IR 05000247/2019012

From kanterella
Jump to navigation Jump to search
Temporary Instruction 2515/194 Inspection Report 05000247/2019012 and 05000286/2019012
ML20010D444
Person / Time
Site: Indian Point  Entergy icon.png
Issue date: 01/09/2020
From: Glenn Dentel
Engineering Region 1 Branch 2
To: Vitale A
Entergy Nuclear Operations
Dentel G
References
IR 2019012
Download: ML20010D444 (9)


Text

ary 9, 2020

SUBJECT:

INDIAN POINT NUCLEAR GENERATING, UNITS 2 AND 3 - TEMPORARY INSTRUCTION 2515/194 INSPECTION REPORT 05000247/2019012 AND 05000286/2019012

Dear Mr. Vitale:

On December 19, 2019, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Indian Point Nuclear Generating, Units 2 and 3 and discussed the results of this inspection with Mr. Richard Drake, Acting Design and Programs Engineer Manager and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Glenn T. Dentel, Chief Engineering Branch 2 Division of Reactor Safety Docket Nos. 05000247 and 05000286 License Nos. DPR-26 and DPR-64

Enclosure:

As stated

Inspection Report

Docket Numbers: 05000247 and 05000286 License Numbers: DPR-26 and DPR-64 Report Numbers: 05000247/2019012 and 05000286/2019012 Enterprise Identifier: I-2019-012-0035 Licensee: Entergy Nuclear Operations, Inc.

Facility: Indian Point Nuclear Generating, Units 2 and 3 Location: Buchanan, NY Inspection Dates: December 16, 2019 to December 19, 2019 Inspectors: C. Hobbs, Reactor Inspector A. Patel, Senior Reactor Inspector Approved By: Glenn T. Dentel, Chief Engineering Branch 2 Division of Reactor Safety Enclosure

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a Temporary Instruction inspection at Indian Point Nuclear Generating, Units 2 and 3, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations No findings or violations of more than minor significance were identified.

Additional Tracking Items None.

INSPECTION SCOPES

The inspection was conducted using Temporary Instruction 2515/194 (ADAMS Accession No. ML17137A416), effective November 1, 2017. The inspectors reviewed Entergys implementation of the Nuclear Energy Institutes voluntary industry initiative in compliance with Commission guidance. The inspectors discussed Entergys open phase condition system design and ongoing implementation plans with plant staff. The inspectors reviewed Entergy and vendor documentation, and performed system walkdowns to verify that the installed equipment was supported by the design documentation. Entergy had recently completed physical installation and the equipment was being operated in a monitoring mode with the trip functions enabled.

OTHER ACTIVITIES

- TEMPORARY INSTRUCTIONS, INFREQUENT AND ABNORMAL 2515/194 - Inspection of the Licensees Implementation of Industry Initiative Associated With the Open Phase Condition Design Vulnerabilities In Electric Power Systems (NRC Bulletin 2012-01)

The inspectors reviewed the licensees implementation of the Nuclear Energy Institute Voluntary Industry Initiative, (ADAMS Accession No. ML15075A454) dated March 16, 2015. This included reviewing how the licensee updated their licensing basis to reflect the need to protect against open phase conditions.

Inspection of the Licensees Implementation of Industry Initiative Associated With the Open Phase Condition Design Vulnerabilities In Electric Power Systems (NRC Bulletin 2012-01)

(1 Sample)

(1) Entergy Operations Inc. selected the open phase detection system designed and manufactured by PCS2000 Solutions, LLC, as the design vendor for the open phase condition system at Indian Point Nuclear Generating. The onsite and offsite electrical distribution system is functionally the same for both Indian Point Unit 2 and Unit 3.

Two general design criteria (GDC-17) offsite power sources are credited for each unit.

The normal offsite power source is a 138 kV feeder from the Buchanan switchyard that supplies a station auxiliary transformer (SAT) which in turn feeds two 6.9 kV buses in the onsite electrical distribution. If the normal source of offsite power is lost, the two 6.9 kV buses can be manually connected to the alternate offsite power source which is the gas turbine autotransformer (GTA). The GTA is fed by a 13.8 kV feeder from a different section of the Buchanan switchyard. The 6.9 kV buses then feed the four safety-related 480 V engineered safeguards (ESF) buses through station service transformers (SSTs).

During normal operation with the reactor at power, the SAT will feed 6.9 kV buses 5 and 6. These (6.9 kV buses 5 and 6) will then feed 480 V ESF buses 5A and 6A through SSTs 5 and 6. If 138 kV offsite power is lost, or if a lockout of the SAT occurs due to an electrical fault such as an open phase condition, power will be lost to 6.9 kV buses 5 and 6 as well as as 480 V bus 5A and 6A temporarily. Each 480 V ESF is supplied by an emergency diesel generator and the respective emergency diesel generator for 480 V bus 5A and 6A will start and supply power to its respective bus. Operators can then manually shift power from the SAT to the GTA and supply 13.8 kV offsite power to 6.9 kV buses 5 and 6, thus restoring offsite power to the buses. Once offsite power has been restored to 6.9 kV buses 5 and 6, the emergency diesel generator supplying power to the respective 480 V bus may be secured. Throughout the loss of offsite power, 6.9 kV buses 1 through 4 will continue to supply power to 480 V ESF buses 2A and 3A. Power to 6.9 kV buses 1 through 4 are supplied from the main generator through the unit auxiliary transformer while the reactor is at power. These buses also supply power to all four reactor coolant pumps, therefore, a loss of offsite power by itself does not result in a reactor and turbine trip.

In the event of a reactor and turbine trip, 6.9 kV buses 1 through 4 will fast transfer to 6.9 kV buses 5 and 6 so that power will be supplied to all six 6.9 kV buses from offsite power, thus continuity of power is retained. This same configuration is used during a refueling outage when the reactor is offline.

Indian Point has installed redundant open phase detection systems on each offsite power transformer for each unit. For a single offsite power transformer, there are duplicate current sensors installed on each phase on the line side of the transformer bushings, as well as duplicate electronic relay cabinets. Coincidence logic is utilized for the electronic relays to prevent spurious trips of the system. At the end of this inspection, the PCS2000 system was operating with all functions enabled for each SAT and GTA.

INSPECTION RESULTS

Voluntary Industry Initiative (Part 1) 2515/194 Based on discussions with licensee staff; review of design, installation, and testing documentation; and walkdowns of installed equipment; the inspectors had reasonable assurance the licensee is appropriately implementing the voluntary industry initiative. No exceptions were noted. The inspectors verified by design document review, walkdowns, staff discussions, and observation the following criteria:

Detection, Alarms, and General Criteria

(1) Open phase conditions will be detected and alarmed in the both the Unit 2 and Unit 3 control rooms.
(2) Detection circuits are sensitive enough to identify an open phase condition for all credited loading conditions.
(3) The PCS2000 system is designed to minimize misoperation or spurious action in the range of voltage unbalance normally expected in the transmission system that could cause separation from an operable offsite power source. The licensee has demonstrated that the actuation circuit design did not result in lower overall plant operation reliability.
(4) No Class-1E circuits were replaced with non-Class 1E circuits in the design.
(5) The licensee had updated the Unit 2 and Unit 3 Final Safety Analysis Reports to discuss the design features and analyses related to the effects of, and protection for, any open phase condition vulnerabilities.

Protective Actions Criteria

(1) The SATs and the GTAs at both Unit 2 and Unit 3 were identified as susceptible to an open phase condition and the licensee has implemented design changes to mitigate the effects.
(2) With an open phase condition present, and no accident condition signal present, the PCS2000 system would not adversely affect the function of important-to-safety systems, structures, or components. The PCS2000 open phase condition design solution added a set of additional tripping inputs in parallel with existing transformer isolation controls. This addition added a new tripping condition (open phase) to the previously analyzed electrical faults, which result in isolation of the offsite power transformer. The credited plant response was unaffected and would be the same independent of the conditions that would generate electrical isolation of the offsite power transformer.
(3) With an open phase condition present, and an accident condition signal present, the PCS2000 system would not adversely affect the transfer of 480 V ESF buses to the onsite emergency diesel generators as required by the current licensing bases. Only a new tripping condition (open phase) was added to the electrical faults which result in isolation of the offsite source of power.
(4) Periodic tests, calibrations, and setpoint verifications have been established for the open phase detection system for both Unit 2 and Unit 3.

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On December 19, 2019, the inspectors presented the Temporary Instruction results to Mr. Richard Drake, Acting Design and Programs Engineer Manager and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection Type Designation Description or Title Revision or

Procedure Date

2515/194 Calculations IP-CALC-15- Open Phase Detection Time Delay Trip Setting for Unit 2 0

00103

IPC-CALC-16- Open Phase Detection Time Delay Trip Setting for Unit 3 0

00023

Corrective Action Condition Reports CR-HQN-2018-02169, CR-IP3-2017-03153, CR-IP2-2018-

Documents 03631, CR-IP3-2018-02862, CR-IP3-2018-02656, CR-IP2-

2019-04438, CR-IP2-2019-04439, CR-IP3-2019-03728, CR-

IP3-2019-04217, CR-IP3-2019-03496, CR-IP3-2019-03727

Drawings 504277 Indian Point Unit 2 Station Aux Transformer OPD Systems 1 0

& 2 Trip and Alarm Schematic Diagram

504288 Indian Point Unit 2 GT1 Autotransformer OPD Systems 1 & 2 0

Trip and Alarm Schematic Diagram

504379 Indian Point Unit 3 Station Aux Transformer OPD Systems 1 0

& 2 Trip and Alarm Schematic Diagram

504391 Indian Point Unit 3 GT1 Autotransformer OPD Systems 1 & 0

Trip and Alarm Schematic Diagram

617F645 Indian Point Unit 3 Main One Line Diagram 24

908 Indian Point & Buchanan System Ties 46

21-LL-3132-15 Schematic Diagram Pilot Wire and Misc. Lockout Relays, 15

Sheet 3

A208377-21 Indian Point Unit 2 Main One Line Diagram 21

Engineering EC-52526 Open Phase Detection on Unit 2 Station Aux Transformer 0

Changes and GT Autotransformer

EC-52527 Open Phase Detection on Unit 3 Station Aux Transformer 0

and GT Autotransformer

Miscellaneous Maintenance Rule IPEC Maintenance Rule Basis Document for 13.8 kVAC 3

Electrical System

Maintenance Rule IPEC Maintenance Rule Basis Document for 138 kVAC 4

Electrical System

UFSAR Indian Point Unit 2 UFSAR 26

UFSAR Indian Point Unit 3 UFSAR 7

Work Orders 00433527, 00433529

Inspection Type Designation Description or Title Revision or

Procedure Date

Procedures 2-ARP-SCF ARP - Condensate and Boiler Feed 54

2-ARP-SHF ARP - CCR Electrical 32

3-ARP-010 ARP - 13.8 KV Substation Trouble 36

3-ARP-011 ARP - Station Aux XFMR Trouble 38

Self-Assessments LO-IP3LO-2019- NRC Inspection of Implementation of Open Phase Detection 10/29/2019

00121 Modifications

7