MONTHYEARCP-202400030, License Renewal Application Revision 0 - Supplement 3, Revision 12024-01-31031 January 2024 License Renewal Application Revision 0 - Supplement 3, Revision 1 CP-202400034, (CPNPP) - Core Operating Limits Report (Colr), Unit 2 Cycle 21, (ERX-23-001, Revision 1)2024-01-29029 January 2024 (CPNPP) - Core Operating Limits Report (Colr), Unit 2 Cycle 21, (ERX-23-001, Revision 1) CP-202300575, (Cpnpp), License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors Supplement 22023-12-13013 December 2023 (Cpnpp), License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors Supplement 2 CP-202300566, (Cpnpp), Special Report 1-SR-23-001-00, Inoperable Post Accident Monitoring Instrumentation2023-12-12012 December 2023 (Cpnpp), Special Report 1-SR-23-001-00, Inoperable Post Accident Monitoring Instrumentation CP-202300494, License Renewal Application Revision 0, Supplement 32023-12-0606 December 2023 License Renewal Application Revision 0, Supplement 3 CP-202300349, License Amendment Request (Lar) 23-004 Technical Specifications (TS) 3.9.3, Nuclear Instrumentation2023-11-20020 November 2023 License Amendment Request (Lar) 23-004 Technical Specifications (TS) 3.9.3, Nuclear Instrumentation CP-202300416, Supplemental Information to Facilitate Acceptance of Licensee Amendment Request 23-002, Application Regarding GDC-5 Shared System Requirements2023-10-12012 October 2023 Supplemental Information to Facilitate Acceptance of Licensee Amendment Request 23-002, Application Regarding GDC-5 Shared System Requirements CP-202300432, Response to Request for Additional Information Regarding the Safety Review of the License Renewal Application - Set 42023-10-0404 October 2023 Response to Request for Additional Information Regarding the Safety Review of the License Renewal Application - Set 4 CP-202300442, (CPNPP) - Request to Use Later Code Edition for Inservice Inspection (ISI) Program2023-09-15015 September 2023 (CPNPP) - Request to Use Later Code Edition for Inservice Inspection (ISI) Program CP-202300391, (CPNPP) - Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule2023-08-24024 August 2023 (CPNPP) - Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule CP-202300411, (Cpnpp), Inservice Inspection (ISI) Owner'S Activity Reports (OAR-1 Forms) for Unit 2 Refueling Outage 20 (2RF20)2023-08-17017 August 2023 (Cpnpp), Inservice Inspection (ISI) Owner'S Activity Reports (OAR-1 Forms) for Unit 2 Refueling Outage 20 (2RF20) CP-202300361, (CPNPP) - Unit 2 Refueling Outage 20 (2RF20) Steam Generator 180 Day Report2023-08-17017 August 2023 (CPNPP) - Unit 2 Refueling Outage 20 (2RF20) Steam Generator 180 Day Report CP-202300401, 10CFR50.59 Evaluation Summary Report 024, 10CFR72.48 Evaluation Summary Report 009, and Commitment Material Change Evaluation Report 0182023-08-15015 August 2023 10CFR50.59 Evaluation Summary Report 024, 10CFR72.48 Evaluation Summary Report 009, and Commitment Material Change Evaluation Report 018 CP-202300358, (Cpnpp), Transmittal of Electronic Licensing Basis Documents Including Certified FSAR Amendment 1122023-08-0101 August 2023 (Cpnpp), Transmittal of Electronic Licensing Basis Documents Including Certified FSAR Amendment 112 CP-202300322, Response to Requests for Additional Information Regarding Review of the License Renewal Application Sets 2 and 32023-07-27027 July 2023 Response to Requests for Additional Information Regarding Review of the License Renewal Application Sets 2 and 3 CP-202300348, (Cpnpp), Transmittal of Revised Emergency Plan (Revision 48)2023-07-18018 July 2023 (Cpnpp), Transmittal of Revised Emergency Plan (Revision 48) CP-202300285, Response to Request for Additional Information Regarding Review of the License Renewal Application - Set 12023-07-12012 July 2023 Response to Request for Additional Information Regarding Review of the License Renewal Application - Set 1 CP-202300262, Response to Request for Confirmation of Information Regarding Review of the License Renewal Application - Set 22023-06-20020 June 2023 Response to Request for Confirmation of Information Regarding Review of the License Renewal Application - Set 2 CP-202300263, Supplemental Information to Facilitate Acceptance of Licensee Amendment Request 23-002, Application Regarding GDC-5 Shared System Requirements2023-06-15015 June 2023 Supplemental Information to Facilitate Acceptance of Licensee Amendment Request 23-002, Application Regarding GDC-5 Shared System Requirements CP-202300248, Response to Request for Additional Information Regarding License Renewal Application - Set 12023-06-13013 June 2023 Response to Request for Additional Information Regarding License Renewal Application - Set 1 CP-202300209, Response to Request for Additional Information - License Renewal Application Environmental Review2023-06-0606 June 2023 Response to Request for Additional Information - License Renewal Application Environmental Review CP-202300207, Revision to Comanche Peak Nuclear Power Plant'S Response to Notice of Violation (NOV) 05000445/2021011-052023-05-25025 May 2023 Revision to Comanche Peak Nuclear Power Plant'S Response to Notice of Violation (NOV) 05000445/2021011-05 CP-202300182, Response to Requests for Confirmation of Information Regarding the Environmental Review of the License Renewal Application2023-05-0808 May 2023 Response to Requests for Confirmation of Information Regarding the Environmental Review of the License Renewal Application CP-202300201, (CPNPP) - Core Operating Limits Report (Colr), Unit 2 Cycle 21, (ERX-23-001, Revision 0)2023-05-0404 May 2023 (CPNPP) - Core Operating Limits Report (Colr), Unit 2 Cycle 21, (ERX-23-001, Revision 0) CP-202300160, (Cpnpp), 2022 Annual Radiological Environmental Operating Report2023-04-27027 April 2023 (Cpnpp), 2022 Annual Radiological Environmental Operating Report CP-202300159, (Cpnpp), 2022 Annual Radiological Effluent Release Report2023-04-27027 April 2023 (Cpnpp), 2022 Annual Radiological Effluent Release Report CP-202300165, License Renewal Application Revision 0 - Supplement 22023-04-24024 April 2023 License Renewal Application Revision 0 - Supplement 2 CP-202300175, Submittal of 2022 Annual Environmental Operating Report (Non-Radiological)2023-04-20020 April 2023 Submittal of 2022 Annual Environmental Operating Report (Non-Radiological) CP-202300181, ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, ISFSI, Corrected Affidavit for Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-04-20020 April 2023 ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, ISFSI, Corrected Affidavit for Application for Order Consenting to Transfer of Licenses and Conforming License Amendments CP-202300096, License Amendment Request (LAR) 23-002 Application Regarding GDC-5 Shared Systems Requirements2023-04-20020 April 2023 License Amendment Request (LAR) 23-002 Application Regarding GDC-5 Shared Systems Requirements CP-202300140, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors. LAR 23-0012023-04-19019 April 2023 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors. LAR 23-001 CP-202300157, ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, and ISFSI, Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-04-14014 April 2023 ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, and ISFSI, Application for Order Consenting to Transfer of Licenses and Conforming License Amendments CP-202300135, License Renewal Application Revision 0 - Supplement 12023-04-0606 April 2023 License Renewal Application Revision 0 - Supplement 1 CP-202300144, (CPNPP) - Decommissioning Report2023-03-30030 March 2023 (CPNPP) - Decommissioning Report CP-202300139, (CPNPP) - Property Damage Insurance2023-03-30030 March 2023 (CPNPP) - Property Damage Insurance CP-202300098, (Cpnpp), Annual Report of Changes in Peak Cladding Temperature2023-03-16016 March 2023 (Cpnpp), Annual Report of Changes in Peak Cladding Temperature CP-202200481, Response to Request for Additional Information - Relief Request Application P-1, Inservice Testing (IST)2022-12-0707 December 2022 Response to Request for Additional Information - Relief Request Application P-1, Inservice Testing (IST) CP-202200454, (Cpnpp), Reply to a Notice of Violation Transmitted Via NRC Letter from Gregory Werner to Ken Peters Dated 11/01/2022, Comanche Peak Nuclear Power Plant, Units 1 and 2 Integrated Inspection Report 05000445/2022003 .2022-12-0101 December 2022 (Cpnpp), Reply to a Notice of Violation Transmitted Via NRC Letter from Gregory Werner to Ken Peters Dated 11/01/2022, Comanche Peak Nuclear Power Plant, Units 1 and 2 Integrated Inspection Report 05000445/2022003 . CP-202200355, Application to Revise Technical Specifications to Apply the Westinghouse Full Spectrum Loss of Coolant Accident Evaluation Model LAR 22-0022022-11-21021 November 2022 Application to Revise Technical Specifications to Apply the Westinghouse Full Spectrum Loss of Coolant Accident Evaluation Model LAR 22-002 CP-202200380, (CPNPP) - Non-Voluntary License Amendment Request to Revise Technical Specifications 3.2.1, Fq(Z), to Implement Methodology from WCAP-17661, Revision 1, Improved RAOC and CAOC Fq Surveillance Technical Specifications2022-11-21021 November 2022 (CPNPP) - Non-Voluntary License Amendment Request to Revise Technical Specifications 3.2.1, Fq(Z), to Implement Methodology from WCAP-17661, Revision 1, Improved RAOC and CAOC Fq Surveillance Technical Specifications CP-202200450, (CPNPP) - Registration of Dry Spent Fuel Storage Canisters2022-11-16016 November 2022 (CPNPP) - Registration of Dry Spent Fuel Storage Canisters CP-202200435, (Cpnpp), Registration of Dry Spent Fuel Storage Canisters2022-11-0808 November 2022 (Cpnpp), Registration of Dry Spent Fuel Storage Canisters CP-202200419, (CPNPP) - Unit 1 Refueling Outage 22 (1RF22) Steam Generator 180 Day Report2022-11-0303 November 2022 (CPNPP) - Unit 1 Refueling Outage 22 (1RF22) Steam Generator 180 Day Report CP-202200357, (CPNPP) Unit 2 - Response to Request for Additional Information, Fall 2021 (2RF19) Steam Generator Tube Inspection Report2022-09-14014 September 2022 (CPNPP) Unit 2 - Response to Request for Additional Information, Fall 2021 (2RF19) Steam Generator Tube Inspection Report CP-202200358, (CPNPP) - Transmittal of Revised Emergency Plan (Revision 46)2022-09-14014 September 2022 (CPNPP) - Transmittal of Revised Emergency Plan (Revision 46) CP-202200246, Evacuation Time Estimate Analysis2022-08-25025 August 2022 Evacuation Time Estimate Analysis CP-202200306, (CPNPP) - Inservice Inspection (ISI) Owner'S Activity Reports (OAR-1 Forms) for Unit 1 Refueling Outage 22 (1RF22)2022-08-11011 August 2022 (CPNPP) - Inservice Inspection (ISI) Owner'S Activity Reports (OAR-1 Forms) for Unit 1 Refueling Outage 22 (1RF22) CP-202200273, Third Supplement to License Amendment Request (LAR) 20-006 Application to Revise Technical Specifications to Adopt Risk Informed Completion Times, TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative2022-07-20020 July 2022 Third Supplement to License Amendment Request (LAR) 20-006 Application to Revise Technical Specifications to Adopt Risk Informed Completion Times, TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative CP-202200276, (CPNPP) - Relief Request Application P-1, Inservice Testing (IST)2022-07-20020 July 2022 (CPNPP) - Relief Request Application P-1, Inservice Testing (IST) CP-202200247, (CPNPP) - 10CFR50.59 Evaluation Summary Report 023, 10CFR72.48 Evaluation Summary Report 008 and Commitment Material Change Evaluation Report 0172022-06-30030 June 2022 (CPNPP) - 10CFR50.59 Evaluation Summary Report 023, 10CFR72.48 Evaluation Summary Report 008 and Commitment Material Change Evaluation Report 017 2024-01-31
[Table view] |
Text
Mike Blevins Luminant Power Senior Vice President P 0 Box 1002
& Chief Nuclear Officer 6322 North FM 56 Mike.Blevins@Luminant.com Glen Rose, TX 76043 LuM, 0 'F'. %ýLFJim T 254 897 5209 C 817 559 9085 F 254 897 6652 CP-200700046 Ref. # 10CFR 50.80 Log # TXX-07154 November 5, 2007 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555
SUBJECT:
COMANCHE PEAK STEAM ELECTRIC STATION DOCKET NOS. 50-445 AND 50-446 INFORMATION REQUIRED BY ORDER APPROVING THE INDIRECT TRANSFER OF FACILITY OPERATING LICENSES AND CONFORMING LICENSE AMENDMENTS
REFERENCE:
NRC Order Approving The Indirect Transfer Of Facility Operating Licenses And Conforming License Amendments dated September 10, 2007
[TAC Nos. MD5289 and MD5290]
Dear Sir or Madam:
Luminant Generation Company LLC (Luminant Power, formerly known as TXU Power) hereby submits as an Enclosure to this letter the information as ordered by the Commission in the referenced letter above.
The support agreement between Luminant Holding Company LLC and Luminant Generation Company LLC was executed on October 10, 2007 upon closing of the transaction and completion of the license transfer.
If the NRC requires additional information concerning this license transfer, please contact Mr. Fred Madden, Director, Oversight & Regulatory Affairs (tel: 254-897-8601).
This communication contains no new licensing basis commitments regarding Comanche Peak Units 1 and 2.
A member of the STARS (Strategic Teaming and Resource Sharing) Alliance 40oo/
Callaway - Comanche Peak - Diablo Canyon
- Palo Verde ' South Texas Project - Wolf Creek 0,-eA
U. S. Nuclear Regulatory Commission TXX-07154 Page 2 11/05/2007 Sincerely, Luminant Generation Company LLC Mike Blevins By:
/"e-' a-fW."Madden Director, Oversight & Regulatory Affairs Enclosure Executed Support Agreement RJK
U. S. Nuclear Regulatory Commission TXX-07154 Page 3 11/05/2007 cc: (paper copy) (electronic copy)
James E. Dyer Timothy Matthews, Esq.
Director, Office of Nuclear Reactor Regulation Bruce McPherson, Esq.
U.S. Nuclear Regulatory Commission - Morgan, Lewis & Bockius LLP One White Flint North 11555 Rockville Pike Dr. Richard A. Meserve Rockville, MD 20852 Thomas L. Cubbage III, Esq.
- Covington & Burling LLP Regional Administrator, Region IV U.S. Nuclear Regulatory Commission Marc S. Lipschultz, KKR 611 Ryan Plaza Drive, Suite 400 Frederick M. Goltz, KKR Arlington, TX 76011-8064 Jonathan D. Smidt, KKR Robert D. Carlson Michael MacDougall, Texas Pacific Group U. S. Nuclear Regulatory Commission Jeffrey Liaw, Texas Pacific Group One White Flint North 11555 Rockville Pike Kenneth Pontarelli, Goldman Rockville, MD 20852 Scott Lebovitz, Goldman Mail Stop OWFN/12-D3 David Thomas, Esq., Goldman Michael A. Dusaniwskyj U. S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike Rockville, MD 20852 Mail Stop TWFN/2E-26 Susan L. Uttal, Esq.
U. S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike Rockville, MD 20852 Mail Stop OWFN/15-D21 Resident Inspectors, CPSES Balwant Singal U.S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike Rockville, MD 20852 Mail Stop OWFN/7-D1A Ms. Alice K. Rogers Environmental & Consumer Safety Section Texas Department of State Health Services 1100 West 49th Street Austin, Texas 78756-3189
SUPPORT AGREEMENT THIS SUPPORT AGREEMENT (as amended, supplemented or otherwise modified from time to time, this "Agreement"), dated as of October 10, 2007, between Luminant Holding Company LLC, a Delaware limited liability company (the "Parent"), and Luminant Generation Company LLC (formerly TXU Generation Company LP), a Texas limited liability company (the "Subsidiary").
WITNESSETH:
WHEREAS, the Parent is the direct owner of 100% of the limited liability company interests of the Subsidiary; WHEREAS, the Subsidiary is the owner of the Comanche Peak Steam Electric Station, Units 1 and 2 ("CPSES") and holder of the licenses to operate CPSES; WHEREAS, TXU Corp., which indirectly owns 100% of the interests of Parent and Subsidiary, has entered into an Agreement and Plan of Merger, dated as of February 25, 2007 (as amended, supplemented or otherwise modified from time to time, the "Merger Agreement"),
with Texas Energy Future Holdings Limited Partnership ("Texas Energy LP") and Texas Energy Future Merger Sub Corp ("Merger Sub"), pursuant to which Merger Sub, a Texas corporation and wholly-owned subsidiary of Texas Energy LP, will merge with and into TXU Corp. (the "Merger"), with TXU Corp. continuing as the surviving entity and a subsidiary of Texas Energy LP; WHEREAS, consummation of the Merger will effect an indirect transfer of control of the Subsidiary's licenses to operate CPSES from TXU Corp. to Texas Energy LP; and WHEREAS, in connection with the indirect transfer of control of the Subsidiary's licenses to operate CPSES, the Parent and the Subsidiary desire to take certain actions to enhance and maintain the financial condition of the Subsidiary as hereinafter set forth in order to ensure its ability to pay the costs and expenses relating to the operations and maintenance of CPSES; NOW THEREFORE, in consideration of the mutual promises herein contained, the parties hereto agree as follows:
- 1. Support Payments. At all times while this Agreement is in effect and subject to the limitations set forth in paragraphs 3 and 4, the Parent agrees that it will make, or cause one of its subsidiaries or affiliates to make, to the extent necessary, a Support Payment (as defined in paragraph 2) to the Subsidiary in order to ensure that the Subsidiary has sufficient liquidity in order to pay the costs and expenses relating to the operations and maintenance of CPSES. Any Support Payments required by this Agreement shall be made not later than the end of the next fiscal quarter.
- 2. Commitment to Provide Capital. If during the term of this Agreement, the Parent is required to make a Support Payment to the Subsidiary, such payment may be provided by the Support Agreement 051200-0514-10087-NY02 2599053.6
2 Parent, or any subsidiary or affiliate of the Parent, at the Parent's option, either as an equity, investment or capital contribution or as a loan, in each case in cash or other liquid assets (any of the foregoing, a "Support Payment"). If such payment is advanced to the Subsidiary as a loan, the loan shall be on such terms and conditions, including maturity and rate of interest, as the Parent and the Subsidiary shall agree.
- 3. Limitation of the Parent's Support Obligations. Each of the Parent and the Subsidiary agree that the Parent shall not be required to make, or cause its subsidiaries or affiliates to make, Support Payments to the Subsidiary in excess of $250,000,000 in the aggregate.
- 4. Not a Guaranty. This Agreement, its provisions and any actions pursuant hereto by the Parent shall not constitute or be deemed to constitute a direct or indirect guaranty by the Parent of any indebtedness for borrowed money or other obligation or liability of any kind or character whatsoever of the Subsidiary.
- 5. Rights of Participants and Creditors. The obligations of the Parent pursuant to this Agreement are to the Subsidiary only and do not run to and are not enforceable directly by any creditor of the Subsidiary or other entity or person, nor shall this Agreement cause the Parent to be responsible for payment of any obligation of the Subsidiary to any creditor or other entity or person or give rise to any recourse by any creditor or other entity or person to or against the Parent or any of its assets or properties.
- 6. Waivers. Any failure by any party hereto, at any time or times hereafter, to require strict performance by the other party of any provision of this Agreement shall not waive, affect or diminish any right of any party thereafter to demand strict compliance and performance therewith. None of the agreements contained in this Agreement shall be deemed to have been suspended or waived by any party hereto unless such suspension or waiver is in writing.
- 7. Amendments. This Agreement may be amended, modified or terminated at any time by the parties hereto only by a written instrument signed by both the Parent and the Subsidiary.
- 8. Successors. This Agreement shall be binding upon, and shall inure to the benefit of, the parties hereto and their respective successors and assigns, provided that the Subsidiary may not assign, transfer or pledge its rights hereunder without the prior written consent of the Parent. This Agreement is not intended for the benefit of any entity or person other than the parties hereto, and shall not confer or be deemed to confer upon any other such entity or person any benefits, rights or remedies hereunder.
- 9. Governing Law: Severability. This Agreement and all rights and obligations hereunder shall be governed by and construed and enforced in accordance with the laws of the State of New York. Whenever possible, each provision of this Agreement shall be interpreted in such a manner as to be effective and valid under applicable law, but if any provision of this Agreement shall be prohibited by or invalid under applicable law, such provision shall be ineffective only to the extent of such prohibition or invalidity, without invalidating the remainder of such provisions or the remaining provisions of this Agreement.
Support Agreement 051200-0514-10087-NY02.2599053.6
- 10. Notice to NRC. Subsidiary shall take no action to cause Parent, or its successors and assigns, to void, cancel, or modify the commitment to provide capital to Subsidiary as set forth in this Support Agreement or cause Parent to fail to perform or impair its performance under the commitment, or remove or interfere with Subsidiary's ability to draw upon the commitment, without the prior written consent of the Director of the Office of Nuclear Reactor Regulation of the Nuclear Regulatory Commission (NRC). Also, Subsidiary shall inform the NRC in writing any time that it draws upon the commitment to provide capital by obtaining a Support Payment.
IN WITNESS WHEREOF, the parties hereto have caused this Agreement to be executed and delivered by their respective officers thereunto duly authorized as of the day and year first above written.
LUMINANT HOLDING COMPANY LLC, a Delaware limited liability company By:__ _ _ _ _
94a: Sal K. Jo shi Title Authorized Signatory LUMINANT GENERATION COMPANY LLC, a Texas limited liability company By: _____.____
e: ufal K. Joshi thorized Signatory