05000454/FIN-2018002-03
From kanterella
Jump to navigation
Jump to search
Finding | |
---|---|
Title | Minor Violation |
Description | Minor Violation: The inspectors identified multiple instances of a failure to perform inservice testing in accordance with written procedures appropriate for the circumstances during this inspection period: 1. On March 30, 2018, the licensee performed 1BOSR 5.5.8.DO2, Test of the Diesel Oil Transfer System, and declared the 1B diesel oil transfer pump inoperable due to flow results being low out of specification. Subsequently, the licensee determined that the instrument setup was incorrect in that an incorrect value was entered into the flow meter for pipe diameter. The licensee declared the surveillance invalid and scheduled a time to re-perform the activity. Acceptable system flow rates were achieved a week later when the correct pipe diameter was used for the instrument setup. 2. On April 26, 2018, while observing the licensee perform 2BOSR 5.5.8.CS.52C, Comprehensive Inservice Testing (IST) Requirements for Containment Spray Pump 1CS01PB, the inspectors noted that the pump suction pressure and discharge pressure test gauges were not installed as described in the Precautions and Limitations section of the procedure. After the inspectors asked how the installed configuration satisfied the procedure requirement, the licensee suspended the test to obtain clarification. After some deliberation between engineers and operators attempting to identify the correct instrument location, the test data was recorded with the instruments at different locations for data gathering and comparison. The licensee verified that pump performance had sufficient margin, including the introduced error, to remain operable and available to perform its safety-related function as expected.3. On May 1, 2018, while observing the licensee perform 2BOSR 5.5.8.SX.51C, Comprehensive Inservice Testing (IST) Requirements for the Essential Service Water (SX) Pump 2SX01PA and Unit 2 SX Pumps Discharge Check Valves, the inspectors noted that operators were not taking data from the ultrasonic flow meter in accordance with the procedure. Specifically, the instrument was not set up to indicate time and flow so that an average flow could be determined as required by a Note in the procedure. Instead the operators were recording instantaneous flowrate. When the inspector asked for clarification and the operators and technicians deferred to their supervisors, the licensee suspended the test to obtain clarification. The test was performed again after the instrument was set up correctly and operators were briefed on how to obtain the correct data.Title 10 CFR Part 50, Appendix B, Criterion V, Instructions, Procedures, and Drawings, requires, in part, that activities affecting quality shall be prescribed by documented instructions of a type appropriate to the circumstances and shall be accomplished in accordance with these instructions. Contrary to the above, for the diesel fuel oil transfer pump surveillance, 1BOSR 5.5.8.DO2, the procedure listed an incorrect pipe diameter value that was subsequently entered into the flow meter resulting in unacceptable test results; for the containment spray pump surveillance, 2BOSR 5.5.8.CS.52C, the licensee potentially introduced an unaccounted for error in the surveillance test method by not setting up test equipment in accordance with the procedure; and for the SX surveillance, 2BOSR 5.5.8.SX.51C, the licensee introduced a potential error in the surveillance test by not determining an average flow rate as discussed in the procedure Note.Screening: The failure to perform inservice testing in accordance with written procedures appropriate for the circumstances was a performance deficiencyin each of the listed 11 examples. The performance deficiency was determined to be minor in each case because the inspectors answered No to all of the more-than-minor screening questions in IMC 0612, Appendix B. The licensee generated the following issue reports (IRs) to document these issues:AR 04121539, Ultrasonic Flow Measurement Installation IssueAR 04122295, PCR [procedure change request] 1/2BOSR 5.5.8.DO1 AR 04131201, Engineering Clarification Needed on ASME Precaution AR 04133585, NRC ID: Potential Concerns With Execution of 2A SX Pump Surveillance Violation: These failures to comply with 10 CFR Part 50, Appendix B, Criterion V, Instructions, Procedures, and Drawings, constituted minor violations that are not subject to enforcement action in accordance with the NRCs Enforcement Policy |
Site: | Byron |
---|---|
Report | IR 05000454/2018002 Section 4OA2 |
Date counted | Jun 30, 2018 (2018Q2) |
Type: | Violation: Severity level Minor |
cornerstone | No Cornerstone |
Identified by: | NRC identified |
Inspection Procedure: | IP 71152 |
Inspectors (proximate) | J Mcghee C Hunt D Betancourt C Thompson E Duncan |
Violation of: | 10 CFR 50 Appendix B 10 CFR 50 Appendix B Criterion V |
INPO aspect | |
' | |
Finding - Byron - IR 05000454/2018002 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Finding List (Byron) @ 2018Q2
Self-Identified List (Byron)
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||