ENS 40538
From kanterella
Jump to navigation
Jump to search
ENS Event | |
---|---|
22:30 Feb 22, 2004 | |
Title | Unit 1 Manually Tripped After the "B" Sg Feedwater Isolation Valve Failed Closed |
Event Description | The 1CF-42B (1B Steam Generator Feedwater Isolation Valve) failed closed with Unit 1 at 100% power. Operators performed a manual reactor trip as required by 'Loss of Normal Steam Generator Feedwater Supply', AP-06. Emergency procedures were utilized to respond and stabilize Unit 1 in mode 3. The plant is currently stable in mode 3 at normal operating pressure and temperature. Currently, steam generator levels are being maintained using the auxiliary feedwater system. Other than the failure of 1CF-42B (Initiating Event), all plant safety systems operated as required.
No primary or secondary safeties or reliefs lifted during the transient. All control rods fully inserted. The main condenser is in-service to remove decay heat. The licensee had identified a problem with the hydraulic motor associated with 1CF-42B and was in the process of developing corrective actions before the failure. The licensee will inform both state/local agencies (courtesy notification) and has informed the NRC resident inspector. |
Where | |
---|---|
Catawba South Carolina (NRC Region 2) | |
Reporting | |
10 CFR 50.72(b)(2)(iv)(B), RPS Actuation 10 CFR 50.72(b)(3)(iv)(A), System Actuation | |
Time - Person (Reporting Time:+-3.47 h-0.145 days <br />-0.0207 weeks <br />-0.00475 months <br />) | |
Opened: | Jimmy Burgess 19:02 Feb 22, 2004 |
NRC Officer: | Steve Sandin |
Last Updated: | Feb 22, 2004 |
40538 - NRC Website | |
Unit 1 | |
---|---|
Reactor critical | Critical |
Scram | Yes, Manual Scram |
Before | Power Operation (100 %) |
After | Hot Standby (0 %) |
Catawba with 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation | |
WEEKMONTHYEARENS 570262024-03-13T01:11:00013 March 2024 01:11:00
[Table view]10 CFR 50.72(b)(3)(iv)(A), System Actuation Loss of Power to Containment Radiation Monitors ENS 561772022-10-24T12:57:00024 October 2022 12:57:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Manual Reactor Trip and Auxiliary Feedwater System Actuation ENS 558562022-04-23T06:24:00023 April 2022 06:24:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Manual Reactor Trip During Control Rod Testing ENS 555492021-10-27T18:29:00027 October 2021 18:29:00 10 CFR 50.72(b)(3)(iv)(A), System Actuation Automatic Actuation of the 1B EDG Load Sequencer on Bus Undervoltage Condition ENS 552292021-05-01T11:55:0001 May 2021 11:55:00 10 CFR 50.72(b)(3)(iv)(A), System Actuation Automatic Reactor Trip and Actuation of the Auxiliary Feedwater System ENS 548882020-09-08T13:25:0008 September 2020 13:25:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation Automatic Reactor Trip on Over Power Delta Temperature ENS 545232020-02-12T23:00:00012 February 2020 23:00:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation Automatic Reactor Scram Due to Main Turbine Trip ENS 543072019-10-02T08:15:0002 October 2019 08:15:00 10 CFR 50.72(b)(3)(iv)(A), System Actuation Actuation of Containment Spray System ENS 532712018-03-19T07:29:00019 March 2018 07:29:00 10 CFR 50.72(b)(3)(iv)(A), System Actuation Unplanned Actuation of Auxiliary Feedwater System During Maintenance ENS 467802011-04-23T13:21:00023 April 2011 13:21:00 10 CFR 50.72(b)(3)(iv)(A), System Actuation Valid Auxiliary Feedwater Pump Start While Cooling Down Reactor ENS 435972007-08-25T14:58:00025 August 2007 14:58:00 10 CFR 50.72(b)(3)(iv)(A), System Actuation Autostart of All Emergency Diesel Generators Due to a Grid Disturbance ENS 412462004-12-06T02:35:0006 December 2004 02:35:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Automatic Turbine Trip/Reactor Trip Due to Moisture Separator Reheater (Msr) High Level Trip Signal. ENS 411542004-10-28T04:52:00028 October 2004 04:52:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Manual Reactor Trip After Shutdown Bank Dropped Into Core ENS 405382004-02-22T22:30:00022 February 2004 22:30:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Unit 1 Manually Tripped After the "B" Sg Feedwater Isolation Valve Failed Closed ENS 401142003-08-29T06:03:00029 August 2003 06:03:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Catawba Unit 1 Automatic Reactor Trip Due to Reactor Protection System Actuation 2024-03-13T01:11:00 | |