Entergy Operations, Inc. and Entergy Nuclear Operations, Inc., Nuclear Onsite Property Damage Insurance (10 CFR 50.54(w)(3))
ML13085A401
Person / Time
Site: Palisades, Indian Point, Grand Gulf, Pilgrim, Arkansas Nuclear, River Bend, Vermont Yankee, Waterford, Big Rock Point, FitzPatrick  Entergy icon.png
Issue date: 03/25/2013
From: Mccann J
Entergy Nuclear Operations, Entergy Operations
To:
Document Control Desk, NRC/FSME, Office of Nuclear Material Safety and Safeguards
References
CNRO-2013-00004, ENOC-13-00005
Download: ML13085A401 (12)


Text

Entergy Entergy Operations, Inc.

Entergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, New York 10601 Tel: 914-272-3370 John F. McCann Vice President, Nuclear Safety, Emergency Planning & Licensing CNRO-2013-00004 ENOC-1 3-00005 March 25, 2013 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001

SUBJECT:

Nuclear Onsite Property Damage Insurance [10 CFR 50.54(w)(3)]

Arkansas Nuclear One, Units 1 and 2, Docket Nos. 50-313 & 50-368 Big Rock Point, Docket No. 50-155 Grand Gulf Nuclear Station, Docket No. 50-416 Indian Point Nuclear Generating Units 1, 2, and 3, Docket Nos.50-003, 50-247 & 50-286 James A. FitzPatrick Nuclear Power Plant, Docket No. 50-333 Palisades Nuclear Plant, Docket No. 50-255 Pilgrim Nuclear Power Station, Docket No. 50-293 River Bend Station, Docket No. 50-458 Vermont Yankee Nuclear Power Station, Docket No. 50-271 Waterford 3 Steam Electric Station, Docket No. 50-382

Dear Sir or Madam:

In accordance with 10 CFR 50.54(w)(3), the attached summary is the consolidated Entergy submittal to document the primary and excess property damage insurance coverage for the nuclear sites of Entergy Operations, Inc and Entergy Nuclear Operations, Inc. The insurance certificates that correspond to the policy numbers identified in the attachment will be available in Entergy's Risk Management files following their effective date, April 1, 2013.

This submittal contains no commitments.

Should there be any questions concerning this joint submittal, please contact Anders Eng of our corporate staff at 914-272-3523.

Sincerely, J FM/cdf/aye Attachment (10 pages) cc: Next Page WPoD

CNRO-2013-00004 ENOC-1 3-00005 Page 2 of 2 cc: (All Below w/o Certificates - See Risk Management Files For Certificates)

Mr. J. S. Forbes (ECH)

Mr. M. A. Balduzzi (ECH)

Mr. J. A. Kowalewski (ECH)

Mr. T. G. Mitchell (WPO)

Mr. M. Perito (WPO)

Mr. M. J. Colomb (JAF)

Mr. R. G. Smith (PNPS)

Mr. K. J. Mulligan (GGNS)

Ms. D. Jacobs (WF3)

Mr. J. A. Ventosa (IPEC)

Mr. J. G. Browning (ANO)

Mr. C. J. Wamser (VY)

Mr. E. W. Olsen (RBS)

Mr. A. J. Vitale (PLP)

Mr. L. J. Smith (Wise, Carter)

Mr. W. M. Dean, NRC Regional Administrator, RI Mr. C. Casto, NRC Regional Administrator, RIII Mr. E. E. Collins, NRC Regional Administrator, RIV NRC Project Manager, IPEC NRC Project Manager, PLP NRC Project Manager, PNP NRC Project Manager, BRP NRC Project Manager, ANO NRC Project Manager, WF3 NRC Project Manager, VY NRC Project Manager, JAF NRC Project Manager, RBS NRC Project Manager, GGNS Ms. Bridget Frymire NYS Department of Public Service 3 Empire State Plaza Albany, NY 12223 Mr. Francis J. Murray President NYSERDA 17 Columbia Circle Albany, NY 12203-6399 Mr. Christopher Recchia Commissioner VT Department of Public Service 112 State Street, Drawer 20 Montpelier, VT 15620-2601

CNRO 2013-00004 ENOC-13-00005 Attachment Entergy Operations, Inc. /

Entergy Arkansas, Inc.

Arkansas Nuclear One Nuclear Property Insurance Effective April 1, 2013 The combined amount of Primary, Excess and Blanket Excess Property Insurance totals $1.6 Billion.

Primary:

Policy Period: 4/1/13-14 Insurer: Nuclear Electric Insurance Limited Policy Number: P13-045 Policy Limit: $500 Million Excess:

Policy Period: 4/1/13-14 Insurer: Nuclear Electric Insurance Limited Policy Number: X13-002 Policy Limit: $750 Million Blanket Excess:

Policy Period: 4/1/13-14 Insurer: Nuclear Electric Insurance Limited Policy Number: BX13-001 Policy Limit: $350 Million 1

CNRO 2013-00004 ENOC-1 3-00005 Attachment Entergy Operations, Inc. /

System Energy Resources, Inc. /

South Mississippi Electric Power Association Grand Gulf Nuclear Station Nuclear Property Insurance Effective April 1, 2013 The combined amount of Primary, Excess and Blanket Excess Property Insurance totals $1.6 Billion.

Primary:

Policy Period: 4/1/13-14 Insurer: Nuclear Electric Insurance Limited Policy Number: P13-026 Policy Limit: $500 Million Excess:

Policy Period: 4/1/13-14 Insurer: Nuclear Electric Insurance Limited Policy Number: X13-047 Policy Limit: $750 Million Blanket Excess:

Policy Period: 4/1/13-14 Insurer: Nuclear Electric Insurance Limited Policy Number: BX13-001 Policy Limit: $350 Million 2

CNRO 2013-00004 ENOC-1 3-00005 Attachment Entergy Operations, Inc. /

Entergy Louisiana, LLC Waterford 3 Nuclear Station Nuclear Property Insurance Effective April 1, 2013 The combined amount of Primary, Excess and Blanket Excess Property Insurance totals $1.6 Billion.

Primary:

Policy Period: 4/1/13-14 Insurer: Nuclear Electric Insurance Limited Policy Number: P13-036 Policy Limit: $500 Million Excess:

Policy Period: 4/1/13-14 Insurer: Nuclear Electric Insurance Limited Policy Number: X13-053 Policy Limit: $750 Million Blanket Excess:

Policy Period: 4/1/13-14 Insurer: Nuclear Electric Insurance Limited Policy Number: BX13-001 Policy Limit: $350 Million 3

CNRO 2013-00004 ENOC-13-00005 Attachment Entergy Operations, Inc. /

Entergy Gulf States Louisiana, L.L.C.

River Bend Nuclear Station Nuclear Property Insurance Effective April 1, 2013 The combined amount of Primary, Excess and Blanket Excess Property Insurance totals $1.6 Billion.

Primary:

Policy Period: 4/1/13-14 Insurer: Nuclear Electric Insurance Limited Policy Number: P13-066 Policy Limit: $500 Million Excess:

Policy Period: 4/1/13-14 Insurer: Nuclear Electric Insurance Limited Policy Number: X13-066 Policy Limit: $750 Million Blanket Excess:

Policy Period: 4/1/13-14 Insurer: Nuclear Electric Insurance Limited Policy Number: BX13-001 Policy Limit: $350 Million 4

CNRO 2013-00004 ENOC-13-00005 Attachment Entergy Nuclear Operations, Inc. /

Entergy Nuclear Generation Company Pilgrim Nuclear Station Nuclear Property Insurance Effective April 1, 2013 The combined amount of Primary and Excess Property Insurance totals $1.115 Billion.

Primary:

Policy Period: 4/1/13-14 Insurer: Nuclear Electric Insurance Limited Policy Number: P13-078 Policy Limit: $500 Million Excess:

Policy Period: 4/1/13-14 Insurer: Nuclear Electric Insurance Limited Policy Number: X13-089 Policy Limit: $615 Million 5

CNRO 2013-00004 ENOC-1 3-00005 Attachment Entergy Nuclear Operations, Inc. /

Entergy Nuclear Fitzpatrick, LLC FitzPatrick Nuclear Station Nuclear Property Insurance Effective April 1, 2013 The combined amount of Primary and Excess Property Insurance totals $1.115 Billion.

Primary:

Policy Period: 4/1/13-14 Insurer: Nuclear Electric Insurance Limited Policy Number: P13-092 Policy Limit: $500 Million Excess:

Policy Period: 4/1/13-14 Insurer: Nuclear Electric Insurance Limited Policy Number: X13-092 Policy Limit: $615 Million 6

CNRO 2013-00004 ENOC-1 3-00005 Attachment Entergy Nuclear Operations, Inc. /

Entergy Nuclear Indian Point 2, LLC Entergy Nuclear Indian Point 3, LLC Indian Point Station Units 1, 2 & 3 Nuclear Property Insurance Effective April 1, 2013 The combined amount of Primary and Excess Property Insurance totals $1.115 Billion.

Primary:

Policy Period: 4/1/13-14 Insurer: Nuclear Electric Insurance Limited Policy Number: P13-093 Policy Limit: $500 Million Excess:

Policy Period: 4/1/13-14 Insurer: Nuclear Electric Insurance Limited Policy Number: X13-093 Policy Limit: $615 Million 7

CNRO 2013-00004 ENOC-1 3-00005 Attachment Entergy Nuclear Operations, Inc./

Entergy Nuclear Vermont Yankee, LLC Vermont Yankee Nuclear Station Nuclear Property Insurance Effective April 1, 2013 The combined amount of Primary and Excess Property Insurance totals $1.115 Billion.

Primary:

Policy Period: 4/1/13-14 Insurer: Nuclear Electric Insurance Limited Policy Number: P13-096 Policy Limit: $500 Million Excess:

Policy Period: 4/1/13-14 Insurer: Nuclear Electric Insurance Limited Policy Number: X13-096 Policy Limit: $615 Million 8

CNRO 2013-00004 ENOC-13-00005 Attachment Entergy Nuclear Operations, Inc./

Entergy Nuclear Palisades, LLC Palisades Nuclear Generating Plant Nuclear Property Insurance Effective April 1, 2013 The combined amount of Primary and Excess Property Insurance totals $1.115 Billion.

Primary:

Policy Period: 4/1/13-14 Insurer: Nuclear Electric Insurance Limited Policy Number: P13-110 Policy Limit: $500 Million Excess:

Policy Period: 4/1/13-14 Insurer: Nuclear Electric Insurance Limited Policy Number: X13-110 Policy Limit: $615 Million 9

CNRO 2013-00004 ENOC-1 3-00005 Attachment Entergy Nuclear Operations, Inc./

Entergy Nuclear Palisades, LLC Big Rock Point ISFSI Nuclear Property Insurance Effective April 1, 2013 Primary Property Insurance in the amount of $500 Million.

Primary:

Policy Period: 4/1/13-14 Insurer: Nuclear Electric Insurance Limited Policy Number: P13-109 Policy Limit: $500 Million 10