15:25 Nov 7, 2009 | |
Title | Manual Reactor Scram Due to a Main Turbine Digital Electro-Hydraulic Control System Leak |
Event Description | At 0725 hours0.00839 days <br />0.201 hours <br />0.0012 weeks <br />2.758625e-4 months <br />, a manual scram was inserted due to a Main Turbine Digital Electro-Hydraulic (DEH) control system leak and anticipated turbine trip on loss of DEH tank level. Initial investigation identified a DEH leak at the area of the Quad-Voter hydraulic trip subsystem on the high pressure turbine.
All rods fully inserted, main steam isolation valves (MSIVs) remained open, no safety/relief valves (SRVs) opened, and all other safety systems operated as designed. Reactor water level was restored and maintained with the Reactor Feedwater and Condensate systems during the post-scram transient within normal operating bands. Reactor pressure was controlled using main steam drain lines. A normal cooldown to the condenser is in progress. Offsite power is available. All three emergency diesel generators are operable and available. The plant was operating at 52% for planned maintenance. All safety systems remain available. The licensee has notified the NRC Resident Inspector. |
Where | |
---|---|
Columbia Generating Station Washington (NRC Region 4) | |
Reporting | |
10 CFR 50.72(b)(2)(iv)(B), RPS Actuation | |
LER: | 05000397/LER-2009-005 |
Time - Person (Reporting Time:+-2.47 h-0.103 days <br />-0.0147 weeks <br />-0.00338 months <br />) | |
Opened: | Eric Franke 12:57 Nov 7, 2009 |
NRC Officer: | Dong Park |
Last Updated: | Nov 7, 2009 |
45484 - NRC Website | |
Unit 2 | |
---|---|
Reactor critical | Critical |
Scram | Yes, Manual Scram |
Before | Power Operation (52 %) |
After | Hot Shutdown (0 %) |
WEEKMONTHYEARENS 534102018-05-18T13:51:00018 May 2018 13:51:00
[Table view]10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation Automatic Reactor Scram Caused by Main Transformer Trip ENS 529182017-08-20T23:05:00020 August 2017 23:05:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Manual Reactor Scram Due to a Rise in Main Condenser Back Pressure ENS 524422016-12-18T19:24:00018 December 2016 19:24:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation, 10 CFR 50.72(b)(2)(iv)(A), System Actuation - ECCS Discharge Automatic Scram Due to Load Reject from Substation ENS 518262016-03-28T20:22:00028 March 2016 20:22:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation Manual Scram Following Loss of Reactor Closed Cooling ENS 454842009-11-07T15:25:0007 November 2009 15:25:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation Manual Reactor Scram Due to a Main Turbine Digital Electro-Hydraulic Control System Leak ENS 452452009-08-05T14:50:0005 August 2009 14:50:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(a)(1)(i), Emergency Class Declaration, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Unusual Event Declared Due to Toxic Gas from a Switchgear Fire in the Turbine Building ENS 451692009-06-27T03:05:00027 June 2009 03:05:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(a)(1)(i), Emergency Class Declaration Unusual Event Declared Based on Fire Lasting Greater than 15 Minutes ENS 450512009-05-08T17:45:0008 May 2009 17:45:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation Manual Reactor Scram After Loss of Generator Seal Oil ENS 448392009-02-08T19:25:0008 February 2009 19:25:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation Automatic Reactor Scram Due to a Governor Valve Fast Closure Signal ENS 444322008-08-21T23:06:00021 August 2008 23:06:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation Automatic Reactor Scram Due to a Main Turbine Trip ENS 434572007-06-29T00:17:00029 June 2007 00:17:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation Reactor Trip Due to Condensate Pump Trip ENS 429502006-10-31T12:45:00031 October 2006 12:45:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation Reactor Trip from Turbine Trip on Low Auto Stop Oil Pressure ENS 417902005-06-23T20:46:00023 June 2005 20:46:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Unit Experienced an Automatic Reactor Scram Due to a Loss of Feedwater Flow ENS 417792005-06-15T21:00:00015 June 2005 21:00:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Automatic Reactor Scram Due to Turbine Throttle Valve Closure ENS 409642004-08-17T12:28:00017 August 2004 12:28:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation Manual Reactor Scram Due to Trip of Reactor Feedwater Pump "a" on Low Suction Pressure. ENS 409592004-08-15T20:03:00015 August 2004 20:03:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation Manual Reactor Scram Due to Reactor Feedwater Pump Trip ENS 409102004-07-30T17:00:00030 July 2004 17:00:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(a)(1)(i), Emergency Class Declaration Alert Declared at Columbia Generating Station 2018-05-18T13:51:00 | |
Retrieved from "https://kanterella.com/w/index.php?title=ENS_45484&oldid=425565"