IR 05000282/2018004

From kanterella
Jump to navigation Jump to search
NRC Integrated Inspection Report 05000282/2018004 and 05000306/2018004
ML19045A197
Person / Time
Site: Prairie Island  Xcel Energy icon.png
Issue date: 02/12/2019
From: Hironori Peterson
Region 3 Branch 3
To: Sharp S
Northern States Power Company, Minnesota
References
IR 2018004
Download: ML19045A197 (22)


Text

UNITED STATES ebruary 12, 2019

SUBJECT:

PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNITS 1 AND 2NRC INTEGRATED INSPECTION REPORT 05000282/2018004 AND 05000306/2018004

Dear Mr. Sharp:

On December 31, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Prairie Island Nuclear Generating Plant, Units 1 and 2. On January 10 and 22, 2019, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

Based on the results of this inspection, the NRC has identified one issue that was evaluated under the risk significance determination process as having very low safety significance (Green). The NRC has also determined that one violation was associated with this issue.

Because the licensee initiated condition reports to address this issue, this violation is being treated as a Non-Cited Violation (NCV), consistent with Section 2.3.2 of the Enforcement Policy.

The NCV is described in the subject inspection report. Further, the inspectors documented a licensee-identified violation which was determined to be of very low safety significance in this report. The NRC is treating this violation as a NCV consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violations or significance of the NCVs, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; the Director, Office of Enforcement; and the NRC Resident Inspector at the Prairie Island Nuclear Generating Plant. If you disagree with a cross-cutting aspect assignment or a finding not associated with a regulatory requirement in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; and the NRC resident inspector at the Prairie Island Nuclear Generating Plant.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, and Requests for Withholding.

Sincerely,

/RA/

Hironori Peterson, Chief Branch 3 Division of Reactor Projects Docket Nos. 50-282; 50-306;72-010 License Nos. DPR-42; DPR-60; SNM-2506 Enclosure:

IR 05000282/2018004; 05000306/2018004 cc: Distribution via LISTSERV

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring licensees performance by conducting an integrated quarterly inspection at Prairie Island Nuclear Generating Plant,

Units 1 and 2 in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

One self-revealed Green finding and Non-Cited Violation (NCV), and one licensee identified non-cited violation are documented in report section 71153.

List of Findings and Violations Failure to Develop Appropriate Clearance Order Results in Loss of Power to 4kV Bus 25 Cornerstone Significance Cross-Cutting Report Aspect Section Mitigating Green H.2 - Field 71153 Systems NCV 05000306/2018004-01 Presence Closed A Green finding and associated NCV of Title 10 CFR Part 50, Appendix B, Criterion V,

Instructions, Procedures, and Drawings, was self-revealed when the licensee failed to properly develop a Clearance Order (C/O) for modification activities within 4kV safeguards Bus 25.

Additional Tracking Items Type Issue Number Title Report Status Section LER 05000306/2018-001-00 Automatic Actuation of 71153 Closed Emergency Diesel Generator D5 LER 05000306/2018-001-01 Automatic Actuation of 71153 Closed Emergency Diesel Generator D5 LER 05000306/2018-002-00 RHR Flood Barriers 71153 Closed Compensatory Measures

TABLE OF CONTENTS

PLANT STATUS

INSPECTION SCOPES

................................................................................................................

REACTOR SAFETY

.....................................................................................................................

RADIATION SAFETY

...................................................................................................................

OTHER ACTIVITIES - BASELINE

..............................................................................................

INSPECTION RESULTS

............................................................................................................

EXIT MEETINGS AND DEBRIEFS

............................................................................................ 13

DOCUMENTS REVIEWED

........................................................................................................ 14

PLANT STATUS

Unit 1 began the inspection period shut down for refueling outage activities. On

October 30, 2018, Unit 1 returned to full power and remained at full power for the remainder of

the inspection period with the exception of brief down-power maneuvers to support surveillance

testing activities.

Unit 2 operated at full power for the entirety of the inspection period with the exception of brief

down-power maneuvers to support surveillance testing activities and a flexible power operations

demonstration on December 21, 2018.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in

effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with

their attached revision histories are located on the public website at http://www.nrc.gov/reading-

rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared

complete when the IP requirements most appropriate to the inspection activity were met

consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection

Program - Operations Phase. The inspectors performed plant status activities described in

IMC 2515 Appendix D, Plant Status and conducted routine reviews using IP 71152, Problem

Identification and Resolution. The inspectors reviewed selected procedures and records,

observed activities, and interviewed personnel to assess licensee performance and compliance

with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01Adverse Weather Protection

Winter Seasonal Readiness Preparations (1 Sample)

The inspectors evaluated the licensees preparations for winter conditions to verify that the

plants design features and implementation of procedures were sufficient to protect

mitigating systems from the effects of adverse weather.

71111.04Equipment Alignment

Partial Walkdown (4 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following

systems/trains:

(1) Spent Fuel Pool Heat Exchangers and Pumps on October 3, 2018;

(2) Buses 15, 112 and 113 on November 28, 2018;

(3) No. 22 Diesel-Driven Cooling Water Pump on December 10, 2018; and

(4) Buses 25, 26 and 27 on December 18, 2018.

71111.05QAFire Protection Quarterly/Annual

Quarterly Inspection (5 Samples)

The inspectors evaluated fire protection program implementation in the following selected

areas:

(1) Fire Zone 43: Buses 111 and 121 on November 28, 2018;

(2) Fire Zones 1 and 35: 11, 12, 21 and 22 Battery rooms on October 31, 2018;

(3) Fire Zone 31; 121 & 122 Control Room Chiller Rooms; Revision 41;

(4) Fire Zone 97: D5 and D6 Emergency Diesel Generator (EDG) rooms on

November 27, 2018; and

(5) Fire Zones 26 and 50: A and B Event Monitoring Rooms on November 28, 2018.

Annual Inspection (1 Sample)

The inspectors evaluated fire brigade performance for a simulated fire in the No. 122 Diesel-

Driven Fire Pump Fuel Oil Storage Tank berm area on October 30, 2018.

71111.07Heat Sink Performance

Heat Sink (1 Sample)

The inspectors evaluated 11 Component Cooling Heat Exchanger performance on

October 3, 2018.

71111.08In-Service Inspection Activities (1 Sample)

The inspectors assessed the effectiveness of the licensees programs for monitoring

degradation of the Unit 1 reactor coolant system boundary, risk-significant piping system

boundaries, and the containment boundary by reviewing the following activities from

September 26, 2018 to October 11, 2018:

(1) Ultrasonic examination of: volume control system welds W-1 and W-2, reactor coolant

system drain line piping weld 2-RC10A; and the pressurizer shell welds W-2 and W-5.

(2) Visual VT-3 examination of: the internal casing surfaces of the No. 12 Reactor Coolant

Pump (RCP); and the Auxiliary Feedwater (AFW) system pipe support hanger H1

(Drawing ISI-69A).

(3) Fabrication of welds 3 and 4 in the residual heat removal system under Work Order 00535854-01 Install Vents/Valves for Voids.

(4) Fabrication of welds 1 and 2 in the steam generator blowdown system under Work Order 00388028-01 Replace MV 32040, 11 Steam Generator (SG) B Isolation Train B.

(5) Bare metal visual examination of the Unit 1 vessel head penetration nozzles.

(6) Boric acid evaluations and related corrective actions: Evaluation 5430 VC-16-24 12-

RCP Seal Water Injection Line Vent, Evaluation 5450 MV-32077-Sump B to 11

Residual Heat Removal System Pump and AR 01538861 1FE-459 -Bolted

Connection.

(7) Eddy current examination of tubes in Unit 1 SGs 11 and 12.

71111.11 A and QLicensed Operator Requalification Program and Licensed Operator

Performance

Operator Requalification (1 Sample)

(1) The inspectors observed and evaluated a licensed operator requalification scenario

(Cycle 18F) on November 27, 2018.

Operator Performance (1 Sample)

(1) The inspectors observed and evaluated operator response to an unexpected control rod

withdrawal of 3 steps on Unit 1 on November 13, 2018.

Operator Exams (1 Sample)

The inspectors reviewed and evaluated requalification examination results on

December 19, 2018.

71111.12Maintenance Effectiveness

Routine Maintenance Effectiveness (2 Samples)

The inspectors evaluated the effectiveness of routine maintenance activities associated

with the following equipment and/or safety significant functions:

(1) Valve gland follower issues on October 31, 2018; and

(2) Balance of plant controller issues on December 10, 2018.

71111.13Maintenance Risk Assessments and Emergent Work Control (2 Samples)

The inspectors evaluated the risk assessments for the following planned and emergent

work activities:

(1) Motor-operated valve disconnected conduit issue on October 30, 2018; and

(2) No. 12 Diesel-Driven Cooling Water pump leaking anode on December 11, 2018.

71111.15Operability Determinations and Functionality Assessments (6 Samples)

The inspectors evaluated the following operability determinations and functionality

assessments:

(1) AR 501000016536: Unacceptable Void Found in 2RH-01 on October 24, 2018;

(2) AR 501000017940: Equipment Environment QualificationFlood Level Elevation

Incorrect on October 26, 2018;

(3) AR 501000019966: Gas Accumulation Management Program: 12 RHR Discharge Void

Locations on November 15, 2018;

(4) AR 501000020578: Refueling Water Storage Tank Leaking into Sump B on

December 6, 2018;

(5) AR 501000020995: Equipment Environment QualificationCable Noncompliance-X2

Compartment on December 14, 2018; and

(6) AR 501000020132: D6 E2 LO Press Switch Leak, 2PSL-6673 on December 26, 2018.

71111.18Plant Modifications (1 Sample)

The inspectors evaluated the following permanent modification:

(1) EC 25124 D1 Breaker 15-2 NFPA 805 Modification on November 29, 2018.

71111.19Post Maintenance Testing (4 Samples)

The inspectors evaluated the following post maintenance tests:

(1) SP 1106B; 22 Diesel Cooling Water Pump Monthly Test; Revision 95 following leak

identified from a jacket water hose on October 17, 2018;

(2) SP 1103B; Unit 1 Train B AFW Cold Shutdown Testing; Revision 1 on October 27, 2018;

(3) SP 1003; Analog Protection Functional Test; Revision 78 following variable gain unit

emergent work on November 15, 2018; and

(4) SP 1295; D1 Diesel Generator 6 Month Fast Start Test; Revision 63 following 2-Year

Preventative Maintenance on December 8, 2018.

71111.20Refueling and Other Outage Activities (1 Sample)

The inspectors evaluated Refueling Outage 1R31 activities from September 23 through

October 30, 2018.

71111.22Surveillance Testing

The inspectors evaluated the following surveillance tests:

Routine (4 Samples)

(1) SP 1083A; Unit 1 Integrated Safety Injection (SI) Test with a Simulated Loss of Offsite

Power Train A; Revision 10, and SP 1083B; Unit 1 Integrated SI Test with a Simulated

Loss of Offsite Power Train B; Revision 10 on October 16, 2018;

(2) SP 11106B; 22 Diesel Cooling Water Pump Monthly Test; Revision 95 on

October 18, 2018;

(3) SP 2855; Monthly 4kV Bus 25 Undervoltage Relay Test (OMICRON); Revision 7 on

November 6, 2018; and

(4) SP 2015; 4kV Bus 21/22 Under-Voltage & Under-Frequency Test; Revision 33 on

November 27, 2018.

Containment Isolation Valve (1 Sample)

(1) SP 1072.29B; Local Leak Rate Test of Penetration 29B (Containment Spray);

Revision 31 on October 4, 2018.

71114.04Emergency Action Level and Emergency Plan Changes (1 Sample)

The inspectors completed the evaluation of submitted Emergency Action Level and

Emergency Plan changes on December 18, 2018. This evaluation does not constitute

NRC approval.

RADIATION SAFETY

71124.01Radiological Hazard Assessment and Exposure Controls

Radiological Hazard Assessment (1 Sample)

The inspectors evaluated radiological hazards assessments and controls.

Instructions to Workers (1 Sample)

The inspectors evaluated worker instructions.

Contamination and Radioactive Material Control (1 Sample)

The inspectors evaluated contamination and radioactive material controls.

Radiological Hazards Control and Work Coverage (1 Sample)

The inspectors evaluated radiological hazards control and work coverage.

High Radiation Area and Very High Radiation Area Controls (1 Sample)

The inspectors evaluated risk-significant high radiation area and very high radiation area

controls.

Radiation Worker Performance and Radiation Protection Technician Proficiency (1 Sample)

The inspectors evaluated radiation worker performance and radiation protection technician

proficiency.

71124.02Occupational As Low As Reasonably Achievable Planning and Controls

The inspectors evaluated the licensees radiological work planning by reviewing the

following activities:

(1) Radiation Work Permit (RWP) 181031; 1R31Sump C Inspection; Revision 00;

(2) RWP 181013; 1R31Residual Heat Removal (RHR) Pit Work; Revision 01;

(3) RWP 181040; 1R31Refuel Work; Revision 00; and

(4) RWP 181071; 1R31Steam Generator (SG) Primary Side Work; Revision 00.

Verification of Dose Estimates and Exposure Tracking Systems (1 Sample)

The inspectors evaluated dose estimates and exposure tracking.

Implementation of As Low As Reasonably Achievable and Radiological Work Controls

(Partial Sample)

The inspectors reviewed As Low As Reasonably Achievable (ALARA) practices and

radiological work controls by reviewing the following activities:

(1) RWP 181031; 1R31Sump C Inspection; Revision 00;

(2) RWP 181013; 1R31Residual Heat Removal Pit Work; Revision 01;

(3) RWP 181040; 1R31Refuel Work; Revision 00; and

(4) RWP 181071; 1R31SG Primary Side Work; Revision 00.

Radiation Worker Performance (1 Sample)

The inspectors evaluated radiation worker and radiation protection technician performance.

No findings or violations were identified.

OTHER ACTIVITIES - BASELINE

71151Performance Indicator Verification (6 Samples)

The inspectors verified licensee performance indicators submittals listed below:

(1) MS06: Emergency AC Power Systems (2 Samples)

(October 1, 2017-September 30, 2018);

(2) MS09: RHR Systems (2 Samples)

(October 1, 2017-September 30, 2018); and

(3) MS10: Cooling Water Support Systems (2 Samples)

(October 1, 2017-September 30, 2018).

71152Problem Identification and Resolution

Semiannual Trend Review (1 Sample)

The inspectors reviewed the licensees corrective action program for trends that might be

indicative of a more significant safety issue. See Inspection Results below for more details.

71153Follow-Up of Events and Notices of Enforcement Discretion

Licensee Event Reports (2 Samples)

The inspectors evaluated the following licensee event reports which can be accessed at

https://lersearch.inl.gov/LERSearchCriteria.aspx:

(1) (Closed) Licensee Event Report (LER) 05000306/2018-001-00 & 05000306/2018-001-01;

Automatic Actuation of Emergency Diesel Generator D5; issued July 16 and September 17,

2018, respectively. See Inspection Results below for more details.

(2) (Closed) LER 05000306/2018-002-00; RHR Flood Barriers Compensatory Measures;

issued July 18, 2018. See Inspection Results below for more details.

INSPECTION RESULTS

71152Problem Identification and Resolution

Observation 71152Semi Annual Trend Review

During the inspection period, the licensee identified several trends. Notably, the licensee

identified potential trends in gas accumulation in the Unit 1 RHR system (no impact to safety

function), and a potential trend in minor jacket water leaks identified following the performance

of maintenance on EDGs at the site. The inspectors reviewed the inputs, evaluations, and

planned actions associated with these trends, and also performed their own search of the

corrective action program to validate that all inputs were considered. Although some of the

evaluations were ongoing at the end of the inspection period, the inspectors held discussions

with licensee management to understand interim actions taken to mitigate the trends until final

corrective actions were taken.

The inspectors did not identify any concerns with the licensees interim actions and

determined that the scope of each evaluation was appropriate.

71153Follow-Up of Events and Notices of Enforcement Discretion

Licensee Identified Non-Cited Violation 71153

This violation of very low safety significance was identified by the licensee and has been

entered into the licensee corrective action program and is being treated as a NCV, consistent

with Section 2.3.2 of the Enforcement Policy.

Enforcement:

Violation: Prairie Island Technical Specification (TS) Limiting Condition for Operation 3.9.5

states, in part, one RHR loop shall be operable and in operation while in Mode 6 with water

level greater than, or equal to, above the top of the reactor vessel flange.

Contrary to the above, on October 19, 2017, the licensee removed a flood barrier floor plug

that rendered the No. 22 RHR pump inoperable for 28 hours3.240741e-4 days <br />0.00778 hours <br />4.62963e-5 weeks <br />1.0654e-5 months <br /> and 40 minutes (greater than the

Immediate and 4-hour TS-Required Action Completion Times of TS 3.9.5, Condition A).

Because the No. 21 RHR pump was out-of-service while the flood barrier was removed, a

condition existed where the RHR safety function could have been impacted if a postulated

internal flood event had occurred.

Significance/Severity Level: The failure to restore the flood barrier floor plug prior to the

expiration of the TS Action Completion time was considered a performance deficiency. The

inspectors determined the performance deficiency was more than minor because it adversely

affected the Mitigating Systems Cornerstone attribute of configuration control. The inspectors

attempted to screen the finding using IMC 0609, Appendix G, Attachment 1 Shutdown

Operations Significance Determination Process Phase 1 Initial Screening and

Characterization of Findings. The inspectors answered Yes to Question 2 of Exhibit 3

because the condition represented a loss of safety function for 28 hours3.240741e-4 days <br />0.00778 hours <br />4.62963e-5 weeks <br />1.0654e-5 months <br /> and 40 minutes, and

thus required further review using IMC 0609, Appendix G, Attachment 2, Phase 2 SDP

Template for PWR During Shutdown. An NRC Region III senior risk analyst reviewed the

finding and confirmed it to be very low safety significance (Green) based on the condition

existing while the refueling cavity was flooded-up (aka Plant Operating State-3), where a

potential Loss of Residual Heat Removal would have negligible impact.

Corrective Action Reference: AR 501000012293

This Licensee Identified NCV closes LER 05000306/2018-002-00.

Failure to Develop Appropriate Clearance Order Results in Loss of Power to 4kV Bus 25

Cornerstone Significance Cross-Cutting Aspect Report

Section

Mitigating Systems Green H.2Field Presence 71153

NCV 05000306/2018004-01

Closed

Introduction:

A Green finding and associated NCV of Title 10 CFR Part 50, Appendix B, Criterion V,

Instructions, Procedures, and Drawings, was self-revealed when the licensee failed to

properly develop a Clearance Order (C/O) for modification activities within 4kV safeguards

Bus 25. This resulted in the de-energization of the bus, the automatic actuation, loading and

unloading of the D5 EDG, and a loss of available power to Unit 2 A train safeguards

equipment for 52 minutes.

This issue was documented in LERs 05000306/2018001-001-00 and-01, Automatic

Actuation of Emergency Diesel Generator D5.

Description:

On May 17, 2018, with Unit 2 operating at full power, a complete loss of power occurred to

4kV Bus 25 with a subsequent valid actuation of the D5 EDG during the performance of

modification activities within Bus 25. The D5 supply breaker closed onto Bus 25 as designed,

but immediately tripped open. Operators responded to the event and restored power to

Bus 25 within 52 minutes. The inspectors observed operator response to this event and

reviewed the event timeline, use of response procedures, and immediate corrective

actions. The event response and inspector activities were documented in Section 71153 of

Prairie Island Inspection Report 2018002.

Following the event, the licensee conducted a root cause evaluation (RCE) to identify root and

contributing causes, as well as corrective actions. The licensee also submitted an 8-hour

Event Notification for the valid actuation of the D5 EDG, and also submitted a LER. The

inspectors reviewed the RCE and LER that identified an overall lack of risk recognition as part

of the modification preparation/planning, development of tagging and clearances, and also

oversight of supplemental personnel for the physical work that was being conducted on

May 17, 2018. The licensee determined that several programmatic deficiencies and

inappropriate decisions were made that led to workers inappropriately manipulating a potential

transformer drawer for the energized Bus 25 causing the event.

The licensee determined that C/O development was inappropriate, in that,

C/O 2-EA 7000282-0150, TD Install Conduit Cable for PT to Breaker 25-16, for the

modification was not properly screened on December 14, 2017 as an Exceptional C/O per

station procedure FP-OP-TAG-01, Fleet Tagging, Revision 34. Had the C/O been properly

developed, the site would have altered the work instructions to avoid work in the proximity to

an energized potential transformer drawer, or the work would have been scheduled to coincide

with a Bus 25 outage window.

Corrective Actions: Corrective actions to address the root and contributing causes included

implementation of a nuclear risk mitigation program, revision to supplemental oversight

procedures, and the study and development of rigorous walk-down expectations for the

Design, Maintenance, and Operations planning departments. Also, the site revised

FP-OP-TAG-01 to ensure that all tagging and clearances associated with modifications were

designated as complex and exceptional. Corrective actions were also planned to install

locking devices for Bus potential transformer drawers during the next planned bus

outages. Interim actions were taken to preclude opening of the drawers until locking devices

are installed.

Corrective Action Reference: AR 501000012089

Performance Assessment:

Performance Deficiency: The inspectors determined that the failure to accomplish

FP-OP-TAG-01, Fleet Tagging, Revision 34 in the development of a C/O for modification

activities within 4kV safeguards Bus 25, was a performance deficiency. The cause of the

issue of concern was reasonably within the licensees ability to foresee and correct and

the issue of concern should have been prevented. Specifically, by failing to accomplish

FP-OP-TAG-01, an inadequate C/O was created that led to Bus 25 to be de-energized.

Screening: The inspectors determined the performance deficiency was more than minor, and

a finding, because it adversely affected the Mitigating Systems Cornerstone Attribute of

Configuration Control to ensure the availability, reliability, and capability of systems that

respond to initiating events to prevent undesirable consequences. Specifically, the licensees

failure to properly develop a C/O for modification activities within 4kV Bus 25 (a Mitigating

System) led to the unavailability of Bus 25 for approximately 52 minutes.

Significance: The inspectors assessed the significance of the finding using IMC 0609,

Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The

finding screened as very low safety significance (Green) because the inspectors answered No

to Questions A.1 to A.4 under Exhibit 2Mitigating Systems Screening Questions due to the

finding not representing an actual loss of function of a single train for greater than its Technical

Specification-allowed outage time.

Cross-cutting Aspect: The finding had a cross-cutting aspect in the Field Presence

component of the Human Performance cross-cutting area that states that leaders are

commonly seen in the work areas of the plant observing, coaching, and reinforcing standards

and expectations. Deviations from standards and expectations are corrected promptly.

Senior managers ensure supervisory and management oversight of work activities, including

contractors and supplemental personnel. Specifically, several standards and expectations

were not reinforced during the development of the open phase modification, and oversight was

lacking on several occasions during the work control process. (H.2)

Enforcement:

Violation: Title 10 CFR Part 50, Appendix B, Criterion V, Instructions, Procedures, and

Drawings, requires, in part, that activities affecting quality be prescribed by documented

procedures of a type appropriate to the circumstances and be accomplished in accordance

with these procedures. The licensee prescribed procedure FP-OP-TAG-01, Fleet Tagging,

Revision 34, as the implementing procedure for establishing a safe tagging boundary for

C/O 2-EA 700007282-0150: TD INSTALL CONDUIT CABLE FOR PT TO BKR25-16

(EC 26784), an activity affecting quality for safety-related Bus 25 modifications.

Procedure FP-OP-TAG-01, Step 5.3.1 stated, in part, The Clearance Order Preparer

SHALL screen for Exceptional C/Os. Additionally, Step 4.15 stated, in part, that Examples of

[Exceptional C/Os] would include: All stored energy cannot be relieved from within a blocking

boundary.

Contrary to the above, on December 14, 2017, the licensee failed to accomplish Step 5.3.1 of

procedure FP-OP-TAG-01. Specifically, the Clearance Order Preparer did not screen

C/O 2-EA 700007282-0150 as an Exceptional C/O as evidenced by answering NO to the

question, "Is this an EXCEPTIONAL Tagout?" in the Attributes Section of the Electronic

Tagout system. In fact, this C/O was an EXCEPTIONAL Tagout due to the inability to relieve

all stored energy within the Bus 25 BKR 25-16 blocking boundary for the activity affecting

quality.

This self-revealed Green NCV closes LER 05000306/2018-001-00 and-01.

EXIT MEETINGS AND DEBRIEFS

The inspectors confirmed that proprietary information was controlled to protect from public

disclosure. No proprietary information was documented in this report.

  • On October 4, 2018, the inspectors presented the radiation protection program inspection

results to Mr.

J. Boesch, acting General Manager-Maintain, and other members of the

licensee staff.

  • On October 11, 2018, the inspector presented the inservice inspection activities results to

Mr.

T. Conboy, Director of Site Operations, and other members of the licensee staff.
  • On December 19, 2018, the inspector presented the completed 2018 Licensed Operator

Requalification Program annual operating test inspection results with Mr.

S. Sarrasin,

Operations Training Program Supervisor.

results to Mr.

B. Carberry, Emergency Preparedness Manager, and other members of the

licensee staff.

  • On January 10 and 22, 2019, the inspectors presented the quarterly integrated inspection

results to Mr.

S. Sharp, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

The following is a list of documents reviewed during the inspection. Inclusion on this list does

not imply that the NRC inspectors reviewed the documents in their entirety but rather that

selected sections of portions of the documents were evaluated as part of the overall inspection

effort. Inclusion of a document on this list does not imply NRC acceptance of the document or

any part of it, unless this is stated in the body of the inspection report.

71111.01Adverse Weather

- TP 1637; Winter Plant Operation; Revision 54

71111.04Equipment Alignment

- C1.1.20.6-1; Unit 1 480V System Switches and Indication Checklist; Revision 39

- C1.1.20.5-1; Unit 1 4.6kV System Switches and Indication Checklist; Revision 28

- F5 Appendix A; Fire Detection Zone 43Fire Areas 22 & 80; Revision 43

- F5 Appendix A; Fire Strategies Symbols Legend; Revision 39

- C1.1.20.5-2; Unit 2 4.16 kV System Switches and Indication Checklist; Revision 30

- AR 501000021170; Missing Brass Plug on Breaker 26-16; 12/16/2018

71111.05AQFire Protection

- Fire Drill Critique Report; 122 DDFP Day Tank Berm Area; 11/26/2018

- Fire Detection Zone 74; Screenhouse Ground Floor; Revision 34

- Fire Detection Zone 43; Bus 111 and 121 Switchgear Rooms; Revision 43

- Fire Detection Zone 1; 695 Level Turbine Building, Battery Room 11 & 12; Revision 27

- Fire Detection Zone 35; Battery Room 21 and 22; Revision 30

- Fire Zone 31; 121 and 122 Control Room Chiller Rooms; Revision 41

- Fire Detection Zone 26; Bus 112 and Train A Event Monitoring Rooms; Revision 34

- Fire Detection Zone 50; Bus 122 and Train B Event Monitoring Rooms; Revision 11

- Fire Detection Zone 97; D5/D6 Building; Revision 34

71111.07Heat Sink Performance

- NF-39245-1; Component Cooling System Unit 1 Flow Diagram; Revision 84

- NF-39245-2; Component Cooling System Unit 1 Flow Diagram; Revision 81

71111.08Inservice Inspection Activities

- 51-9200443-001; Prairie Island Unit 1 Condition Monitoring for EOC27 and Final Operational

Assessment for Cycles 28, 29, and 30; Revision 1

- ACTS NSP-18-OXP-10041; X-Probe Array 41 IPS; Revision 0

- ACTS NSP-18-OXP-10022; X-Probe Array 22 IPS; Revision 0

- ACTS NSP-18-O-BOB-A; Bobbin 48 IPS; Revision 0

- ACTS NSP-18-O-BOB-B; Bobbin 24 IPS; Revision 1

- ACTS NSP-18-O-BOB-C; Bobbin 12 IPS; Revision 1

- AR 501000017818; 1R31 SP 1403 Relevant Indications; 10/01/2018

- AR 501000017733; NRC Observation 2018 ISI Inspection; 09/28/2018

- AR 501000012442; LTR NRC 18-34; CRDM Thermal Sleeve Part 21; 07/19/2018

- AR 501000011605; Risk Failure to Perform Pressure Test; 05/03/2018

- AR 500001555855; Valve VC-15-56 Diaphragm Failed; 07/14/2017

- AR 500001542542; Water Found on Flange and Fitting VC-16-24; 11/18/2016

- AR 500001540887; SP 1168.13 Active Leak SI-145-2; 11/17/2016

- AR 500001540890; MV-32068 1SAF Injection Loop B Leak; 11/07/2016

- AR 500001539956; 12 RCP NDE Non-Relevant Indications; 10/29/2016

- AR 500001539574; 1R30 Foreign Material Found in 11 SG LPTS; 10/27/2016

- AR 500001538861; SP 1392 Bolted Connections ISI Indications; 10/21/2016

- AR 500001452005; Preliminary Flaw Indications in U1 Baffle Assembly; 10/24/2014

- EVAL 5430; VC-16-24 12 RCP Seal Water Injection Line Vent; 12/19/2016

- EVAL 5450; MV--32077 Sump B to 11 RCP Pump; 02/07/2017

- MRJTRC-2354; Site Validated Inspection Techniques Fall 2018 SG Inspection; Revision 0

- Personnel Certification Record; E. Fennern-UT Level II; 08/07/2018

- Personnel Certification Record; A. Jensen-UT Level III; 08/07/2018

- Personnel Certification Record; A. Jensen-VT-2 Level III; 08/07/2018

- Personnel Certification Record; K. Wickenheiser-VT-2 Level II; 07/19/2018

- PQR PAL-SM-8-8(2) Revision 0

- PQR DAEC-PrQR-W-12; Revision 1

- PQR NSP-PQR-1270/1271; Revision 0

- PQR DAEC-W-66; Revision 0

- PQR PBNP-WP-6; Revision 0

- PQR KNPP-GMP-102-311-GS-PQR; Revision 0

- PQR PAL-SM-1-1(1); Revision 0

- PI-400-001; Multi-frequency Eddy Current of Non-Ferromagnetic SG Tubing-Prairie Island

Nuclear Generating Station; Revision 15

- H2; Boric Acid Corrosion Control Program; Revision 28

- H25.0 SG Program; Revision 23

- H25.3 SG Tube Repair Criteria; Revision 11

- 54-ISI-366-012; VT-1 and VT-3 Examinations; 06/19/2014

- FP-PE-NDE-402; UT of Austenitic Pipe Welds-Supplement 2; Revision 7

- FP-PE-NDE-406; Ultrasonic Examination of Reactor Pressure Vessel Welds; Revision 3

- FP-PE-NDE-530; Visual Examination VT-3; Revision 8

- MRS-GEN-1240; Steam Generator Position Verification; Revision 6

- MRS-GEN-1245 Steam Generator Tube Plugging Procedure Specification for Rolled

Mechanical Plugs; Revision 1

- SWI NDE-ET-1; Bobbin Data Analysis; Revision 9

- SWI NDE-ET-3; Rotating Coil Data Analysis; Revision 8

- SWI NDE-ET-6; Array Coil Data Analysis; Revision 4

- SWI NDE-VT-6.0; Visual Examination for Leakage on Reactor Vessel Penetrations (VT-2);

Revision 3

- Report 2016VE001; Visual Examination12 RCP Pump Internals; 10/27/2016

- Report 2018VE001; Visual ExaminationReactor Closure Head Bare Metal Visual Exam;

10/02/2018

- Report 2018U020; UT Calibration/Examination-Pressurizer Top Head/Shell Weld W-5;

10/02/2018

- Report 2018U021; UT Calibration/Examination-Pressurizer Vertical Shell Weld W-2;

10/02/2018

- Report 2018U009; UT Calibration/ExaminationVC System W-1; 10/01/2018

- Report 2018U010; UT Calibration/Examination-VC System W-2; 10/01/2018

- Report 2018U014; Visual Examination of Pipe Hanger, Support or Restraint (VT-3)-AFW

System Hanger H1 Drawing ISI-69A; 10/10/2018

- Report BOP-UT-18-10; UT Calibration/Examination-Weld 2-RC-10A 2018U020; 10/01/2018

- Report BOP-PT-16-023; Liquid Penetrant Examination of Welds 3-7 and 9-31; 09/15/2016

- Report BOP-VT-16-002; Visual System Leakage (VT-2) Replaced Flange Joints/Welds;

11/02/2016

- Report BOP-PT-16-067; Liquid Penetrant Examination of Welds 1 and 2; 11/06/2016

- Report BOP-VT-16-050; Visual Examination System Leakage (VT-2) MV-32040 and

Adjacent Welds; 11/19/2016

- SG-SGMP-18-3; Prairie Island U1R31 SG Degradation Assessment; Revision 0

- Weld Control Record; Welds 1-4, WCR 535854-03-1; 09/15/2016

- Work Order 00535854-01; EC26588; Install Vents/Valves for RHR Voids (B Train);

11/01/2016

- Work Order 00388028-01; Replace MV-32040-11 SGB Isolation Train B; 11/06/2016

- WPS FP-PE-B31-P8P8-GTSM-03; Revision 5

- WPS FP-PE-B31-P1P1-GTSM-001; Revision 3

71111.11QLicensed Operator Requalification

- Simulator Exercise Guide P9118ST-0605; Cycle 18F Simulator Session #2; Revision 0

71111.12Maintenance Effectiveness

- AR 501000019081; Indications of Cracked Gland Follower; 10/24/2018

- AR 501000019059; 1R31 EOC VC-16-24 Gland Follower; 10/24/2018

- Type 2-Operational Decision Making Issue Evaluation; Operational Maintenance Strategy for

Manual Valve Gland Flange IGSCC-related Issues; Revision 0

- AR 501000018720; Re-Evaluate SI-15-9 Gland Follower EOC; 10/17/2018

- EC Number: 27070; Two-Piece Gland Follower (XH-1-84-1); Revision 0

- EC Number: 0000027166; Rockwell Edward 3/4 Model #3624F316J Two-Piece Gland

Follower; Revision 000

- EC Number: 27167; Two-Piece Gland Follower (XH-1-82-1, Alternate Follower Detail);

Revision 0

- EC Number: 27408; Valve Variable Spacer Generic Modification; Revision 0

- AR 501000020830; Roll-Up for Secondary Level Controllers; 12/07/2018

71111.13Maintenance Risk Assessment and Emergent Work

- AR 501000020904; Active Jacket Water Leak on 12 DDCLP; 12/10/2018

71111.15Operability Evaluations

- AR 501000016536; Unacceptable Void Found in 2RH-01; 09/15/2018

- AR 501000017940; EEQFlood Level Elevation Incorrect; 10/02/2018

- AR 501000019966; GAMP: 12 RHR Discharge Void Locations; 11/14/2018

- AR 501000020578; RWST Leaking into Sump B; 12/02/2018

- AR 501000020995; EEQ Cable Non-ComplianceX2 Compartment; 12/12/2018

- AR 501000020132; D6 E2 LO Press Switch Leak, 2PSL-6673; 11/19/2018

71111.18Plant Modifications

- EC 25124; D1 Breaker 1502 NFPA 805 Modification

71111.19Post Maintenance Testing

- PM 3001-2-D1; D1 Diesel Generator Inspection (034-011); Revision 38

- WO 700045998; Troubleshoot and Repair 1TM-401L; 11/13/2018

- SP 1003; Analog Protection Functional Test; Revision 78

71111.20-Refueling Outage

- 1R31 Prairie Island Refueling Outage September 2018 Shutdown Safety Assessment

- 1C1.3-M3; Unit 1 Shutdown to Mode 3; Revision 2

- 1C1.3-M2; Unit 1 Shutdown to Mode 2; Revision 2

- SP 1036; Turbine Overspeed Trip Exercise; Revision 32

- 1C1.2-M1; Unit 1 Startup to Mode 1; Revision 9

- C1-B; Unit Startup Checklist; Revision 23

- C1.M2; Surveillance RequirementsMode 2, Startup; Revision 18

71111.22Surveillance Test

- SP 1072.29B; Local Leakage Rate Test of Penetration 29B (Containment Spray); Revision 31

- AR 501000018753; CV-31019 + CV-31092 Closed in SP-10838; 10/17/2018

- NE-40009-172; (FP-R-LIC-06 Pertaining to QIM 501000018657; 10/22/2018

- NF-86186-3; Interlock Logic DiagramsContainment and Auxiliary Building Chilled Water

System

- WO 700044590; SV-37460 Did Not Vent Properly (No Date)

- WO 700044590-0030; SV-37460, PMT/RTS; 10/18/2018

- AR 501000018658; SP-1083A Table 20-D1 Data Point OOT; 10/15/2018

- SP 1083A; Unit 1 Integrated SI Test With a Simulated Loss of Offsite Power Train A;

Revision 10

- SP 2015; 4kV Bus 21/22 Undervoltage and Under Frequency Relay Test; Revision 33

- NF-40524-3; 4.16 kV Bus 22 Undervoltage Relay Test Point Cabinets (No Date)

- NF-40524-1; Wiring Diagram 4.16 kV SWGR Normal Relay Cabinet (No Date)

- NF-40524-2; Wiring Diagram 4.16 kV SWGR Normal Transducer CA6 (No Date)

- NE-40405-Sheet 3; Revision 77

- NE-40405-Sheet 18; Revision L

- NF-40002-1; Single Line-Metering and Relaying 1 and 2 Generator and Normal Incoming

4.16kV Switchgear Unit 1 and 2 (No Date)

- XH-1001-1407; Prairie Island Nuclear Generating Plant No. 2 Reactor Protection System;

08/22/1990

- WO 700036282; SP 2090B 22 Containment Spray Pump; 11/21/2018

- SP 2090B; 22 Containment Spray Pump Quarterly Test; Revision 27

71114.04Emergency Action Level and Emergency Plan Changes

- Emergency Plan; Revision 55

- F3-2.1; Emergency Action Level Technical Bases; Revision 14

- PI-2017-584; 10 CFR 50.54(q) Review Form; 11/03/2017

- PI-2018-594; 10 CFR 50.54(q) Review Form; 03/19/2018

- PI-2018-600; 10 CFR 50.54(q) Review Form; 03/21/2018

- PI-2018-601; 10 CFR 50.54(q) Review Form; 05/16/2018

- PI-2018-602; 10 CFR 50.54(q) Review Form; 05/15/2018

- PI-2018-609; 10 CFR 50.54(q) Review Form; 05/23/2018

- AR 501000007938; NOS Finding: 50.54(q) Evil of EP EAL Chg; 04/06/2018

- AR 501000012092; Rev.6 EAL Bases Change Recommended; 07/13/2018

71124.01Radiological Hazard Assessment and Exposure Controls

- SnapShot Report; AR Number 607000000190; RP Program Readiness Review for NRC

Inspection; 07/17/2018 through 07/25/2018

- Radiation Work Permit and Associated ALARA Files; RWP 181031; 1R31-Sump C Work;

Revision 00

- Radiation Work Permit and Associated ALARA Files; RWP 181013; 1R31-Residual Heat

Removal Pit Work; Revision 01

- Radiation Work Permit and Associated ALARA Files; RWP 181040; 1R31-Refuel Work;

Revision 00

- Radiation Work Permit and Associated ALARA Files; RWP 181042; 1R31-Reactor (RX) Head

Disassembly / Reassembly Work; Revision 00

- Radiation Work Permit and Associated ALARA Files; RWP 181070; 1R31-11 & 12 Steam

Generator (SG) Secondary Side Work; Revision 00

- Radiation Work Permit and Associated ALARA Files; RWP 181071; 1R31-11 & 12 Steam

Generator (SG) Primary Side Work; Revision 00

- AR 501000018036; RP to Review the Adequacy of the Equipment Hatch Shield Blocks Free

Release Policy; 10/04/2018

- AR 501000018054; Monitoring the Equipment Hatch Opening Observations; 10/04/2018

- AR 501000007328; Apparent Cause Evaluation; Poor HRA Rad Worker Practice Trend;

03/12/2018

- AR 501000007162; Pre-job Brief Delta; 01/11/18

- AR 501000017776; RP Staffing for Outages Gets Less and Less; 09/29/2018

- AR 501000017871; 1R31 I-131Quantified in Air Samples; 10/01/2018

- Alpha Characterization Study; 08/17/18

- Radioactive Source Inventory/Leak Check; 08/21/2018

- Technical Document 17-003; Ni-63 Detection Capability of the Protean WPC-9550-FC for

Source Leakage Tests; Revision 1

- Radiation Surveys Unit 1 Containment; 10/1/2018 through 10/04/2018

- Radiological Air Samples Unit 1 Containment; 1R31 Outage (No Date)

- Electronic Dosimeter Alarm Logs; Various Records (No Date)

- National Source Tracking System Annual Reconciliation; 01/2018

- Personnel Contamination Monitor Alarm Setpoint Information; Current Data (No Date)

- RPIP 1302; Unconditional Release of Materials; Revision 30

- SSA 606000000562; 2018 Prairie Island Isotopic Mix Evaluation (No Date)

71124.02Occupational As Low As Reasonably Achievable Planning and Controls

- Radiation Work Permit and Associated ALARA Files; RWP 181031; 1R31-Sump C Work;

Revision 00

- Radiation Work Permit and Associated ALARA Files; RWP 181013; 1R31-Residual Heat

Removal Pit Work; Revision 01

- Radiation Work Permit and Associated ALARA Files; RWP 181040; 1R31-Refuel Work;

Revision 00

- Radiation Work Permit and Associated ALARA Files; RWP 181042; 1R31-Reactor (RX) Head

Disassembly / Reassembly Work; Revision 00

- Radiation Work Permit and Associated ALARA Files; RWP 181070; 1R31-11 & 12 Steam

Generator (SG) Secondary Side Work; Revision 00

- Radiation Work Permit and Associated ALARA Files; RWP 181071; 1R31-11 & 12 Steam

Generator (SG) Primary Side Work; Revision 00

71151Performance Indicator Verification

- Prairie Island MSPI Basis Document; Revision 25

- Units 1 & 2 MSPI Margin Reports; 09/2018

- MSPI Tracking Table; 11/2018

- H33.2; Mitigating Systems Performance Index (MSPI) Reporting Instructions; Revision 10

- FP-PA-PI-02; NRC/INPO/WANO Performance Indicator Reporting; Revision 14

71152Problem Identification and Resolution

- AR 501000015715; GAMP: SP 2082A Void Tracking; 08/16/2018

- AR 501000020043; GAMP: SP 1468.1 Trend RHR Suction; 11/15/2018

- AR 501000016523; 12 DDCLP Low Jacket Water Temperature; 09/06/2018

- AR 501000016583; Thermocouple Leads Appear to be Swapped; 09/06/2018

- AR 501000016757; Thermocouple Wire for 16280 Broken; 09/06/2018

- AR 501000019523; 12 and 22 DDCLP Trend; 11/12/2018

19