IR 05000313/2022006

From kanterella
Jump to navigation Jump to search
Annual Assessment Letter for Arkansas Nuclear One Units 1 and 2 (Report 05000313/2022006 and 05000368/2022006)
ML23055B067
Person / Time
Site: Arkansas Nuclear  Entergy icon.png
Issue date: 03/01/2023
From: John Dixon
NRC/RGN-IV/DORS
To: Sullivan J
Entergy Operations
Shared Package
ML23055B060 List:
References
IR 2022006
Download: ML23055B067 (1)


Text

March 01, 2023

SUBJECT:

ANNUAL ASSESSMENT LETTER FOR ARKANSAS NUCLEAR ONE - UNITS 1 AND 2 (REPORT 05000313/2022006 AND 05000368/2022006)

Dear Joseph Sullivan:

The U.S. Nuclear Regulatory Commission (NRC) has completed its end-of-cycle performance assessment of Arkansas Nuclear One, Units 1 and 2, reviewing performance indicators (PIs),

inspection results, and enforcement actions from January 1, 2022, through December 31, 2022.

This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. The NRC concluded that overall performance at your facility preserved public health and safety. The baseline inspection program was completed at your facility as defined in Inspection Manual Chapter 2515, Light-Water Reactor Inspection Program - Operations Phase.

The NRC determined the performance at Arkansas Nuclear One, Units 1 and 2 during the most recent quarter was within the Licensee Response Column, the highest performance category of the NRCs Reactor Oversight Process (ROP) Action Matrix, because all inspection findings had very low safety significance (i.e., Green), and all PIs were within the expected range (i.e.,

Green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.

The enclosed inspection plan lists the inspections scheduled through December 31, 2024.

The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.

In response to the COVID-19 public health emergency (PHE), the NRC adjusted inspection plans and schedules to safeguard the health and safety of both NRC and licensee staff while still effectively implementing the ROP. While the PHE continues, overall conditions throughout the country support performance of our inspection and oversight activities returning to normal onsite presence by our resident and region-based inspectors and completion of nominal baseline inspection samples. We continue to monitor site-specific conditions and, as discussed in our November 2, 2021, memo, Implementation of Inspection Programs Following Re-Entry from the Public Health Emergency for the Reactor Safety Program (ML21295A302), it may be necessary to alter how and when we perform our inspection and oversight activities as we balance the importance of protecting the health and safety of our staff with the need to conduct effective oversight that supports the NRCs critical safety mission.

For inspections requiring extensive coordination with offsite organizations, such as evaluated emergency preparedness exercises, NRC guidance and frequently asked questions for security and emergency preparedness can be found here: https://www.nrc.gov/about-nrc/covid-19/security-ep/. Similarly, the NRC has developed guidance if force-on-force inspections cannot be completed as scheduled due to an emergency, such as the COVID-19 PHE. These changes help ensure the health and safety of both NRC and licensee staff while maintaining the NRCs important safety and security mission during the COVID-19 PHE. The attached inspection plan is accurate on the date of issuance but remains subject to change based on approval of potential exemption requests or other changes needed due to changing conditions in the COVID-19 PHE. NRC staff will contact your appropriate regulatory affairs staff in order to coordinate inspection planning and scheduling.

Beginning on January 1, 2023, the engineering inspection frequency will transition from a triennial (3-year) to a quadrennial (4-year) cycle. The new engineering inspection program will consist of a Comprehensive Engineering Team Inspection (CETI)(1) and three Focused Engineering Inspections (FEIs) that will be performed in each quadrennial cycle. For the cycle beginning in 2023, the FEIs will be: Fire Protection Team Inspection, Commercial Grade Dedication and Age-Related Degradation.

In accordance with Title 10 of the Code of Federal Regulations 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

1 Aspects of the Design Basis Assurance Inspection (DBAI), Evaluations of Changes, Tests, & Experiments, and Heat Sink inspections will be included in the new CETI inspection. Previously scheduled Evaluation of Changes, Tests, & Experiments and Heat Sink inspections have been cancelled and removed from attached Report 22. Please contact me at 817-200-1574 with any questions you have regarding this letter.

Sincerely, Signed by Dixon, John on 03/01/23 John L. Dixon, Jr., Chief Project Branch D Division of Operating Reactor Safety Docket Nos. 05000313, 05000368 License Nos. DPR-51, NPF-6 Enclosure:

Inspection Plan cc w/ encl: Distribution via LISTSERV

ML23055B067 SUNSI Review ADAMS: Non-Publicly Available Non-Sensitive Keyword:

By: ASanchez Yes No Publicly Available Sensitive NRC-002 OFFICE SRI:DORS/D SPE:DORS/D BC:DORS/D NAME RBywater RLB ASanchez JDixon SIGNATURE /RA/ /RA/ /RA/

DATE 02/28/23 02/28/23 03/01/23

Site Inspection Activity Plan 07200013 - ANO (ISFSI)

01/01/2023 - 12/31/2024 Unit Start End Activity CAC Title Staff Count ANO ISFSI Inspection for Transition to Holtec FW System (Part 72) (Multiple weeks during timeframe) 4 9/1/2023 10/31/2023 IP 60854 001000 Preoperational Testing Of An ISFSI 9/1/2023 10/31/2023 IP 60855 001001 Operation Of An ISFSI 9/1/2023 10/31/2023 IP 60856 001003 Review of 10 CFR 72.212(b) Evaluations Prepared on 2/21/2023 9:23:52 AM 1 of 4

Site Inspection Activity Plan Arkansas Nuclear One 01/01/2023 - 12/31/2024 Unit Start End Activity CAC Title Staff Count ANO UNIT 2 2023 INITIAL EXAM 4 2 2/12/2023 2/18/2023 OV 000956 FB-OR-ONSITE VALIDATION OF INITIAL LICENSE EXAMINATION (OV)

2 3/19/2023 3/25/2023 EXAD 000500 FB-OR-INITIAL LICENSE EXAM ADMINISTRATION (EXAD)

Inservice Inspection 2R29 - ANO 1 2 4/17/2023 4/28/2023 IP 71111.08P 000702 Inservice Inspection Activities (PWR)

RP 1,4,PI - 2 1,2 4/24/2023 4/28/2023 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1,2 4/24/2023 4/28/2023 IP 71124.04 000728 Occupational Dose Assessment RP 6,7 2 1,2 6/12/2023 6/16/2023 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment 1,2 6/12/2023 6/16/2023 IP 71124.07 000731 Radiological Environmental Monitoring Program Security Access Authorization .01 - Access Control .02 + PIV + Plan Change .09 2 1,2 6/12/2023 6/16/2023 IP 71130.01 000733 Access Authorization 1,2 6/12/2023 6/16/2023 IP 71130.02 000734 Access Control 1,2 6/12/2023 6/16/2023 IP 71130.09 001656 Security Plan Changes 1,2 6/12/2023 6/16/2023 IP 71151 001338 Performance Indicator Verification ANO UNIT 1 2023 BRQ 3 1 7/9/2023 7/15/2023 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance ANO Biennial PI&R 4 1,2 8/7/2023 8/11/2023 IP 71152B 000747 Problem Identification and Resolution 1,2 8/21/2023 8/25/2023 IP 71152B 000747 Problem Identification and Resolution EP 2023 Program Inspection - ANO 1 1,2 8/28/2023 9/1/2023 IP 71114.02 000717 Alert and Notification System Testing 1,2 8/28/2023 9/1/2023 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 1,2 8/28/2023 9/1/2023 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 1,2 8/28/2023 9/1/2023 IP 71114.05 000720 Maintenance of Emergency Preparedness 1,2 8/28/2023 9/1/2023 IP 71151 001397 Performance Indicator Verification Commercial Grade Dedication Inspection - 21N - Arkansas Nuclear 3 1,2 9/11/2023 9/15/2023 IP 71111.21N.03 001808 Commercial Grade Dedication 1,2 9/25/2023 9/29/2023 IP 71111.21N.03 001808 Commercial Grade Dedication FORCE-ON-FORCE PLANNING AND EXERCISE - ANO 4 1,2 11/13/2023 11/17/2023 IP 71130.03 000735 Contingency Response - Force-On-Force Testing 1,2 12/11/2023 12/15/2023 IP 71130.03 000735 Contingency Response - Force-On-Force Testing Prepared on 2/21/2023 9:23:52 AM 2 of 4

Site Inspection Activity Plan Security FFD .08 1 1,2 11/13/2023 11/17/2023 IP 71130.08 000740 Fitness For Duty Program MC&A - 1 1,2 11/27/2023 12/1/2023 IP 71130.11 000742 Material Control and Accounting (MC&A)

ANO UNIT 1 2024 INITIAL EXAM 7 1 2/4/2024 2/10/2024 OV 000956 FB-OR-ONSITE VALIDATION OF INITIAL LICENSE EXAMINATION (OV)

1 3/3/2024 3/9/2024 EXAD 000500 FB-OR-INITIAL LICENSE EXAM ADMINISTRATION (EXAD)

Security Equipment (.04), Security Training (.07) 2 1,2 3/4/2024 3/8/2024 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance 1,2 3/4/2024 3/8/2024 IP 71130.07 000739 Security Training Inservice Inspection - ANO (U1) 1 1 4/15/2024 4/26/2024 IP 71111.08P 000702 Inservice Inspection Activities (PWR)

RP 5,8 2 1,2 7/8/2024 7/12/2024 IP 71124.05 000729 Radiation Monitoring Instrumentation 1,2 7/8/2024 7/12/2024 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, & Transportation ANO UNIT 2 2024 BRQ 3 2 7/14/2024 7/20/2024 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance Comprehensive Engineering Team Inspection - 21M - Arkansas Nuclear 7 1,2 7/15/2024 7/19/2024 IP 71111.21M 000713 Design Bases Assurance (DBA) Inspection 1,2 7/29/2024 8/2/2024 IP 71111.21M 000713 Design Bases Assurance (DBA) Inspection EP Exercise & PI Inspection (2024) - ANO 4 1,2 8/19/2024 8/23/2024 IP 71114.01 000716 Exercise Evaluation 1,2 8/19/2024 8/23/2024 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 1,2 8/19/2024 8/23/2024 IP 71151 001397 Performance Indicator Verification Cyber Security - ANO 4 1,2 8/19/2024 8/23/2024 IP 71130.10 000741 Cybersecurity Inservice Inspection - ANO (U2) 1 2 10/7/2024 10/18/2024 IP 71111.08P 000702 Inservice Inspection Activities (PWR)

RP 1,3,PI 2 1,2 10/7/2024 10/11/2024 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1,2 10/7/2024 10/11/2024 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation Security Access Control (.02), Security Plan Changes (.09), Security PIV (71151) 1 1,2 11/18/2024 11/22/2024 IP 71130.02 000734 Access Control 1,2 11/18/2024 11/22/2024 IP 71130.09 001656 Security Plan Changes 1,2 11/18/2024 11/22/2024 IP 71151 001338 Performance Indicator Verification Prepared on 2/21/2023 9:23:52 AM 3 of 4

Site Inspection Activity Plan Prepared on 2/21/2023 9:23:52 AM 4 of 4