| Quarter | Site | Title |
---|
05000298/FIN-2018003-01 | 2018Q3 | Cooper | Failure to Provide Complete and Accurate Information in a License Amendment Request |
05000382/FIN-2013005-02 | 2013Q4 | Waterford | Protective Action Recommendations Under Conditions of Changing Wind Vectors Not Consistent with Federal Guidance |
05000285/FIN-2013019-01 | 2013Q4 | Fort Calhoun | Failure to Correct Deficiencies in Operations Support Center Functions |
05000382/FIN-2013005-01 | 2013Q4 | Waterford | Failure to Critique Weaknesses During an Evaluated Exercise |
05000528/FIN-2013002-02 | 2013Q1 | Palo Verde | Failure to identify weak performance during an exercise |
05000336/FIN-2012503-01 | 2012Q4 | Millstone | Failure to Adequately lmplement Fuel Clad Barrier EALs |
05000313/FIN-2013503-01 | 2012Q4 | Arkansas Nuclear | Senior emergency planner falsely submitted documents that showed a postaccident sampling system drill and an environmental monitoring drill were conducted. |
05000298/FIN-2012004-09 | 2012Q3 | Cooper | Failure to Correct Exercise Performance Deficiencies |
05000443/FIN-2012503-01 | 2012Q2 | Seabrook | Failure of Exercise Critique to ldentify an RSPS Weakness as a DEP Pl Opportunity Failure |
05000445/FIN-2011005-03 | 2011Q4 | Comanche Peak | Failure to Provide Guidelines for Protective Action Recommendations Outside the Emergency Planning Zone |