licensee failed to maintain Procedure 12-FPP-4030-066-006, Three Year Fire Protection System Unobstructed Flow Test, by not including appropriate acceptance criteria in the procedure to demonstrate that adequate fire protection water flow and pressure would be delivered to various fire suppression loads in the plant.

Description:

On September 29, 2016, Procedure 12-FPP-4030-066-006, Revision 7 was implemented to meet the requirements of Technical Requirements Surveillance (TRS)8.7.5.20 and thereby, establish operability of the fire suppression water system per Technical Requirements Manual (TRM) 8.7.5. TRM 8.7.5, states, in part, that the fire suppression water system shall be operable with an operable flow path capable of taking suction from either one of the fire water tanks and transferring the water through protected area distribution piping and TRS 8.7.5.20 requires, in part, that the licensee verify, by a series of full flow tests, every fire main segment to be clear of obstruction. Section 1.0 of procedure 12-FPP-4030-066-006 states, in part, that the purpose of this procedure is to verify that the fire mains are clear and free of obstructions and that this procedure complies with Unit 1 and Unit 2 TRM TRS 8.7.5.20. Procedure 12-FPP-4030-066-006, Section 5.0, Acceptance Criteria, states, in part, that the fire protection engineer verifies that the flow loop test demonstrates adequate, unimpeded system flow for the system to perform its intended fire protection functions. However, the inspectors identified that no quantitative acceptance criteria was included in the procedure for the fire protection engineer to verify that the flow and pressure measurements taken during the flow test demonstrated unimpeded flow and that the fire suppression system would be able to perform its intended fire protection function of supplying adequate flow and pressure to various suppression loads throughout the plant. Specifically, the licensee stated that at the time of the test, no quantitative acceptance criteria for maximum allowed pressure loss in the system piping had been established for this test and a general trend in pressure and flow measurements taken during each test was used to qualitatively access the degradation of the fire suppression system piping. The inspectors determined that the licensee could therefore not have verified the operability of the fire suppression water system because the maximum allowed pressure loss for the system to still be able to perform its fire protection functions was not known. The inspectors further determined that in December 2016, the licensee performed a calculation to determine the maximum allowed pressure losses in the system piping to be used as the acceptance criteria for procedure 12-FPP-4030-066-006 for future tests. The inspectors questioned the licensee's acceptance of the September 29, 2016, test against the new quantitative acceptance criteria and the licensee stated that no determination had been conducted to ensure that the previous September 29, 2016, test was satisfactory. In order to address the inspector's question and concern regarding the September 29, 2016, test, the licensee reconciled the test data against the new quantitative acceptance criteria and determined that the test had failed the acceptance criteria and therefore, the licensee would have failed to meet TRS 8.7.5.20 and TRM 8.7.5. In addition, during the inspection, the licensee conducted its Three Year Fire Protection System Unobstructed Flow Test to meet TRM 8.7.5 and TRS 8.7.5.20 requirements utilizing the new quantitative acceptance criteria and again failed the test. Therefore, the licensee declared the fire suppression water system inoperable per TRM 8.7.5.

Corrective Actions: The licensee documented the failed flow tests of 2016 and 2019 and the inspectors' concerns into its corrective action program (CAP) and implemented immediate corrective action to align a backup source of fire suppression system water distribution as required by TRM 8.7.5 action item. In addition, the licensee had reached out to its contractor that performed the quantitative hydraulic calculation to re-evaluate the plant's fire suppression system piping flow model and the licensee intends to inspect and determine which sections of piping may be obstructed.

Corrective Action References:

AR 2019-9028; NRC Identified Finding for 12-FPP-4030-066-006 Done in 2016 AR 2019-8760; Loop 3 FP Flow Test Did Not Meet Acceptance Criteria

Performance Assessment:

Performance Deficiency: The inspectors determined that the licensee's failure to include appropriate acceptance criteria in the fire protection suppression water system flow test procedure 12-FPP-4030-066-006, Revision 7 was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Protection Against External Factors attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, the failure to include acceptance criteria in the flow test procedure resulted in the licensee accepting the fire protection suppression system flow test as satisfactory even though the system would not be able to automatically meet the pressure and flow requirements for various automatic suppression loads in the plant. Therefore, this failure adversely affected the mitigating system cornerstone objective of ensuring the availability, reliability and capability of systems that respond to initiating events (fire) to prevent undesirable consequences (i.e., core damage).

Significance: The inspectors assessed the significance of the finding using Appendix F, Fire Protection and Post - Fire Safe Shutdown SDP. The inspectors screened the finding using Appendix F, Attachment 1, Part 1: Fire Protection SDP Phase 1 Worksheet, dated September 20, 2013. The inspectors answered YES to Question 1.4.3.A, Would adequate fire water capacity (flow and required pressure) still be available for protection of equipment important to safe shutdown in the most limiting location onsite? Specifically, the licensee had the capability to manually start a second fire pump to augment the lowered pressure and flow seen by the fire suppression system due to the main distribution piping obstructions. Therefore, the inspectors determined that adequate fire water capacity would still be available to provide protection of equipment important to safe shutdown in the most limiting location onsite and that the finding screened as having very-low safety significance (Green).

Cross-Cutting Aspect: H.6 - Design Margins: The organization operates and maintains equipment within design margins. Margins are carefully guarded and changed only through a systematic and rigorous process. Special attention is placed on maintaining fission product barriers, defense-in-depth, and safety related equipment. Specifically, the inspectors determined that the licensee failed to understand, calculate and guard the absolute design margins of pressure and flow required for adequate suppression capabilities onsite and instead relied on relative trending data to establish system capability resulting in the licensee's failure to incorporate acceptance criteria into its flow test procedure that would maintain the fire water system within its design margins.

Enforcement:

Violation: TRM 8.7.5, states, in part, that the fire suppression water system shall be operable with an operable flow path capable of taking suction from either one of the fire water tanks and transferring the water through protected area distribution piping and TRS 8.7.5.20 requires, in part, that the licensee verify, by a series of full flow tests, every fire main segment to be clear of obstruction. Procedure 12-FPP-4030-066-006 Revision7 was used to ensure this requirement was met; however, this procedure contained no acceptance criteria to ensure the adequacy of flow. Technical Specification 5.4.1.d requires, in part, that, written procedures shall be established, implemented, and maintained covering the Fire Protection Program implementation. Contrary to the above, on September 29, 2016, the licensee did not have a procedure that implemented the Fire Protection Program requirement in the TRM (8.7.5) to verify that the fire distribution piping was free of obstruction and operable. Specifically, procedure 12-FPP-4030-066-006 Revision 7, Three Year Fire Protection Water System Unobstructed Flow Test did not contain acceptance criteria to verify that the fire protection water system could meet its intended fire protection function.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On September 26, 2019, the inspectors presented the triennial fire protection inspection results to Joel P. Gebbie and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection Type Designation Description or Title Revision or

Procedure Date

71111.05XT Calculations MD-12-HV-013-N AB & CD Battery Rooms Hydrogen Evolution 2

PRA-NB-FIRE- Fire PRA Model Quantification Notebook 1

FQ

R2684-1098-000 Unobstructed Flow Test Acceptance Criteria 12/22/2016

Corrective Action AR 2016-7239 NFPA 805 Monitoring Program FPRA/Maintenance 06/16/2016

Documents Performance

GT 2014-13933 Change NFPA 805 Higher Risk Evaluation (HRE) Definition 11/05/2014

GT 2016-12812 NFPA 805 Monitoring Program - return systems to a(2) 11/04/2016

status

Corrective Action AR 2019-8242 12-OHP-4026-EDM-001 Observations 08/28/2019

Documents AR 2019-8593 Additional Spare Batteries needed for NFPA 805 09/10/2019

Resulting from Headlamps

Inspection AR 2019-8712 Possible Enhancements to 12-OHP-4025-001-002 09/12/2019

AR 2019-9028 NRC Identified Finding for 12-FPP-4030-066-006 Done in 09/24/2019

2016

AR 2019-9101 NRC Observation from 2019 Fire Protection Triennial 09/26/2019

Drawings 2-5724E Heating & Ventilation Cable Enclosure Area & Battery 1

Room @ El.625'-0" Unit 2

OP-2-5148C Flow Diagram Diesel Generator Area & Elec. Switchgear 31

Rooms Heating & Ventilation Sys. Unit #2

OP-2-98731 Area Heating Elementary Diagram 15

OP-2-98741 Aux Bldg Ventilation Sheet No. 1 Elementary Diagram 36

Engineering EC-0000053523 Modify U1 East 600V SWGR RM Mezz Area C02 from 5

Changes Manual to Automatic

Engineering Engineering Emergency Power Systems Area and EPS Control Rod 04/03/2017

Evaluations Equivalency Drive Room Fire Door Closure Evaluation

Evaluation 11-71

Fire Plans FPMP NFPA 805 Monitoring Program Analysis 3

FSA Fire Area: AA5/6 - Auxiliary Building (El. 587 ft.) 3

FSA Fire Area: AA40 - Unit 1 Engineered Safeguards Systems 3

and Motor Control Center Room

Inspection Type Designation Description or Title Revision or

Procedure Date

(El. 609 ft. 6 in.)

FSA Fire Area: AA44 - Unit 2 Emergency Power Systems Area 3

(El. 609 ft. 6 in.)

FSA Fire Area: AA48 - Unit 1 Switchgear Rooms Cable Vault 3

and Auxiliary Cable Vault (El. 625 ft. 10 in. and 620 ft. 6 in.)

Miscellaneous ES-PIPE-1013- Pipe Material Specification 10

QCN

FAQ 10-0059 NFPA 805 Monitoring 6

NFPA 805 Performance-Based Standard for Fire Protection for Light 2001 Edition

Water Reactor Electric Generating Plants

TRM Technical Requirements Manual 80

Procedures 1-OHP-4025-LS- Process Monitoring from LSI Panels 3

1-OHP-4025-LS- Start-up AFW 5

1-OHP-4025-LS- Start-up AFW 7

1-OHP-4025-LS- RCS Make-up with CVCS Cross-tie 6

1-OHP-4025-LTI- Local Main Steam Isolation 1

2-FPE-2270- Fire Protection Program Change Evaluations (FPCE) 3

FPCE-001

2-FPE-2270- Fire Protection Required SSC Monitoring Program 1

FPMP-001

2-FPP-2270- Fire Truck Inventory and Operability Test 14

066-005

2-FPP-2270- Hydrostatic Testing and Re-Rack of Fire Hose 10

066-024

2-FPP-2270- Other Fire Protection Equipment Inspections 29

066-030

2-FPP-2270- Functional Check and Inspection of the Hale Portable 9

066-037 Pumps

2-FPP-4030- Three Year Fire Protection Water System Unobstructed 7

Inspection Type Designation Description or Title Revision or

Procedure Date

066-006 Flow Test

2-OHP-4025- Fire Response Guidelines 7

001-002

2-OHP-4025- Fire Response Guidelines 19

001-002

2-OHP-4026- Extensive Damage Mitigation Initial Response 8

EDM-001

2-OHP-4026- Extensive Damage Mitigation Enhanced Site Response 6

EDM-002 Strategies

2-IHP-4030-266- Unit 2 Engineered Safety Switchgear CO2 Fire Suppression 2

2 Test

2-OHP-4025-LS- Process Monitoring from LSI Panels 3

2-OHP-4025-LS- RCS Make-up with CVCS Cross-tie 8

NFPPM NFPA 805 Fire Protection Program Manual 3

PMP-2270-CCM- Control of Combustible Materials 24

001

PMP-2270-CCM- Control of Combustible Materials 43

001

PMP-2270-SDR- Fire Protection Suppression, Detection Systems, and Rated 17

001 Assemblies

PMP-4030--001- Impact of Safety Related Ventilation on the Operability of 31

001 Technical Specification Equipment

PMP-4100-SDR- Outage Risk Assessment and Management 13

2

Work Orders 12-PP-144 Electric Fire Pump Test 07/17/2018

2-PP-145E Diesel Fire Pump Test 07/18/2018

55470909 3 Year Fire Protection Water Flow Test 09/26/2016

55470910 3 Year Fire Protection Water Flow Test 09/28/2016

55499733 OPFP, U-2 Turb Bldg, Hydro Test/Re-Rack Fire Hose 06/27/2018

55506058 OPFP, Annual Hydro Test of Misc Fire Hose Outside P.A. 06/06/2018

55521410 OPFP, Hale Portable Pumps Accessory Inspection 07/25/2019

10