8-22-2016 | At 1005 on June 9, 2016, during routine periodic predictive maintenance thermography activities, the 'A' phase connection to the Unit 1, Train A Safety Chiller was identified to be at an elevated temperature. Inspection found three of the six electrical connections associated with the chiller to be un-torqued. Subsequent investigation found the affected connections should have been torqued on May 10, 2016 as part of restoration actions following planned preventive maintenance. On June 22, 2016 an evaluation was completed that determined the Unit 1, Train A Safety Chiller was inoperable from May 28, 2016 to June 9, 2016.
The cause of this event was the restoration and post work activities by Maintenance personnel did not ensure that the Unit 1, Train A Safety Chiller was properly configured per procedure and ready to be turned over to Operations. Corrective actions included replacing the Phase 'A' cable and dashpot relay and re-torqueing the Phase 'B' and 'C' dashpot relay terminations. The applicable procedure will be revised before the next scheduled performance to have the equipment specific thermography inspection performed as a part of the maintenance restoration/post work activities.
All times in this report are approximate and Central Time unless noted otherwise. |
---|
LER-2016-001, Safety Chiller Inoperable For Longer Than Allowed By Technical SpecificationsComanche Peak |
Event date: |
6-22-2016 |
---|
Report date: |
8-22-2016 |
---|
Reporting criterion: |
10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications |
---|
4452016001R00 - NRC Website |
|
|
---|
Category:Letter
MONTHYEARCP-202400030, License Renewal Application Revision 0 - Supplement 3, Revision 12024-01-31031 January 2024 License Renewal Application Revision 0 - Supplement 3, Revision 1 IR 05000445/20230042024-01-29029 January 2024 Integrated Inspection Report 05000445/2023004 and 05000446/2023004 CP-202400034, (CPNPP) - Core Operating Limits Report (Colr), Unit 2 Cycle 21, (ERX-23-001, Revision 1)2024-01-29029 January 2024 (CPNPP) - Core Operating Limits Report (Colr), Unit 2 Cycle 21, (ERX-23-001, Revision 1) ML24024A2102024-01-29029 January 2024 Summary of Regulatory Audit Regarding a License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors ML24025A0052024-01-25025 January 2024 Review of the Spring 2023 Steam Generator Tube Inspection Report ML24023A0242024-01-24024 January 2024 Correction to Amendment Nos. 185 and 185 Regarding Implementation of Full Spectrum Loss-of-Coolant Accident Methodology ML24018A1072024-01-18018 January 2024 Notification of Commercial Grade Dedication Inspection (05000445/2024012 and 05000446/2024012) and Request for Information ML23159A2082023-12-20020 December 2023 Request for Withholding Information from Public Disclosure ML23319A3872023-12-20020 December 2023 Issuance of Amendment Nos. 185 and 185 Regarding Implementation of Full Spectrum Loss-of-Coolant Accident (Fsloca) Methodology ML23348A2392023-12-19019 December 2023 Nonacceptance of License Amendment Request to Relocate Technical Specification 3.9.3, Nuclear Instrumentation, to the Technical Requirements Manual CP-202300575, (Cpnpp), License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors Supplement 22023-12-13013 December 2023 (Cpnpp), License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors Supplement 2 ML23333A0872023-12-13013 December 2023 Transmittal of Dam Safety Inspection Report - Public CP-202300566, (Cpnpp), Special Report 1-SR-23-001-00, Inoperable Post Accident Monitoring Instrumentation2023-12-12012 December 2023 (Cpnpp), Special Report 1-SR-23-001-00, Inoperable Post Accident Monitoring Instrumentation CP-202300494, License Renewal Application Revision 0, Supplement 32023-12-0606 December 2023 License Renewal Application Revision 0, Supplement 3 ML23313A0732023-12-0606 December 2023 Issuance of Amendment Nos. 184 and 184 Regarding Revision to Technical Specifications to Implement WCAP-17661-P-A, Rev. 1, Improved Roac and CAOC Fq Surveillance Technical Specifications ML23291A4382023-11-30030 November 2023 Notice of Availability of the Draft Plant-Specific Supplement 60, to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Comanche Peak Nuclear Power Plant, Unit Numbers 1 and 2, License Renewal Applica ML23325A0182023-11-30030 November 2023 Schedule Revision for the License Renewal Application Review IR 05000445/20234022023-11-30030 November 2023 NRC Security Inspection Report 05000445/2023402 and 05000446/2023402 CP-202300349, License Amendment Request (Lar) 23-004 Technical Specifications (TS) 3.9.3, Nuclear Instrumentation2023-11-20020 November 2023 License Amendment Request (Lar) 23-004 Technical Specifications (TS) 3.9.3, Nuclear Instrumentation ML23308A0032023-11-17017 November 2023 Letter to R. Nelson, Executive Director; Achp; Re., Comanche Peak Draft Environmental Impact Statement ML23308A0022023-11-17017 November 2023 Letter to M. Wolfe, Executive Director; Shpo; Re., Comanche Peak Draft Environmental Impact Statement ML23317A3002023-11-13013 November 2023 Letter to R. Sylestine, Chairman, Alabama-Coushatta Tribe of Texas Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2972023-11-13013 November 2023 Letter to R. Martin, President, Tonkawa Tribe of Oklahoma Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2872023-11-13013 November 2023 Letter to J. Garza, Chairman, Kickapoo Traditional Tribe of Texas Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2832023-11-13013 November 2023 Letter to D. Dotson, President, Delaware Nation Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2852023-11-13013 November 2023 Letter to E. Martinez, President, Mescalero Apache Tribe Regarding Comanche Peak Draft Environmental Impact Statement ML23306A0302023-11-13013 November 2023 Letter to J. Cernek, Chairman; Coushatta Tribe of Louisiana Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2902023-11-13013 November 2023 Letter to M. Pierite, Chairman, Tunica Biloxi Tribe of Louisiana Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2982023-11-13013 November 2023 Letter to R. Morrow, Town King, Thlopthlocco Tribal Town Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2842023-11-13013 November 2023 Letter to D. Kaskaske, Chairman, Kickapoo Tribe of Oklahoma Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2822023-11-13013 November 2023 Letter to D. Cooper, Chairman, Apache Tribe of Oklahoma Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2962023-11-13013 November 2023 Letter to M. Woommavovah, Chairman, Comanche Nation Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2812023-11-13013 November 2023 Letter to C. Hoskin, Principal Chief, Cherokee Nation; Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2862023-11-13013 November 2023 Letter to J. Bunch, Chief, United Keetoowah Band of Cherokee Indians Regarding Comanche Peak Draft Environmental Impact Statement ML23317A3032023-11-13013 November 2023 Letter to W. Yargee, Chief, Alabama-Quassarte Tribal Town Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2882023-11-13013 November 2023 Letter to L. Johnson, Chief, Seminole Nation of Oklahoma Regarding Comanche Peak Draft Environmental Impact Statement ML23317A3012023-11-13013 November 2023 Letter to S. Yahola, Mekko, Kialegee Tribal Town Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2792023-11-13013 November 2023 Letter to B. Gonzalez, Chairman, Caddo Nation Regarding Comanche Peak Draft Environmental Impact Statement ML23317A3022023-11-13013 November 2023 Letter to T. Parton, President, Wichita and Affiliated Tribes Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2892023-11-13013 November 2023 Letter to L. Spottedbird, Chairman, Kiowa Indian Tribe Regarding Comanche Peak Draft Environmental Impact Statement ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV ML23360A6312023-10-26026 October 2023 FEMA, Submittal of Radiological Emergency Preparedness Final Report for the Comanche Peak Nuclear Power Plant Medical Services Drill Evaluated on August 23, 2023 CP-202300416, Supplemental Information to Facilitate Acceptance of Licensee Amendment Request 23-002, Application Regarding GDC-5 Shared System Requirements2023-10-12012 October 2023 Supplemental Information to Facilitate Acceptance of Licensee Amendment Request 23-002, Application Regarding GDC-5 Shared System Requirements CP-202300432, Response to Request for Additional Information Regarding the Safety Review of the License Renewal Application - Set 42023-10-0404 October 2023 Response to Request for Additional Information Regarding the Safety Review of the License Renewal Application - Set 4 ML23237B4222023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Letter Regarding Order Approving Transfer of Licenses and Draft Conforming License Amendments ML23263A0242023-09-21021 September 2023 Revision of Schedule for the Environmental Review of the Comanche Peak Nuclear Power Plant Units 1 and 2 License Renewal Application 2024-01-31
[Table view] Category:Licensee Event Report (LER)
MONTHYEARCP-201900411, Special Report 1-SR-19-001-00, Inoperable Loose Parts Monitoring System2019-06-27027 June 2019 Special Report 1-SR-19-001-00, Inoperable Loose Parts Monitoring System 05000446/LER-2017-0032018-01-22022 January 2018 Manual Reactor Trip due to trip of both Main Feedwater Pumps, LER 17-003-00 for Comanche Peak, Unit 2, Regarding Manual Reactor Trip Due to Trip of Both Main Feedwater Pumps 05000446/LER-2017-0012017-10-0505 October 2017 Auxiliary Feedwater System Actuation During Unit 2 Turbine Trip, LER 17-001-00 for Comanche Peak Nuclear Power Plant Regarding Auxiliary Feedwater System Actuation During Unit 2 Turbine Trip 05000445/LER-2016-0022017-02-22022 February 2017 Unanalyzed Condition Involving Potential Moderate Energy Line Break, LER 16-002-01 for Comanche Peak Nuclear Power Plant, Units 1 & 2 Regarding Unanalyzed Condition Involving Potential Moderate Energy Line Break 05000445/LER-2016-0012016-08-22022 August 2016 Safety Chiller Inoperable For Longer Than Allowed By Technical Specifications, LER 16-001-00 for Comanche Peak Nuclear Power Plant, Unit 1, Regarding Safety Chiller Inoperable For Longer Than Allowed By Technical Specifications 2019-06-27
[Table view] |
comments regarding burden estimate to the FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by e-mail to used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.
05000- NUMBER NO.
., 001 00 Comanche Peak 445 16 -
I. DESCRIPTION OF THE REPORTABLE EVENT
A. REPORTABLE EVENT CLASSIFICATION
10CFR50.73(a)(2)(i)(B) "Any operation or condition which was prohibited by the plant's Technical Specifications" as a result of the Unit 1, Train A Safety Chiller exceeding its LCO completion times, for entering Mode 4 with an inoperable chiller, and for subsequently entering Modes 3, 2, and 1 with an inoperable safety chiller in violation of Technical Specification (TS) 3.7.19.
B. PLANT CONDITION PRIOR TO EVENT
On June 22, 2016, Comanche Peak Nuclear Power Plant (CPNPP) Unit 1 was operating in Mode 1, at or near 100% power.
C. STATUS OF STRUCTURES, SYSTEMS, OR COMPONENTS THAT WERE
INOPERABLE AT THE START OF THE EVENT AND THAT CONTRIBUTED TO THE EVENT
There were no structures, systems, or components that were inoperable at the start of the event that contributed to the event.
D. NARRATIVE SUMMARY OF THE EVENT, INCLUDING DATES AND APPROXIMATE TIMES
On May 10, 2016, during a Unit 1 refueling outage Maintenance personnel (Utility, Non-Licensed) completed dashpot overload relay testing and re-installed the relays into the Unit 1, Train A Safety Chiller Motor Starter Panel [El IS:(KM) (CHU)(DPT)(MSTR)]. The Maintenance personnel then re-terminated the Phase A, B, and C upper and lower cables to their respective dashpot overload relays, and should have torqued the bolted connections in accordance with the applicable Maintenance procedure.
On May 15, 2016, at 1625 the Unit 1, Train A Safety Chiller Technical Specification acceptance criteria was satisfactorily met and approved by the U1 Supervisor (Utility, Licensed) and the chiller was declared operable.
On May 28, 2016 at 0330 Unit 1 entered Mode 4, and per TS 3.7.19 the Unit 1, Train A Safety Chiller was required to be operable.
On June 9, 2016, at 1005 it was discovered during the performance of routine periodic predictive maintenance thermography by Engineering personnel (Utility, Non-Licensed) on the Unit 1, Train A Safety Chiller Motor Starter Panel that the Phase 'A' cable termination on the dashpot overcurrent relay had a significantly higher temperature reading than expected (950°F as opposed to a typical reading of about 90°F). The Unit 1, Train A Safety Chiller was shut down per the direction of the Shift Manager (Utility, Licensed) and the chiller was declared inoperable.
comments regarding burden estimate to the FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by e-mail to used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.
05000- NUMBER NO.
_001 00 Comanche Peak 445 16 - On June 22, 2016, an evaluation was completed that determined the Unit 1, Train A Safety Chiller had been inoperable from May 28, 2016 to June 9, 2016.
E. THE METHOD OF DISCOVERY OF EACH COMPONENT OR SYSTEM FAILURE, OR PROCEDURAL PERSONNEL
ERROR
During routine periodic predictive maintenance thermography activities, Engineering personnel (Utility, Non-Licensed) identified that the 'A' phase connection to the Unit 1, Train A Safety Chiller was at an elevated temperature.
II. COMPONENT OR SYSTEM FAILURES
A. CAUSE OF EACH COMPONENT OR SYSTEM FAILURE
Not Applicable — No other component or system failures were identified that contributed to this event.
B. FAILURE MODE, MECHANISM, AND EFFECTS OF EACH FAILED COMPONENT
Not Applicable — No component or system failures were identified during this event.
C. SYSTEMS OR SECONDARY FUNCTIONS THAT WERE AFFECTED BY FAILURE OF COMPONENTS WITH
MULTIPLE FUNCTIONS
Not Applicable — No component or system failures were identified during this event.
D. FAILED COMPONENT INFORMATION
Not Applicable — No component or system failures were identified during this event.
III. ANALYSIS OF THE EVENT
A. SAFETY SYSTEM RESPONSES THAT OCCURRED
Not Applicable — No safety system responses occurred as a result of this event.
B. DURATION OF SAFETY SYSTEM TRAIN INOPERABILITY
The Unit 1, Train A Safety Chiller was inoperable per Technical Specification 3.17.9 from May 28, 2016 to June 9, 2016 (approximately 222.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br />).
comments regarding burden estimate to the FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by e-mail to used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.
05000- NUMBER NO.
001 00 Comanche Peak 445 16 _ -
C. SAFETY CONSEQUENCES AND IMPLICATIONS OF THE EVENT
The Unit 1, Train A Safety Chiller was inoperable per Technical Specification 3.17.9 from May 28, 2016 to June 9, 2016.
During that time, the Unit 1, Train A Safety Chiller ran without any indication of abnormal performance or degraded function and the Train B Safety Chilled Water System was operable.
The safety significance of the identified condition is low, since the Train B Safety Chiller cooling function remained available during the subject period from May 28, 2016 to June 9, 2016, and no interim actions were required during the planned evolutions to reduce the effect on nuclear safety.
A probabilistic risk assessment of the inoperability of the Unit 1, Train A Safety Chiller found a non-risk significant effect on core damage frequency and large early release frequency. Based on the above considerations, this event had very low safety significance and there was no adverse effect on plant safety or on the health and safety of the public.
IV. CAUSE OF THE EVENT
The cause of this event was the restoration and post work activities by Maintenance personnel during a Unit 1 refueling outage did not ensure that the Unit 1, Train A Safety Chiller was properly configured per procedure and ready to be turned over to Operations. The improper torque resulted in one of the terminations experiencing significantly elevated temperatures once the equipment was returned to service and resulted in the Unit 1, Train A Safety Chiller being declared inoperable. Procedures and work practices contributed to this event. The Maintenance workers inadequately performed a procedure step directly after the termination torque performances directing them to ensure there were no loose electrical connections in the panel. The Maintenance procedure also currently only provides one sign-off step for the performance of six QIV termination torques. There were no training, communication, supervision, human-system interface, fitness for duty, or time/situational pressures associated with this event.
V. CORRECTIVE ACTIONS
The other three Safety Chillers were verified to have no thermal abnormalities. The Phase 'A' cable and dashpot relay were replaced and the Phase 'B' and 'C' dashpot relay terminations were retorqured. The applicable Maintenance procedure will be revised before the next scheduled performance to have the equipment specific thermography inspection performed as a part of the maintenance restoration/post work activities so that an improper torque will be identified and corrected before the equipment is turned over to Operations. The applicable Maintenance procedure will also be revised to include six component verification sign-off steps to verify each of the three line side and three load side terminations are torqued.
VI. PREVIOUS SIMILAR EVENTS
than allowed by Technical Specifications. However, the cause of the 2014 event was due to a different cause than this event.