05-18-2016 | Reactor coolant system pressure boundary leakage was identified by a drywell leak inspection team during a planned shutdown for a Unit 1 refueling outage. This event resulted in a plant shutdown required by Technical Specifications. The Unit 1 'A' RHR Shutdown Cooling Return Check Valve equalizing line developed a crack at the toe of a weld due to high cyclic fatigue induced by vibration from the reactor recirculation system. The Unit 1 welds were reworked to EPRI 2x1 at select locations on the "A" and "B" RHR Shutdown Cooling Return check valve equalizing lines for HV-051-1F050A and 50B. The similar Unit 2 welds on equalizing lines for HV-051-2F050A and 50B will be examined and reinforced. The scope will be added into the next refueling outage (2R14) currently scheduled for April 2017. |
---|
|
---|
Category:Letter
MONTHYEARIR 05000352/20243012024-02-0202 February 2024 Initial Operator Licensing Examination Report 05000352/2024301 and 05000353/2024301 IR 05000352/20230042024-01-31031 January 2024 Integrated Inspection Report 05000352/2023004 and 05000353/2023004 IR 05000352/20240112024-01-31031 January 2024 Information Request to Support Post-Approval Site Inspection for License Renewal; Inspection Report 05000352/2024011 ML24026A2962024-01-26026 January 2024 Supplement to License Amendment Request to Revise the Licensing and Design Basis to Incorporate the Replacement of Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection System (PPS)- Syrs, . ML24004A0342024-01-17017 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0026 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000352/20230102024-01-11011 January 2024 Age-Related Degradation Report 05000352/2023010 and 05000353/2023010 IR 05000352/20234012023-12-21021 December 2023 Cybersecurity Inspection Report 05000352/2023401 and 05000353/2023401 ML23321A2362023-12-14014 December 2023 Issuance of Amendment Nos. 262 and 224 Adoption of TSTF-477, Revision 3 and Associated Technical Specification Changes ML23278A1292023-12-14014 December 2023 Units 1 & 2; Limerick, Units 1 & 2; Nine Mile Point, Units 1 & 2; and Peach Bottom, Units 2 & 3 -Revision to Approved Alternatives to Use Boiling Water Reactor Vessel and Internals Project Guidelines ML23333A2182023-11-29029 November 2023 Operator Licensing Examination Approval ML23325A2062023-11-21021 November 2023 Supplement to License Amendment Request to Revise the Licensing and Design Basis to Incorporate the Replacement of Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection System ML23313A0432023-11-13013 November 2023 Summary of Regulatory Audit in Support of Amendment Request for Control Room Air Conditioning Technical Specifications ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums IR 05000352/20230032023-10-27027 October 2023 Integrated Inspection Report 05000352/2023003 and 05000353/2023003 and Independent Spent Fuel Storage Installation Inspection 07200065/2023001 ML23297A1722023-10-24024 October 2023 Request for Information for a Biennial Problem Identification and Resolution Inspection; Inspection Report 05000352/2024010 and 05000353/2024010 IR 05000352/20235012023-10-17017 October 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000352/2023501 and 05000353/2023501 RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans ML23279A0612023-10-0505 October 2023 Paragon Energy Solutions LLC, Part 21 Final Report Re Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) ML23276A5162023-10-0303 October 2023 Federal Emergency Management Agency Level 1 Finding from 2023 Evaluated Emergency Preparedness Exercise ML23275A1082023-09-29029 September 2023 FEMA Level 1 Findings Limerick NPP- Boyertown/Colebrookdale ML23241A9452023-09-27027 September 2023 Generation Station, Units 1 and 2 Regulatory Audit Plan Supporting Review of the Equipment Qualification Portion of Limerick Digital Instrumentation and Controls License Amendment Request ML23269A0522023-09-26026 September 2023 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000352/2023010 and 05000353/2023010 ML23255A0952023-09-12012 September 2023 Resubmittal of License Amendment Request to Revise the Licensing and Design Basis to Incorporate the Replacement of Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection System (PPS) to Address ML23254A0242023-09-0606 September 2023 Paragon Energy Solutions LLC, Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) ML23249A1002023-09-0606 September 2023 Requalification Program Inspection IR 05000352/20230052023-08-31031 August 2023 Updated Inspection Plan for Limerick Generating Station, Units 1 and 2 (Report 05000352/2023005 and 05000353/2023005) ML23248A2082023-08-31031 August 2023 UFSAR Cover Page ML23242A2172023-08-30030 August 2023 Response to Request for Additional Information for Application to Adopt TSTF-477, Revision 3, Add Action for Two Inoperable Control Room AC Subsystems and Associated Technical Specification Changes NMP2L2851, Relief Request Associated with Successive Inspections for Generic Letter 88-01 / BWRVIP-75-A Augmented Examinations2023-08-25025 August 2023 Relief Request Associated with Successive Inspections for Generic Letter 88-01 / BWRVIP-75-A Augmented Examinations ML23228A0942023-08-16016 August 2023 Response to Request for Additional Information for Supplemental License Amendment Request to Revise Technical Specifications and Exemption Request from Requirements of 10CFR50.62 ATWS Rule to Support the . IR 05000352/20230022023-08-14014 August 2023 Integrated Inspection Report 05000352/2023002 and 05000353/2023002 ML23220A0182023-08-0808 August 2023 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000352/2023401 and 05000353/2023401 RS-23-087, Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor2023-08-0404 August 2023 Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor ML23212B2362023-07-31031 July 2023 Supplement to License Amendment Request to Revise the Licensing and Design Basis to Incorporate the Replacement of Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection System - WEC Documents ML23212B1052023-07-31031 July 2023 Supplement to License Amendment Request to Revise Technical Specifications and Exemption Request from Requirements of 10CFR50.62 ATWS Rule to Support the Digital Modernization Project Installation - Revise ML23202A2192023-07-21021 July 2023 Response to Request for Additional Information for Supplemental License Amendment Request to Revise Technical Specifications and Exemption Request from Requirements of 10CFR50.62 ATWS Rule to Support the . ML23193B0122023-07-20020 July 2023 Audit Plan in Support of Review of License Amendment Request and Exemption Request for Digital Instrumentation and Controls Installation Support (Epids L-2023-LLA-0025 and L-2023-LLE-0005) ML23187A0962023-07-19019 July 2023 Generation Station, Unit Nos. 1 and 2 - Revised Estimated Review Completion Date Concerning License Amendment Request to Replace Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection System ML23208A1522023-07-0606 July 2023 PEMA Letter Dated 7-6-23 Re Limerick Exercise 9-26-23 ML23177A2242023-06-26026 June 2023 Supplement to License Amendment Request to Revise the Licensing and Design Basis to Incorporate the Replacement of Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection . ML23145A1972023-06-23023 June 2023 Correction to the Renewed Facility Operating License Pages in Amendment Nos. 255, 256, 257, 258, 259, and 260 2024-02-02
[Table view] Category:Licensee Event Report (LER)
MONTHYEAR05000352/LER-2017-0012017-01-27027 January 2017 Condition Prohibited by TS due to Parts Quality Issue, LER 17-001-00 for Limerick Generating Station, Units 1 and 2 Regarding Condition Prohibited by TS due to Parts Quality Issue 05000353/LER-2016-0012016-07-27027 July 2016 Manual Actuation of the Reactor Protection System When Critical Due to Wiring Design Error, LER 16-001-00 for Limerick, Unit 2 Regarding Manual Actuation of the Reactor Protection System When Critical Due to Wiring Design Error 05000352/LER-2016-0032016-05-18018 May 2016 Plant Shutdown Required by Technical Specification Due to a Pressure Boundary Leak, LER 16-003-00 for Limerick, Unit 1, Regarding Plant Shutdown Required by Technical Specification Due to a Pressure Boundary Leak 05000352/LER-2016-0022016-04-11011 April 2016 Condition Prohibited by Technical Specifications Due to Inoperable Safeguard Batteries During Cell Replacements, LER 16-002-00 for Limerick, Unit 1 & 2, Regarding Condition Prohibited by Technical Specifications Due to Inoperable Safeguard Batteries During Cell Replacements 05000352/LER-2016-0012016-03-23023 March 2016 Inoperable Reactor Enclosure Secondary Containment Integrity Due to Open Airlock, LER 16-001-00 for Limerick, Unit 1, Regarding Condition That Could Have Prevented Fulfillment of the Reactor Enclosure Secondary Containment Integrity Safety Function 2017-01-27
[Table view] |
Reported lessons learned are incorporated into the licensing process and fed back to industry.
Send comments regarding burden estimate to the FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by intemet e-mail to Infocollects.Resource@nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0104), Office of Management and Budget, Washington, DC 20503. If a means used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.
2. DOCKET
Unit Conditions Prior to the Event Unit 1 was in Operational Condition (OPCON) 1 (Power Operation) at approximately 14.5 percent power performing a planned Unit 1 shutdown to support a refueling outage. There were no structures, systems or components out of service that contributed to this event.
Description of the Event
On Sunday March 20, 2016, Limerick Unit 1 was operating at 14.5 percent power performing a planned Unit 1 shutdown to support a refueling outage (1R16). At 2154 hours0.0249 days <br />0.598 hours <br />0.00356 weeks <br />8.19597e-4 months <br />, the drywell leak inspection team identified a 0.5 gpm pressure boundary leak on the shutdown cooling (BO:EllS) testable check valve (ISV:EllS) equalizing line. The control room supervisor (CRS) entered Technical Specification (TS) 3.4.3.2 Reactor Coolant System - Operational Leakage Action "a" which requires being in at least Hot Shutdown within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> and Cold Shutdown within the next 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. The 12 hour1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> Hot Shutdown TS Action was met at 0133 hours0.00154 days <br />0.0369 hours <br />2.199074e-4 weeks <br />5.06065e-5 months <br /> and the 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Cold Shutdown Action was met at 1401 hours0.0162 days <br />0.389 hours <br />0.00232 weeks <br />5.330805e-4 months <br />.
An investigation determined that Unit 1 Unidentified Leakage increased from 0.03 gpm to 0.06 gpm between January 16, 2016 and January 18, 2016. Leakage increased to 0.24 gpm on January 19, 2016 and continued to vary with reactor recirculation pump speed for the remainder of the cycle. The maximum leakage recorded was 1.2 gpm which stabilized at 1.0 gpm following power reduction to 95 percent. On March 20, 2016 Maintenance Technicians performed a planned drywell entry at 14.5 percent power and identified a leak on the 3/4 inch reactor side equalizing line of the 1A Shutdown Cooling (SDC) Return Line Inboard Testable Check Primary Containment Isolation Valve, HV-051-1F050A. The leak was located approximately 1/4 inch from the valve body weld and was determined to be pressure boundary leakage.
A 4-hour ENS (#51809) was completed at 2351 hours0.0272 days <br />0.653 hours <br />0.00389 weeks <br />8.945555e-4 months <br /> as required by 10CFR50.72(b)(2)(i) for the initiation of a plant shutdown required by TS. The ENS also reported an event that resulted in the condition of the plant principal safety barriers being seriously degraded per 10CFR50.72(b)(3)(ii). Therefore, this LER is being submitted pursuant to the requirements of 10CFR50.73(a)(2)(i)(A) and 10CFR50.73(a)(2)(ii)(A).
Analysis of the Event
There was no actual safety consequence associated with this event. The potential safety consequences of this event were minimal. The Unidentified Leakage remained a small fraction of the 5 gpm TS 3.4.3.2 LCO. HPCI was unavailable less than 29 minutes due to testing and RCIC was unavailable for less than 13 hours1.50463e-4 days <br />0.00361 hours <br />2.149471e-5 weeks <br />4.9465e-6 months <br /> due to maintenance and testing during the three month period (January, February and March of 2016) of elevated drywell leakage. HPCI is designed to prevent the actuation of the automatic depressurization system (ADS) and ensure that the reactor core remains covered in the event of a small pipe break size of one-inch diameter or less.
The SDC return is a 12-inch diameter line equipped with an outboard motor operated valve (MOV) primary containment isolation valve (PCIV) and an inboard testable check valve PCIV.
The testable check valve has a bypass line that is equipped with an air operated valve (AOV) PCIV which is used to equalize the differential pressure across the testable check valve disc when the valve is opened during stroke testing. Testable check valves are also used in similar applications on low pressure coolant injection (LPCI) and core spray (CS) injection lines. The SDC valve is subject to vibration induced high cycle fatigue due to recirculation pump flow induced vibration. The LPCI and CS injection lines' socket welds are not subject to vibration induced high cycle fatigue.
The affected section of bypass line piping was replaced with a new socket weld with a 2x1 weld to improve pipe stability and minimize stresses at the toe as a result of the 2x1 weld configuration. A 2x1 weld was also applied at the similar valve body socket welds for the HV- 051-1F050A residual heat removal (RHR) side and HV-051-1F050B RHR and reactor side welds.
Cause of the Event
The Unit 1 `A' RHR Shutdown Cooling Return Check Valve equalizing line developed a crack at the toe of the weld due to high cyclic fatigue induced by vibration from the reactor recirculation system (Apparent Cause).
Corrective Action Completed The Unit 1 welds were reworked to EPRI 2x1 at select locations on the "A" and "B" RHR Shutdown Cooling Return check valve equalizing lines for HV-051-1F050A and 50B.
Corrective Action Planned The similar Unit 2 welds on equalizing lines for HV-051-2F050A and 50B will be examined and reinforced. The scope will be added into the next refueling outage (2R14) currently scheduled for April 2017.
Previous Similar Occurrences There were no previous similar occurrences of pressure boundary leakage in the past 5 years.
Component data:
System BO RHR/Low Pressure Coolant Injection System Component ISV Valve, Isolation Component number HV-051-1F050A Manufacturer A585 Weir Valves & Controls USA Inc.
Model number 50301-A Serial Number 2-50301-A
|
---|
|
|
| | Reporting criterion |
---|
05000353/LER-2016-001 | Manual Actuation of the Reactor Protection System When Critical Due to Wiring Design Error LER 16-001-00 for Limerick, Unit 2 Regarding Manual Actuation of the Reactor Protection System When Critical Due to Wiring Design Error | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000352/LER-2016-001 | Inoperable Reactor Enclosure Secondary Containment Integrity Due to Open Airlock LER 16-001-00 for Limerick, Unit 1, Regarding Condition That Could Have Prevented Fulfillment of the Reactor Enclosure Secondary Containment Integrity Safety Function | 10 CFR 50.73(a)(2)(v)(C), Loss of Safety Function - Release of Radioactive Material | 05000352/LER-2016-002 | Condition Prohibited by Technical Specifications Due to Inoperable Safeguard Batteries During Cell Replacements LER 16-002-00 for Limerick, Unit 1 & 2, Regarding Condition Prohibited by Technical Specifications Due to Inoperable Safeguard Batteries During Cell Replacements | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000352/LER-2016-003 | Plant Shutdown Required by Technical Specification Due to a Pressure Boundary Leak LER 16-003-00 for Limerick, Unit 1, Regarding Plant Shutdown Required by Technical Specification Due to a Pressure Boundary Leak | 10 CFR 50.73(a)(2)(ii)(A), Seriously Degraded 10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown |
|