ENS 47728
ENS Event | |
---|---|
02:50 Mar 9, 2012 | |
Title | Inoperable Steam Generator Narrow Range Level Transmitters Due to Part 21 Concern |
Event Description | Pacific Gas and Electric (PG&E) is supplying this information as a voluntary report. On March 8, 2012, at 1850 PST, Diablo Canyon Power Plant (DCPP), Unit 1, declared the steam generator (SG) 1-1 narrow-range, low-low, water level channels for level transmitters LT-517 and LT-519 inoperable. This resulted from DCPP determining that the low-low setpoints were non-conservative as a result of its evaluation of the Rosemount Nuclear's 10 CFR Part 21 notification titled 'Notification Under 10 CFR Part 21 on Certain Rosemount Model 1154 Series H Pressure Transmitters,' dated March 2, 2012.
PG&E determined that the following SG narrow-range level transmitters having reactor protection and emergency safeguards actuation functions are affected: Unit 1: - two channels on SG 1-1 - one channel each on SGs 1-2 and 1-4 Unit 2: - one channel each on SGs 2-1, 2-2, 2-3 and 2-4 The Part 21 notification identified that the high temperature/pressure accuracy specification changed for certain transmitters which have higher impedance resistors installed in their temperature compensation circuitry. PG&E's evaluation concluded that narrow range SG low-low level setpoint uncertainty increased by as much as 2 percent of span due to the revised specification. Under the most limiting conditions, this deficiency could result in a short delay in relay actuation. At 1953 PST, DCPP personnel declared the LT-517 and LT-519 water level low-low channels for SG 1-1 to be operable after adjusting the low-low setpoints from 15 percent to 17 percent on SG 1-1. DCPP also changed the low-low setpoints on SG 1-2 and SG 1-4 on March 8, 2012, and is changing this setpoint on all four of the Unit 2 SGs. PG&E plans to submit a Licensee Event Report on this issue. Plant personnel notified the NRC Resident Inspector. |
Where | |
---|---|
Diablo Canyon California (NRC Region 4) | |
Reporting | |
Information Only | |
Time - Person (Reporting Time:+16.45 h0.685 days <br />0.0979 weeks <br />0.0225 months <br />) | |
Opened: | David Bahner 19:17 Mar 9, 2012 |
NRC Officer: | Bill Huffman |
Last Updated: | Mar 9, 2012 |
47728 - NRC Website | |
Unit 1 | |
---|---|
Reactor critical | Critical |
Scram | No |
Before | Power Operation (100 %) |
After | Power Operation (100 %) |
Unit 2 | |
---|---|
Reactor critical | Critical |
Scram | No |
Before | Power Operation (100 %) |
After | Power Operation (100 %) |
WEEKMONTHYEARENS 478582012-04-21T23:15:00021 April 2012 23:15:00
[Table view]Information Only Apparent Phase Imbalance Between Normal and Alternate Power Circuits ENS 477282012-03-09T02:50:0009 March 2012 02:50:00 Information Only Inoperable Steam Generator Narrow Range Level Transmitters Due to Part 21 Concern ENS 431022007-01-14T23:42:00014 January 2007 23:42:00 Information Only Information Regarding Wildfire in the Vicinity of the Plant Site 2012-04-21T23:15:00 | |