Annual Assessment Letter for D.C. Cook Nuclear Power Plant, Units 1 and 2 (Report 05000315/2011007 and 05000316/2011007)
ML12065A112
Person / Time
Site: Cook  American Electric Power icon.png
Issue date: 03/05/2012
From: Jack Giessner
Reactor Projects Region 3 Branch 4
To: Weber L
Indiana Michigan Power Co, Nuclear Generation Group
References
IR-11-007
Download: ML12065A112 (6)


Text

March 5, 2012

SUBJECT:

ANNUAL ASSESSMENT LETTER FOR D.C. COOK NUCLEAR POWER PLANT, UNITS 1 AND 2 (REPORT 05000315/2011007 AND 05000316/2011007)

Dear Mr. Weber:

On February 15, 2012, the NRC staff completed its end-of-cycle performance review of D.C. Cook Nuclear Power Plant, Units 1 and 2. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions for the period from January 1, 2011, through December 31, 2011. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.

This performance review and enclosed inspection plan do not include security information. A separate letter will include the NRCs assessment of your performance in the Security Cornerstone and its security-related inspection plan.

The NRC determined that overall, D.C. Cook Nuclear Power Plant Units 1 and 2, operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at D.C. Cook Nuclear Power Plant Units 1 and 2 during the most recent quarter was within the Licensee Response Column of the NRC=s Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.

The enclosed inspection plan lists the inspections scheduled through June 30, 2013. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last 9 months of the inspection plan are tentative and may be revised at the mid-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. We also plan on conducting several special and infrequently performed Inspection Procedures (IPs) which include: IP 60854.1, Preoperational Testing of Independent Spent Fuel Storage Installation (ISFSIs) at Operating Plants; IP 60855.1, Operation of an ISFSI at Operating Plants; IP 60856.1, Review of 10 CFR 72.212(b) Evaluations at Operating Plants; and IP 92709, Licensee Strike Contingency Plans.

In accordance with 10 CFR 2.390 of the NRC=s ARules of Practice,@ a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at 630-829-9619 with any questions you may have regarding this letter.

Sincerely,

/RA/

John B. Giessner, Chief Branch 4 Division of Reactor Projects Docket Nos. 50-315 and 50-316 License Nos. DPR-58 and DPR-74 Enclosure: D.C. Cook Inspection/Activity Plan cc w/encl: Distribution via ListServ

Page 1 of 2 D.C. Cook Inspection / Activity Plan 01/01/2012 - 06/30/2013 Planned Dates No. of Staff Start End Inspection Activity Title on Site ISFSI - ISFSI INSPECTION - SCHEDULE DEPENDENT 2 01/01/2012 05/31/2012 IP 60856 Review of 10 CFR 72.212(b) Evaluations 01/01/2012 05/31/2012 IP 60856.1 Review of 10 CFR 72.212(b) Evaluations at Operating Plants 02/01/2012 06/30/2012 IP 60854.1 Preoperational Testing of Independent Spent Fuel Storage Facility Installation at Operating Plants TI-177 - TI-2515/177 - GAS VOIDING IN ECCS PIPING 2 01/23/2012 02/10/2012 IP 2515/177 Managing Gas Accumulation In Emergency Core Cooling, Decay Heat Removal & Containment Spray System BI EPR - EP ROUTINE INSPECTION / PI VERIFICATION 1 02/13/2012 02/17/2012 IP 7111402 Alert and Notification System Testing 02/13/2012 02/17/2012 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 02/13/2012 02/17/2012 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 02/13/2012 02/17/2012 IP 71151 Performance Indicator Verification STRIKE - STRIKE CONTINGENCY - RP/EM/MM 2 02/16/2012 03/16/2012 IP 92709 Licensee Strike Contingency Plans BI OLRQ - BIENNIAL REQUAL PROGRAM INSPECTION 3 02/27/2012 03/02/2012 IP 7111111B Licensed Operator Requalification Program BI ISI - INSERVICE INSPECTION - UNIT 2 1 03/19/2012 04/27/2012 IP 7111108P Inservice Inspection Activities - PWR BI RP - RADIATION PROTECTION BASELINE INSPECTIO 1 03/26/2012 03/30/2012 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 03/26/2012 03/30/2012 IP 71124.02 Occupational ALARA Planning and Controls TI-182 - TI-2515/182 PHASE I - BURIED PIPING 1 05/07/2012 05/09/2012 IP 2515/182 Review of the Implementation of the Industry Initiative to Control Degradation of Underground Piping ISFSI - ISFSI INSPECTION - SCHEDULE DEPENDENT 1 06/01/2012 11/30/2012 IP 60855.1 Operation of an Independent Spent Fuel Storage Installation at Operating Plants OL PREP - INITIAL EXAM PREP - JULY 2012 4 06/25/2012 06/29/2012 W90252 OL - INITIAL EXAM - 2012 JULY - COOK BI CDBI - COMPONENT DESIIGN BASIS INSPECT & TI-177 4 07/23/2012 08/24/2012 IP 7111121 Component Design Bases Inspection OL EXAM - INITIAL EXAMS - JULY 2012 4 07/23/2012 08/03/2012 W90252 OL - INITIAL EXAM - 2012 JULY - COOK BI RP - RADIATION PROTECTION BASELINE INSPECTIO 1 08/06/2012 08/10/2012 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 08/06/2012 08/10/2012 IP 71124.02 Occupational ALARA Planning and Controls

Page 2 of 2 D.C. Cook Inspection / Activity Plan 01/01/2012 - 06/30/2013 Planned Dates No. of Staff Start End Inspection Activity Title on Site BI RP - RADIATION PROTECTION BASELINE INSPECTIO 1 08/06/2012 08/10/2012 IP 71151-BI01 Reactor Coolant System Activity 08/06/2012 08/10/2012 IP 71151-OR01 Occupational Exposure Control Effectiveness 08/06/2012 08/10/2012 IP 71151-PR01 RETS/ODCM Radiological Effluent BI RP - RADIATION PROTECTION BASELINE INSPECTIO 1 09/10/2012 09/14/2012 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation BI HS - TRIENNIAL HEAT SINK INSPECTION 2 11/26/2012 11/30/2012 IP 7111107T Heat Sink Performance BI RP - RADIATION PROTECTION BASELINE INSPECTIO 1 12/10/2012 12/14/2012 IP 71124.05 Radiation Monitoring Instrumentation BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 02/04/2013 02/08/2013 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 02/04/2013 02/08/2013 IP 71124.04 Occupational Dose Assessment BI OLRQ - REQUALIFICATION PROGRAM INSPECTION 1 02/25/2013 03/01/2013 IP 7111111A Licensed Operator Requalification Program - Annual Review BI ISI - INSERVICE INSPECTION - UNIT 1 1 03/27/2013 04/28/2013 IP 7111108P Inservice Inspection Activities - PWR RENEWAL - LICENSE RENEWAL INSPECTION-71003 PHASE 1 2 03/27/2013 04/28/2013 IP 71003 Post-Approval Site Inspection for License Renewal BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 04/08/2013 04/12/2013 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 04/08/2013 04/12/2013 IP 71124.02 Occupational ALARA Planning and Controls BI FIRE - FIRE PROTECTION INSPECTION & BAG TRIP 3 05/27/2013 06/28/2013 IP 7111105T Fire Protection [Triennial]

BI EPX - EP EXERCISE INSPECTION / PI VERIFICATION 2 06/03/2013 06/07/2013 IP 7111401 Exercise Evaluation 06/03/2013 06/07/2013 IP 71151 Performance Indicator Verification