Title | Failure to the Update the Final Safety Analysis Report after the Extended Power Uprate |
Description | The inspectors identified a non-cited violation with three examples for the licensees failure to update the Updated Final Safety Analysis Report in accordance with 10 CFR Part 50.71(e). Specifically, the licensee failed to update the Grand Gulf Nuclear Station Updated Final Safety Analysis Report, Section 15.2.2.2.2.1, Generator Load Rejection with Bypass, to appropriately reflect the anticipated plant response to a full load reject after the completion of the extended power uprate. Additionally, the inspectors determined that the licensee did not adequately describe the extended power uprate changes in the Updated Final Safety Analysis Report Chapters 11 (Radioactive Waste Management) and 12 (Radiation Protection) and submit an update to the NRC. The licensee documented this issue in Condition Reports CR-GGN-2015-00892, CR-GGN-2015-01607, and CR-GGN-2015-01610. The licensees failure to update the Updated Final Safety Analysis Report in a timely manner is a performance deficiency. This performance deficiency was evaluated using traditional enforcement because it has the potential to impact the NRCs ability to perform its regulatory function. The inspectors used the NRC Enforcement Policy to evaluate the significance of this violation. Consistent with Section 6.1.d.3 of the NRC Enforcement Policy, the inspectors determined that the performance deficiency is a Severity Level IV non-cited violation because the lack of up-to-date information in the Updated Final Safety Analysis Report has not resulted in any unacceptable change to the facility or procedures. This non-cited violation has no cross-cutting aspect because there was no finding associated with this traditional enforcement violation. |
Site: | Grand Gulf |
---|---|
Report | IR 05000416/2015002 Section 4OA3 |
Date counted | Jun 30, 2015 (2015Q2) |
Type: | TEV: Severity level IV |
cornerstone | Initiating Events |
Identified by: | NRC identified |
Inspection Procedure: | IP 71153 |
Inspectors (proximate) | N Taylor R Alexander G Warnick J Mateychick L Carson M Schwieg M Young N Day |
Violation of: | 10 CFR 50.71(e) 10 CFR 50.71 |
INPO aspect | |
' | |