IR 05000254/1985001

From kanterella
Jump to navigation Jump to search
Errata to SALP Repts 50-254/85-01 & 50-265/85-01 for June 1984 - Sept 1985,correcting Typos Per 860110 Meeting
ML20138B749
Person / Time
Site: Quad Cities  Constellation icon.png
Issue date: 09/30/1985
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML20138B738 List:
References
50-254-85-01, 50-254-85-1, 50-265-85-01, 50-265-85-1, NUDOCS 8603250148
Download: ML20138B749 (8)


Text

. . .. . . . . _

'

.

i SALP 5 APPENDIX

,

i SALP BOARD REPORT

!

J

U.S. NUCLEAR REGULATORY COMISSION i REGION III

,

l

)

'

SYSTEMATIC ASSESSMENT OF LICENSEE PERFORMANCE 50-254/85001; 50-265/85001

Inspection Report

Commonwealth Edison Company Name of Licensee i

Quad Cities Nuclear Power Station l Name of Facility

June 1, 1984 through September 30, 1985 Assessment Period i

i D E

a t

- _ _________________

-

.

Quad Cities Nuclear Plant Meeting Summary The findings and conclusions of the SALP Board are documented in Reports No. 50-254/85001, and No. 50-265/85001. They were discussed with the licensee on January 10, 1986, at the Region III office in Glen Ellyn, Illinois. The licensee's regulatory performance was presented in each functional area. Overall performance and performance in each functional area was found to be acceptable. The performance rating improved in the area of Plant Operations. While the performance rating in the area of Surveillance and Inservice Testing declined based on the number and nature of the violations identified, there was not a declining trend noted. The licensee continues to have a high level of performance in the areas of Radiation Protection, Emergency Preparedness, Security, Refueling, and Licensing activitie While this meeting was primarily a discussion between the licensee and the NRC, it was open to members of the public as observer The following licensee and NRC personnel were in attendance on January 10, 198 Commonwealth Edison Company B. J. Thomas, Executive Vice President Cc,rdell Reed, Vice President of Nuclear Operations N. Wandke, Assistant Vice President D. Galle, Division Vice President and General Manager of Nuclear Stations D. Farrar, Director of Nuclear Licensing B. Stephenson, Manager of Production W. Worden, BWR Operations Manager N. Kalivianakis, Plant Manager, Quad Cities D. Scott, Plant Manager, Dresden G. Plim1, Plant Manager, Zion L. Gerner, Superintendent, Regulatory Assurance J. Bitel, Operations QA Manager W. Shewski, Manager Quality Assurance P. LeBlond, Licensing Administrator, Zion M. Turbak, Operating Plant Licensing Director C. Schultz, Assistant Technical Staff Supervisor, Zion M. Kooi, Compliance Coordinator, Quad Cities F. Palmer, Manager, Nuclear Safety S. Trubatch, Legal Department J. Wojnarowski, Licensing Administrator, Dresden and Quad Cities Milwaukee Sentinel Q. Dadisman, Reporter U.S. Nuclear Regulatory Commission J. G. Keppler, Regional Administrator

_ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ - _ _ _ - _ _ ___-__ __ ___ - _ - - _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _

_ _ _ . _ . . _

.

i A. B. Davis, Deputy Regional Administrator C. E. Norelius, Director, Division of Reactor Projects J. A. Hind, Director, Division of Radiation Safety and Safeguards N. J. Chrissotimos, Chief, Reactor Projects Branch 2

W. D. Shafer, Chief, Emergetcy Preparedness and Radiological Protection Branch

,

G. C. Wright, Chief, Reactor Projects Section 2C D. C. Boyd, Chief, Reactor frojects Section 2A A. D. Mcrrongiello, Resident Inspector, Quad Cities A. L. Madison, Senior Resident Inspector, Quad Cities

J. N. Kish, Resident Inspector, Zion L. E. Kanter, Resident Inspector, Zion

E. A. Hare, Resident Inspector Dresden l T. Tongue, Senior Resident Inspector, Braidwood S. Stasek, Resident Inspector, Dresden L. G. McGregor, Senior Resident Inspector, Dresden R. Lickus, State Liaison Officer R. W. Defayette, Project Manager, Section 2D R. B. Landsman, Project Manager, Section 2C NRC Headquarters

]

S. Varga, Director, PWR Project Directorate No. 3 J. Norris, NRR Project Manager, lion R. Bevan, NRR Project Manager, Quad Cities R. Gilbert, NRR Project Manager, Dresden i

i f

i j

j

!

i

[

'

l T

l l

_ _ _ . _ _ - - _ - - - - _ _ _ _ _ _ _ _ _ _ _ _

. _ _ . _ - _ _ . . . _ _ .- . _ . _

,

'

.

e ERRATA SHEET i

l i

j Facility: Quad Cities Station

} SALP Report No: 50-254/85001; 50-265/85001

1

1 i Page Line Now Reads should Read

1 15 26-27 outage for the work to be outage, j performed.

! Basis for Change: The words "for the work to be performed" were inadvertently added during final typin They were not intended to be l ther Table 1 five table numbers were see errata sheet

,

incorrect Basis for

! Change: Five numbers were inadvertently typed wrong.

I

.

!

!

!

!

l i

I I

i i

i i

1 l I

!

i

.

.

adequately stated and generally understood. The licensee's actions in response to NRC initiatives indicated they understood the issues and their reviews were generally timely, thorough, with technically sound conservative solution Records and calculations were found to be generally complete, well maintained, and available. The records also indicate that equipment and material certifications were current a d complete, and personnel were properly trained and certifie le approach used to evaluate and analyze piping systems and s orts was generally conservative, technically sound, and rough. Audits were generally complete, timely, and thcrough. ]bservations indicate personnel have an adequate understa ng of work practices and that procedures were adhered . Discussions with personnel indicated they were knowledgeab in their jo As with all plants, the licensee wa r uired to complete environmental qualifications by N er 30, 1985. The licensee aggressively worked to ete Environmental Qualification Modifications on ired equipment. Several small planned outages were ac ished in order to comply with the dead line. All work was formed in a thorough and professional manner and m ment maintained effective control throughout the proces As noted earlier, U conducted a major maintenance and refueling outage at beginning of the refueling outage for the work to be p f ed. There was evidence of prior planning and daily mana meetings were conducted to ensure proper priorization esolution of issues. Maintenance activities generally were ceptable. However, the resident inspectors identified s ral concerns with modification which led to the special ins ction and violation discussed earlie )

Unit 2 o underwent a major maintenance and refueling outage l durin he assessment perica. There was consistent evidence of prio planning and assignment of priorities. As with Unit 1, dai management meetings were held to ensure that activities w e properly controlled and to ensure timely resciution to all I technical issues. Adequate staffing levels were maintained to i minimize the amount of overtime required. Contrary to Unit 1, maintenance activities were well controlled and no modification 4 concerns were identified indicating the licensee learned from j the experience and improved its performance. The quality of I work performed is evidenced by the smooth return to operation

'

(ahead of schedule) and the continued uninterrupted operation of Unit 2 throughout the remainder of the assessment perio ,

.

.

adequately stated and generally understood. The licensee's actions in response to NRC initiatives indicated they understood the issues and their reviews were generally timely, thorough, with technically sound conservative solution Records and calculations were found to be generally complete, well maintained, and available. The records also indicate that equipment and material certifications were current and complete, and personnel were properly trained and certifie The approach used to evaluate and analyze piping systems and supports was generally conservative, technically sound, and thorough. Audits were generally complete, timely, and thorough. Observations indicate personnel have an adequate understanding of work practices and that procedures were adhered to. Discussions with personnel indicated they were knowledgeable in their jo As with all plants, the licensee was required to complete environmental qualifications by November 30, 1985. The licensee aggressively worked to complete Environmental Qualification Modifications on required equipment. Several small planned outages were accomplished in order to comply with the dead lin All work was performed in a thorough and professional manner and management maintained effective control throughout the proces As noted earlier, Unit 1 conducted a major maintenance and refueling outage at the beginning of the refueling outag There was evidence of prior planning and daily management meetings were conducted to ensure proper priorization and resolution of issues. Maintenance activities generally were acceptabl However, the resident inspectors identified several concerns with modification which led to the special inspection and violation discussed earlie Unit 2 also underwent a major maintenance and refueling outage during the asse . ment period. There was consistent evidence of prior planning and assignment of priorities. As with Unit 1, daily management meetings were held to ensure that activities were properly coat. rolled and to ensure timely resolution to all technical issues. Adequate staffing levels were' maintained to minimize the amount of overtime required. Contrary to Unit 1, maintenance activities were well controlled and no modification concerns were identified indicating the licensee learned from the experience and improved its performance. The quality of work performed is evidenced by the smooth return to operation (ahead of schedule) and the continued uninterrupted operation of Unit 2 throughout the remainder of the assessment perio !

,

'

15 l

l

\

.

. .

, Inspection Activities An Operational Team Inspection was conducted by Region III on September 24-28, 1984 to assess overall licensee performance and provide an indepth assessment of selected areas including operations. The inspectors found the operations staff to be an effective operating organizatio FEMA issued a report addressing the emergency exercise, which concluded that an adequate level of offsite radiologi prepared-ness had been demonstrated to protect the public in e event of a radiological accident at the Quad Cities Nuclear P. er Statio Violation data for Quad Cities is presented ir ble I which includes inspection reports 84008 through 85 for Unit 1 and 84007 through 85029 for Unit TABLE 1 i

INSPECTION ACTIVITY A ORCEMENT

-

No. o V lations in Each Severity Level Functional 1 Unit 2 Site Areas IV V III IV V III IV V T/

A. Plant Operations 1 1 1 1 B. Radiological Controls 1 1 1 1 1 C. Maintenance /Modificati 1 1 2 D. Surveillance and Inservice Test g 1 1 1 4 1 4 E. Fire Protectio 1 1 1 F. Emergency eparedness 1 1 1 G. Securit 1 1 1 H. Refueling I. Quality Programs and Administrative Controls 1 2 1 2 1 2 J. Licensing Activities _ _ _ _ _ _ _ _ _

TOTALS 2 3 6 1 6 10 2 6 10

.-

[I ..

.

B. Inspection Activities An Operational Team Inspection was. conducted by Region III on September 24-28, 1984 to asses's overall licensee performance and provide an indepth assessment of selected areas including operations. The inspectors found the operations staff to be an effective operating organizatio i FEMA issued a report addressing the emergency exercise, which concluded that an adequate level of offsite radiological prepared-ness had been demonstrated to protect the public in the event of a t radiological accident at the Quad Cities Nuclear Power Statio ,

l Violation data for Quad Cities is presented in Table 1 which !

includes inspection reports 84008 through 85026 for Unit 1 and 84007 through 85029 for Unit ,

TABLE 1 INSPECTION ACTIVITY AND ENFORCEMENT No. of Violations in Each Severity Level Functional Unit 1 Unit 2 Site Areas III IV V III IV V III IV V A. Plant Operations 1 1 1 1 1 1 j B. Radiological Controls 1 1 1 1 1 C. Maintenance / Modifications 1 1 1 (

!

D. Surveillance and .

Inservice Testing 1 1 2 4 2 4 E. Fire Protection 1 1 1 l

F. Emergency Preparedness 1 1 1 [

l G. Security 1 1 1 !

H. Refueling I. Quality Programs and i Administrative Controls 1 2 1 2 1 2 J. Licensing Activities _ _ _ _ _ _ _ _ _ [

TOTALS 2 3 6 1 5 10 2 6 10 ,

i

!

33 [

!

-

?