00:46 Sep 29, 2015 | |
Title | Automatic Reactor Scram Following Trip of Both Reactor Recirculation Pumps |
Event Description | On September 28, 2015 at 2046 EDT, the Hope Creek reactor scrammed following a trip of both reactor recirculation pumps.
All control rods fully inserted into the core. All safety systems responded as designed and expected. There was no radiological release. The unit is stable in Mode 3 with decay heat being removed via the turbine bypass valves rejecting steam to the main condenser. Normal feedwater level control is providing makeup to the reactor vessel. No personnel injuries resulted from the event. The Outage Control Center has been staffed to determine the cause of the reactor scram. The Hope Creek NRC Resident Inspector has been notified. The licensee notified Lower Alloways Creek township of the event. |
Where | |
---|---|
Hope Creek New Jersey (NRC Region 1) | |
Reporting | |
10 CFR 50.72(b)(2)(iv)(B), RPS Actuation | |
Time - Person (Reporting Time:+-1.95 h-0.0813 days <br />-0.0116 weeks <br />-0.00267 months <br />) | |
Opened: | Richard Ficarra 22:49 Sep 28, 2015 |
NRC Officer: | Howie Crouch |
Last Updated: | Sep 28, 2015 |
51430 - NRC Website | |
Unit 1 | |
---|---|
Reactor critical | Critical |
Scram | A/R |
Before | Power Operation (100 %) |
After | Hot Shutdown (0 %) |
WEEKMONTHYEARENS 568892023-12-15T00:39:00015 December 2023 00:39:00
[Table view]10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation Automatic Reactor Scram ENS 541982019-08-03T23:47:0003 August 2019 23:47:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Manual Reactor Trip and Manual Actuation of Reactor Core Isolation Cooling ENS 514302015-09-29T00:46:00029 September 2015 00:46:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation Automatic Reactor Scram Following Trip of Both Reactor Recirculation Pumps ENS 496082013-12-05T08:25:0005 December 2013 08:25:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Automatic Reactor Scram Following Turbine Trip on High Moisture Separator Level ENS 495922013-12-01T11:13:0001 December 2013 11:13:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation Automatic Reactor Scram Due to Main Turbine Trip ENS 491082013-06-12T17:33:00012 June 2013 17:33:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Circulating Water Pump Trip Leads to Reactor Scram ENS 450742009-05-17T07:35:00017 May 2009 07:35:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation Manual Reactor Scram Due to Loss of Scram Air Header ENS 431322007-01-30T04:10:00030 January 2007 04:10:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation Automatic Reactor Scram on Low Reactor Pressure Vessel (Rpv) Water Level ENS 411092004-10-10T22:14:00010 October 2004 22:14:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation, 10 CFR 50.72(b)(2)(iv)(A), System Actuation - ECCS Discharge Manual Reactor Scram Due to a Steam Leak in the Turbine Building ENS 404372004-01-12T15:48:00012 January 2004 15:48:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation Manual Scram Following Invalid Containment Isolation Signal ENS 402242003-10-04T21:13:0004 October 2003 21:13:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation Rps Actuation While Critical 2023-12-15T00:39:00 | |
Retrieved from "https://kanterella.com/w/index.php?title=ENS_51430&oldid=421371"