ENS Event | |
---|---|
12:35 May 20, 2014 | |
Title | Manual Reactor Trip During Reactor Startup |
Event Description | On May 20, 2014, at 0835 hours0.00966 days <br />0.232 hours <br />0.00138 weeks <br />3.177175e-4 months <br /> during plant startup, Beaver Valley Power Station Unit 2 Operations personnel manually tripped the reactor due to meeting the pre-briefed trip criteria of 85% narrow range level on the 'A' Steam Generator. This manual trip criterion was reached after the steam generator water level began to oscillate following the start of the 'A' Condensate pump. A manual main steam line isolation was performed in order to limit reactor coolant system cool down. Plant trip response was as expected without complications, and all control rods fully inserted in the core. The plant is currently stable in Mode 3.
This event is reportable pursuant to 10 CFR 50.72(b)(2)(iv)(B) and 10 CFR 50.72(b)(3)(iv)(A). Beaver Valley Power Station Unit 1 was not affected by this event. The NRC Resident Inspector has been notified. No relief or safety valves lifted during this event. The unit is maintaining primary temperature using the atmospheric steam dumps and main feedwater pumps. There is no primary to secondary leakage. The plant is in its normal shutdown electrical lineup. |
Where | |
---|---|
Beaver Valley Pennsylvania (NRC Region 1) | |
Reporting | |
10 CFR 50.72(b)(2)(iv)(B), RPS Actuation 10 CFR 50.72(b)(3)(iv)(A), System Actuation | |
LER: | 05000412/LER-2014-002 |
Time - Person (Reporting Time:+-1.72 h-0.0717 days <br />-0.0102 weeks <br />-0.00236 months <br />) | |
Opened: | Michael Steranko 10:52 May 20, 2014 |
NRC Officer: | Mark Abramovitz |
Last Updated: | May 20, 2014 |
50124 - NRC Website | |
Unit 2 | |
---|---|
Reactor critical | Critical |
Scram | Yes, Manual Scram |
Before | Power Operation (17 %) |
After | Hot Standby (0 %) |
Beaver Valley with 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation | |
WEEKMONTHYEARENS 565272023-05-19T12:52:00019 May 2023 12:52:00
[Table view]10 CFR 50.72(b)(3)(iv)(A), System Actuation Automatic Actuation of Auxiliary Feedwater System (AFW) ENS 559432022-06-15T11:24:00015 June 2022 11:24:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Manual Reactor Trip and Automatic Auxiliary Feedwater Actuation ENS 555862021-11-17T18:13:00017 November 2021 18:13:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Manual Reactor Trip and Automatic Auxiliary Feedwater Actuation ENS 555722021-11-12T15:07:00012 November 2021 15:07:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation Manual Reactor Trip Due to Increasing Steam Generator Water Levels ENS 555072021-10-05T10:32:0005 October 2021 10:32:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Automatic Reactor Trip and Auxiliary Feedwater Actuation ENS 543692019-11-04T10:35:0004 November 2019 10:35:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation Manual Reactor Trip Due to Steam Dump Transient ENS 530562017-11-07T10:04:0007 November 2017 10:04:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Unit 1 Automatic Reactor Trip Due to Main Unit Generator Over Current ENS 501242014-05-20T12:35:00020 May 2014 12:35:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Manual Reactor Trip During Reactor Startup ENS 496972014-01-06T21:59:0006 January 2014 21:59:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Automatic Reactor Trip Due to Main Transformer Fault ENS 495052013-11-05T23:28:0005 November 2013 23:28:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(a)(1)(i), Emergency Class Declaration, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Notification of Unusual Event Due to Explosion and Fire in the Turbine Building ENS 493922013-09-30T06:38:00030 September 2013 06:38:00 10 CFR 50.72(b)(3)(iv)(A), System Actuation Manual Start of Motor Driven Auxiliary Feedwater Pump ENS 467442011-04-10T07:45:00010 April 2011 07:45:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation, 10 CFR 50.72(b)(2)(i), Tech Spec Required Shutdown, 10 CFR 50.72(b)(3)(ii)(A), Seriously Degraded Manual Reactor Trip While Performing a Technical Specification Required Shutdown ENS 450002009-04-20T05:15:00020 April 2009 05:15:00 10 CFR 50.72(b)(3)(iv)(A), System Actuation Auxiliary Feedwater Actuation on Valid Steam Generator Hi-Hi Signal During Shutdown ENS 442392008-05-24T13:38:00024 May 2008 13:38:00 10 CFR 50.72(b)(3)(iv)(A), System Actuation Steam Generator Level Excursion ENS 428342006-09-08T01:57:0008 September 2006 01:57:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Automatic Reactor Trip Following Spurious Opening of a Reactor Trip Breaker ENS 424672006-04-02T18:02:0002 April 2006 18:02:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Automatic Reactor Trip Due to a Main Generator Trip ENS 403202003-11-13T16:35:00013 November 2003 16:35:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Automatic Reactor Trip from 100% Power with Cause Being Investigated ENS 402472003-10-15T03:55:00015 October 2003 03:55:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Automatic Reactor Trip Due to Low "B" Steam Generator Water Level. 2023-05-19T12:52:00 | |