2CAN111701, Correction to Proposed Revision to Reactor Vessel Surveillance Capsule Withdrawal Schedule

From kanterella
Jump to navigation Jump to search

Correction to Proposed Revision to Reactor Vessel Surveillance Capsule Withdrawal Schedule
ML17305B616
Person / Time
Site: Arkansas Nuclear Entergy icon.png
Issue date: 11/01/2017
From: Pyle S
Entergy Operations
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
2CAN111701
Download: ML17305B616 (2)


Text

Entergy Operations, Inc.

1448 S.R. 333 Russellville, AR 72802 Tel 479-858-4704 Stephenie L. Pyle Manager, Regulatory Assurance Arkansas Nuclear One 2CAN111701 November 1, 2017 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555

SUBJECT:

Correction to Proposed Revision to Reactor Vessel Surveillance Capsule Withdrawal Schedule Arkansas Nuclear One - Unit 2 Docket No. 50-368 License No. NPF-6

REFERENCE:

Entergy letter to NRC, Proposed Revision to Reactor Vessel Surveillance Capsule Withdrawal Schedule, dated September 14, 2017 (2CAN091702)

(ML17257A121)

Dear Sir or Madam:

Via the reference submittal, Entergy Operations, Inc. (Entergy), submitted a request for the NRCs approval of a revision to the Arkansas Nuclear One, Unit 2 (ANO-2) surveillance capsule withdrawal schedule presented in Table 5.2-12 of the Safety Analysis Report. In the description of the change, the Removal Interval for capsule number 4 (W-284) is changed from 30 Effective Full Power Years (EFPY) to the measured interval of 29.94 EFPY.

In a subsequent review of this submittal, Entergy noted that the interval listed in the description of the change did not match the value listed in Table 2 (Proposed Change to Capsule Removal Schedule) of the referenced submittal. In the description it is listed as 29.94 EFPY. Table 2 provides a value of 29.24 EFPY. The value listed in the body of the attachment is in error. The correct value is 29.24 EFPY.

This editorial error has been entered into the ANO Corrective Action program (reference CR-ANO-C-2017-4217). The error does not change the details provided in the reference request nor the conclusions of the request.

The ANO NRR Project Manager has been informed of this editorial error and concurs with the approach taken in this submittal.

This letter contains no new commitments.

2CAN111701 Page 2 of 2 Should you have any questions regarding this submittal, please contact me.

Sincerely, ORIGINAL SIGNED BY DAVID BICE for STEPHENIE L. PYLE SLP/rwc cc: Mr. Kriss Kennedy Regional Administrator U. S. Nuclear Regulatory Commission, Region IV 1600 East Lamar Boulevard Arlington, TX 76011-4511 NRC Senior Resident Inspector Arkansas Nuclear One P.O. Box 310 London, AR 72847 U. S. Nuclear Regulatory Commission Attn: Mr. Thomas Wengert MS O-08B1A One White Flint North 11555 Rockville Pike Rockville, MD 20852