ENS 41212
ENS Event | |
---|---|
22:22 Nov 19, 2004 | |
Title | Technical Specification Required Shutdown Due to a Steam Leak on an Instrument Isolation Valve Inside Containment |
Event Description | The following information was obtained from the licensee via facsimile:
On November 9, 2004, NMC personnel performed a containment entry for Point Beach Nuclear Plant Unit 2 to locate and identify the source of a secondary steam leak. A leak was suspected due to increased pumping of the Unit 2 containment sump 'A'. A steam leak was identified on the body of valve 2MS-465D. This valve is an isolation valve for main steam flow transmitter 2FT-465. For containment isolation considerations, the main steam system is considered to be a closed system inside containment. The steam leak discovered on 2MS-465D cannot be isolated from containment penetration P-1, the main steam line penetration. Accordingly, we declared Technical Specification Condition 3.6.3.C not met. (This condition is applicable to penetration flow paths with only one containment isolation valve and a closed system) and entered TSAC [Technical Specification Action Condition] C.1. The required action for this condition is to isolate the affected penetration flow path with a completion time of 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. In order to repair this valve wall leak, it will be necessary to shutdown and cooldown PBNP Unit 2. Accordingly, at 1622 CST we initiated a reactor shutdown of PBNP Unit 2. Since we anticipate that we would be unable to [meet] the allowed completion time for this TSAC, we have determined that this reactor shutdown is required by the Technical Specifications and is reportable in accordance with 10 CFR 50.72.(b)(2)(i). The licensee has notified the NRC Resident Inspector. |
Where | |
---|---|
Point Beach Wisconsin (NRC Region 3) | |
Reporting | |
10 CFR 50.72(b)(2)(i), Tech Spec Required Shutdown | |
LER: | 05000301/LER-2004-003 |
Time - Person (Reporting Time:+-3.35 h-0.14 days <br />-0.0199 weeks <br />-0.00459 months <br />) | |
Opened: | Mike Meyer 19:01 Nov 19, 2004 |
NRC Officer: | Howie Crouch |
Last Updated: | Nov 19, 2004 |
41212 - NRC Website | |
Unit 2 | |
---|---|
Reactor critical | Critical |
Scram | No |
Before | Power Operation (100 %) |
After | Hot Standby (0 %) |
WEEKMONTHYEARENS 503962014-08-24T05:00:00024 August 2014 05:00:00
[Table view]10 CFR 50.72(b)(2)(i), Tech Spec Required Shutdown Technical Specification Required Shutdown Due to Post Accident Monitoring Instrumentation Out of Service ENS 464752010-12-13T18:10:00013 December 2010 18:10:00 10 CFR 50.72(b)(2)(i), Tech Spec Required Shutdown Technical Specification Required Shutdown Due to Not Meeting Rod Group Allignment Limits ENS 439072008-01-15T20:15:00015 January 2008 20:15:00 10 CFR 50.72(b)(2)(xi), Notification to Government Agency or News Release, 10 CFR 50.72(a)(1)(i), Emergency Class Declaration, 10 CFR 50.72(b)(2)(i), Tech Spec Required Shutdown Unusual Event - Loss of Offsite Power ENS 436492007-09-18T13:43:00018 September 2007 13:43:00 10 CFR 50.72(b)(2)(i), Tech Spec Required Shutdown Refueling Water Storage Tank Temperature Above Operating Limits ENS 434242007-06-14T23:19:00014 June 2007 23:19:00 10 CFR 50.72(b)(2)(i), Tech Spec Required Shutdown Tech Spec. Required Shutdown Due to 72 Hour Completion Time Not Met ENS 421092005-11-02T05:00:0002 November 2005 05:00:00 10 CFR 50.72(b)(3)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident, 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition, 10 CFR 50.72(b)(2)(i), Tech Spec Required Shutdown Tech Spec Required Shutdown Due to Degradation of Containment Coatings ENS 414472005-02-27T17:58:00027 February 2005 17:58:00 10 CFR 50.72(b)(2)(i), Tech Spec Required Shutdown Technical Specification Required Shutdown Due to Loss of Dc Battery Chargers ENS 412122004-11-19T22:22:00019 November 2004 22:22:00 10 CFR 50.72(b)(2)(i), Tech Spec Required Shutdown Technical Specification Required Shutdown Due to a Steam Leak on an Instrument Isolation Valve Inside Containment ENS 406262004-03-30T18:15:00030 March 2004 18:15:00 10 CFR 50.72(b)(2)(i), Tech Spec Required Shutdown Safety Injection Accumulator Level Greater than Allowed by Technical Specification 2014-08-24T05:00:00 | |