ENS 52534
From kanterella
Jump to navigation
Jump to search
ENS Event | |
---|---|
20:45 Feb 3, 2017 | |
Title | Unit 1 Manual Reactor Trip Due to Loop 1 Msiv Starting to Fail Closed |
Event Description | At 1545 EST on 2/3/17, Vogtle Unit 1 was manually tripped from 100% power when loop 1 Main Steam Isolation Valve (MSIV) started to fail closed. Non-Safety Related 4160V bus 1NA01 failed to transfer to alternate incoming power supply automatically and was successfully manually energized.
All control rods fully inserted and AFW [Auxiliary Feedwater] and FWI [Feedwater Isolation] actuated as expected. Unit 1 is in Mode 3 and stable with decay heat being removed by AFW. The licensee informed the NRC Resident Inspector. |
Where | |
---|---|
Vogtle Georgia (NRC Region 2) | |
Reporting | |
10 CFR 50.72(b)(2)(iv)(B), RPS Actuation 10 CFR 50.72(b)(3)(iv)(A), System Actuation | |
Time - Person (Reporting Time:+-1.82 h-0.0758 days <br />-0.0108 weeks <br />-0.00249 months <br />) | |
Opened: | Matthew Norris 18:56 Feb 3, 2017 |
NRC Officer: | Steve Sandin |
Last Updated: | Feb 3, 2017 |
52534 - NRC Website | |
Unit 1 | |
---|---|
Reactor critical | Critical |
Scram | Yes, Manual Scram |
Before | Power Operation (100 %) |
After | Hot Standby (0 %) |
Vogtle with 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation | |
WEEKMONTHYEARENS 566322023-07-21T15:48:00021 July 2023 15:48:00
[Table view]10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation Automatic Reactor Trip ENS 566142023-07-09T17:28:0009 July 2023 17:28:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation Automatic Reactor Trip ENS 564972023-05-02T08:23:0002 May 2023 08:23:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation Manual Reactor Trip ENS 564602023-04-10T04:48:00010 April 2023 04:48:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation Automatic Reactor Trip ENS 564142023-03-16T01:57:00016 March 2023 01:57:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation Automatic Reactor Trip ENS 563112023-01-14T12:21:00014 January 2023 12:21:00 10 CFR 50.72(b)(3)(iv)(A), System Actuation Manual Actuation of Reactor Protection System (RPS) ENS 562942023-01-04T03:59:0004 January 2023 03:59:00 10 CFR 50.72(b)(3)(iv)(A), System Actuation Loss of Offsite Power Source ENS 561472022-10-06T06:44:0006 October 2022 06:44:00 10 CFR 50.72(b)(3)(iv)(A), System Actuation Automatic Actuation of Reactor Protection System (RPS) ENS 558752022-05-03T19:41:0003 May 2022 19:41:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Manual Reactor Trip and Automatic Actuation of Auxiliary Feedwater System ENS 549952020-11-12T22:32:00012 November 2020 22:32:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation Automatic Reactor Trip Due to Turbine Trip ENS 545962020-03-21T20:44:00021 March 2020 20:44:00 10 CFR 50.72(b)(3)(iv)(A), System Actuation Automatic Actuation of the 1B Emergency Diesel Generator ENS 543182019-10-09T14:23:0009 October 2019 14:23:00 10 CFR 50.72(b)(3)(iv)(A), System Actuation Automatic Start of Emergency Diesel Generator and Auxilliary Feedwater System ENS 541752019-07-19T13:45:00019 July 2019 13:45:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Automatic Reactor Trip Due to Main Steam Isolation Valve Failing Shut ENS 539672019-03-31T01:30:00031 March 2019 01:30:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Manual Reactor Trip Due to Msiv Failing Closed ENS 536432018-10-04T04:00:0004 October 2018 04:00:00 10 CFR 50.72(b)(3)(iv)(A), System Actuation En Revision Imported Date 10/22/2018 ENS 534842018-07-03T04:00:0003 July 2018 04:00:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Manual Reactor Trip Due to High Steam Generator Water Level ENS 529922017-09-26T09:43:00026 September 2017 09:43:00 10 CFR 50.72(b)(3)(iv)(A), System Actuation Automatic Start of the 2B Emergency Diesel Due to a Valid Undervoltage Signal ENS 526192017-03-17T19:17:00017 March 2017 19:17:00 10 CFR 50.72(b)(3)(iv)(A), System Actuation Automatic Actuation of Emergency Diesel Generator ENS 525342017-02-03T20:45:0003 February 2017 20:45:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Unit 1 Manual Reactor Trip Due to Loop 1 Msiv Starting to Fail Closed ENS 519562016-05-25T06:06:00025 May 2016 06:06:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Automatic Reactor Trip on Lowering Steam Generator Water Level ENS 508942015-03-14T16:07:00014 March 2015 16:07:00 10 CFR 50.72(b)(3)(iv)(A), System Actuation Unplanned Actuation During Surveillance Test ENS 508932015-03-14T08:29:00014 March 2015 08:29:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation, 10 CFR 50.72(b)(2)(iv)(A), System Actuation - ECCS Discharge Automatic Reactor Trip on System Injection Actuation Signal ENS 505262014-10-12T13:44:00012 October 2014 13:44:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation Manual Reactor Trip During Reactor Startup ENS 503142014-07-27T18:09:00027 July 2014 18:09:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Manual Reactor Trip Due to Loss of Main Feed Pump During Testing ENS 500312014-04-13T00:08:00013 April 2014 00:08:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Manual Reactor Trip Due to Main Steam Isolation Valve Failing Shut ENS 500062014-04-08T08:28:0008 April 2014 08:28:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Automatic Reactor Trip Due to Low Steam Generator Level ENS 494612013-10-22T15:44:00022 October 2013 15:44:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Manual Reactor Trip Due to Decreasing Condenser Vacuum ENS 494532013-10-19T10:43:00019 October 2013 10:43:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Automatic Reactor Trip Due to Turbine Trip ENS 487882013-02-27T04:02:00027 February 2013 04:02:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Manual Reactor Trip Due to Excessive Reactor Coolant Pump Seal Leakoff Flow ENS 483852012-10-05T09:14:0005 October 2012 09:14:00 10 CFR 50.72(b)(3)(iv)(A), System Actuation Unplanned Auxiliary Feedwater Actuation ENS 478362012-04-14T17:46:00014 April 2012 17:46:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Manual Reactor Trip Due to Low Main Feedwater Flow ENS 472242011-08-31T13:06:00031 August 2011 13:06:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Turbine Trip on Hi-Hi Steam Generator Level Results in Automatic Reactor Trip ENS 467722011-04-20T21:34:00020 April 2011 21:34:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Automatic Reactor Trip ENS 455882009-12-23T20:25:00023 December 2009 20:25:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Manual Rps Actuation Due to Loss of Instrument Air ENS 455572009-12-10T04:10:00010 December 2009 04:10:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Manual Scram Following High Turbine Vibration ENS 455472009-12-07T23:01:0007 December 2009 23:01:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Automatic Reactor Trip Due to a Turbine Trip Caused by Low Condenser Vacuum ENS 433132007-04-23T14:24:00023 April 2007 14:24:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Automatic Reactor Trip Due to Generator Ground Relay Actuation ENS 429422006-10-28T16:23:00028 October 2006 16:23:00 10 CFR 50.72(b)(3)(iv)(A), System Actuation Specified System Actuation ENS 428062006-08-27T10:31:00027 August 2006 10:31:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Automatic Reactor Trip Due to Reactor Coolant Pump Trip ENS 425062006-04-17T04:26:00017 April 2006 04:26:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Unit 1 Manually Tripped Due to Failure of a Main Feed Regulating Valve to Control Steam Generator Level ENS 420582005-10-17T22:16:00017 October 2005 22:16:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Manual Reactor Trip Due to Low Steam Generator Level ENS 416532005-04-30T01:55:00030 April 2005 01:55:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Manual Reactor Trip - Lowering Steam Generator Level on Loop #1 ENS 413232005-01-11T12:19:00011 January 2005 12:19:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Automatic Reactor Trip Due to Main Turbine Trip ENS 412132004-11-20T16:40:00020 November 2004 16:40:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation, 10 CFR 50.72(b)(2)(iv)(A), System Actuation - ECCS Discharge Unexpected Automatic Reactor Trip During Surveillance Testing with Si Injection ENS 406822004-04-18T16:38:00018 April 2004 16:38:00 10 CFR 50.72(b)(3)(iv)(A), System Actuation Auxiliary Feedwater System Actuation Due to Main Feed Pump Trips ENS 406152004-03-28T03:05:00028 March 2004 03:05:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Manual Reactor Trip Due to Loss of Feedwater Pump Speed Control ENS 402682003-10-22T05:03:00022 October 2003 05:03:00 10 CFR 50.72(b)(3)(iv)(A), System Actuation High Pressure Hose Connection Failed Resulting in a Train "a" Manual Steam Line Isolation 2023-07-09T17:28:00 | |
Retrieved from "https://kanterella.com/wiki/index.php?title=ENS_52534&oldid=420701"