Finding | |
---|---|
Title | Failure to Obtain NRC Approval for a Change in Method of Evaluation for Determining Reactor Vessel Fluence |
Description | The team identified a Severity Level IV non-cited violation of 10 CFR 50.59, Changes, Tests, and Experiments, involving the licensees failure to obtain a license amendment pursuant to 10 CFR 50.90 prior to implementing a new method of evaluation for determining reactor vessel neutron fluence. On November 4, 2003, the NRC issued Amendment Number 160 to the Facility Operating License of the Grand Gulf Nuclear Station. The amendment revised the Updated Final Safety Analysis Report (UFSAR) to change the Reactor Vessel Material Surveillance Program to reflect participation in the Boiling Water Reactor Vessel and Internals Project (BWRVIP) Integrated Surveillance Program (ISP). Additionally, the amendment revised the UFSAR to state that neutron fluence calculations performed after 2002 will be in accordance a methodology that has been approved by the NRC staff and is consistent with the attributes identified in NRC Regulatory Guide 1.190, Calculation and Dosimetry Methods for Determining Pressure Vessel Neutron Fluence. The licensee developed a new neutron fluence calculation method which was based on a neutron fluence calculation method that had been previously approved by the NRC for another facility, which was documented in Nine Mile Point Nuclear Station, Unit No. 1 Issuance of Amendment RE: Pressure-Temperature Limit Curves and Tables, dated October 27, 2003. The NRC identified that the calculation, which was developed for GGNS, used the CASMO-4/SIMULATE code package to calculate the neutron source, whereas the prior calculation performed for Nine Mile Point Nuclear Station (NMP) used the ORIGEN code to calculate the neutron source. The inspectors determined that, although these codes are intended for the same purpose, they are distinct codes and the NRC approved only the use of one neutron source code (i.e., ORIGEN) in the neutron fluence calculation method of evaluation at Nine Mile Point. This finding was entered into the licensees corrective action program as Condition Report CR-GGN-2013-04743. The licensees failure to determine that a change to their method of evaluation for calculating reactor vessel neutron fluence was a departure from a method of evaluation approved by the NRC and required NRC review and approval prior to implementation was a performance deficiency. The performance deficiency was evaluated using traditional enforcement because the finding had the ability to impact the regulatory process. The performance deficiency was more than minor because there was a reasonable likelihood that the change would require NRC review and approval prior to implementation. In accordance with the NRC Enforcement Manual, risk insights from Inspection Manual Chapter 0609, Significance Determination Process, are used in determining the significance of 10 CFR 50.59 violations. Using the Inspection Manual Chapter 0612, Appendix B, Issue Screening, the team determined the finding adversely affected the Barrier Integrity Cornerstone. Using Inspection Manual Chapter 0609, Appendix A, The Significance Determination Process (SDP) for Findings At-Power, the team determined the finding required a detailed risk evaluation because the finding involved the reactor coolant system boundary. A Senior Reactor Analyst performed the evaluation and determined the finding had very low safety significance (i.e., Green) because the NRC performed calculations and did not determine that the licensees Pressure-Temperature limits had or would have expired or been invalid; therefore, the change in risk was negligible. Since the finding had very low safety significance, the finding was determined to be Severity Level IV, in accordance with the NRC Enforcement Policy. The finding does not have a cross-cutting aspect because cross-cutting aspects are not assigned to traditional enforcement violations. |
Site: | Grand Gulf |
---|---|
Report | IR 05000416/2013004 Section 1R17 |
Date counted | Sep 30, 2013 (2013Q3) |
Type: | TEV: Severity level IV |
cornerstone | Barrier Integrity |
Identified by: | NRC identified |
Inspection Procedure: | IP 71111.17 |
Inspectors (proximate) | J O'Donnell L Carson L Ricketson N Greene N Okonkwo P Elkmann R Kahler R Smith A Allen B Cecere B Rice G Guerra G Pick J Braisted |
Violation of: | 10 CFR 50.59 10 CFR 50.90 |
INPO aspect | |
' | |
Finding - Grand Gulf - IR 05000416/2013004 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Finding List (Grand Gulf) @ 2013Q3