Advises That re-evaluation of Mod Project for Rms Necessary to Ensure Best Approach Adopted Which Has Impacted Existing Schedule,Per Insp Repts 50-272/89-10 & 50-311/89-09 & LERs & Special Repts
ML18095A744
Person / Time
Site: Salem  PSEG icon.png
Issue date: 02/12/1991
From: Crimmins T
Public Service Enterprise Group
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NLR-N90209, NUDOCS 9102190137
Download: ML18095A744 (2)


Text

' '-* * *" Public Service Electric and Gas Company * Thomas M. Crimmins, Jr. Public Service Electric and Gas Company P.O. Box 236, Hancocks Bridge, NJ 08038 609-339-4700 Vice President-Nuclear Engineering FEB 1 2 1991 NLR-N90209 United States Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Gentlemen:

REVISION TO COMMITMENTS REGARDING RADIATION MONITORING SYSTEM MODIFICATIONS SALEM GENERATING STATION UNIT NOS. 1 AND 2 DOCKET NOS. 50-272 AND 50-311 PSE&G is revising its implementation schedule and commitments to modification projects for the Radiation Monitoring System (RMS) as stated in Inspection Report 50-272/89-10; 50-311/89-09, noted LERs and Special Reports. As a result of additional review and evaluati9n of the material condition of the existing Unit 2 and Unit 1 RMS, the required scope to resolve current equipment defects and future problems with aging obsolete components is much larger than originally envisione Therefore a re-evaluation of the project was considered necessary to ensure the best approach will be adopted which has impacted the existing schedul The commitment to install voltage regulators to prevent channel spiking can not be implemented as originally schedule Additionally, the original project commitment has been modified from replacing the existing non-regulated power supplies with voltage regulators to installation of an Uninterruptible Power Source (UPS). The corrective action commitment to replace the RMS Central Processing Unit (CPU) and those monitoring systems that actuate ESFs is being re-evaluated and therefore the original schedule for these long-term projects will not be met. Alternatives have been developed that will provide acceptable resolution of RMS and power supply problems and better utilize available resource Evaluation of the RMS project upgrade alternatives was completed in December, 1990. Upon completion of the RMS upgrade project review the appropriate approach will be approve PSE&G will notify the .NRC of the 1 final decision, project scope and implementation schedule by the end of March, 1991. r-910219(>137 91(12T2 . ' PDR ADOCK 05000272 * G! F'DR /}OtJ I '/tJ

. * Document Control Desk NLR-N90209 2 * FEB 1 2. ,991 Should you have any questions on this issue, please do not hesitate to contact us. C Mr. J. c. Stone Licensing Project Manager Mr. T. Johnson Senior Resident Inspector

Sincerely, Mr. T. Martin, Administrator Region I Mr. Kent Tosch, Chief New Jersey Department of Environmental Protection Division of Environmental Quality Bureau of Nuclear Engineering CN 415 Trenton, NJ 08625