04-08-2016 | On 02/11/16, Unit 1 fuel movement activities were restarted after repairs to the main grapple camera. A refueling interlock of the main grapple was encountered while moving a double blade guide, caused by the disconnection of 20 Rod Position Information System ( RPIS) Position Indicating Probes ( PIPs). The operating crew began troubleshooting and determined that bypassing the RPIS probe "full-in" would clear the interlock. However the crew used a section of the site specific procedure for control rod withdrawal during refuel that wasn't applicable at the time.
The RPIS indications were bypassed and the movement of the double blade guide was recommenced at 12:00 followed by fuel movement. After a review of Technical Specifications 3.9.4, it was determined that fuel movement should not be performed with the RPIS probe disconnected and bypassed because the associated control rods were not disarmed with a tagout. Fuel movement activities were then halted. |
---|
Similar Documents at Hatch |
---|
Category:Letter
MONTHYEARIR 05000321/20230042024-01-31031 January 2024 Integrated Inspection Report 05000321/2023004 and 05000366/2023004 NL-24-0014, Revised Response to Request for Additional Information Regarding License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical.2024-01-30030 January 2024 Revised Response to Request for Additional Information Regarding License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical. ML24012A0652024-01-30030 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting) IR 05000321/20233012024-01-17017 January 2024 NRC Operator License Examination Report 05000321/2023301 and 05000366/2023301 ML23341A2042024-01-12012 January 2024 Request for Additional Information Exemption Requests for Physical Barriers (EPID L-2023-LLE-0018 & L-2023-LLE-0021) ML23345A1312024-01-0303 January 2024 Withholding Letter - SNC Fleet - Physical Barriers Exemption (L-2023-LLE-0018 and L-2023-LLE-0021) NL-23-0889, Units 1 and 2 - License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times for Residual Heat Removal Service Water (RHRSW) and Plant Service Water (Psw) Systems2023-12-0606 December 2023 Units 1 and 2 - License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times for Residual Heat Removal Service Water (RHRSW) and Plant Service Water (Psw) Systems IR 05000321/20234022023-11-29029 November 2023 Security Baseline Inspection Report 05000321/2023402, 05000366/2023402, and 07200036/2023401 NL-23-0879, Request for Exemption from Security Event Notification Implementation2023-11-29029 November 2023 Request for Exemption from Security Event Notification Implementation NL-23-0841, Update to Notice of Intent to Pursue Subsequent License Renewal2023-11-20020 November 2023 Update to Notice of Intent to Pursue Subsequent License Renewal IR 05000321/20230112023-11-17017 November 2023 Biennial Problem Identification and Resolution Inspection Report 050003212023011 and 050003662023011 ML23324A4472023-11-14014 November 2023 302 Exam Approval Letter IR 05000321/20230032023-11-0202 November 2023 Integrated Inspection Report 05000321/2023003, and 05000366/2023003 IR 05000321/20234032023-10-26026 October 2023 Cyber Security Inspection Report 05000321/2023403 and 05000366/2023403 IR 05000321/20234012023-10-17017 October 2023 Security Baseline Inspection Report 05000321 2023401 and 05000366 2023401 ML23250A0472023-09-20020 September 2023 Request for Additional Information Regarding License Amendment Request to Relax Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Bolts in Technical Specifications Table 1.1-1, Modes ML23241B0212023-09-12012 September 2023 Review of Quality Assurance Topical Report IR 05000321/20230052023-08-27027 August 2023 Updated Inspection Plan for Edwin I. Hatch Nuclear Plant, Units 1 & 2 - Report 05000321/2023005 and 05000366/2023005 NL-23-0658, Southern Nuclear Operating Company - Response to Request for Additional Information Regarding Quality Assurance Topical Report Submittal2023-08-11011 August 2023 Southern Nuclear Operating Company - Response to Request for Additional Information Regarding Quality Assurance Topical Report Submittal NL-23-0542, CFR 50.46 ECCS Evaluation Model Annual Report for 20222023-08-0909 August 2023 CFR 50.46 ECCS Evaluation Model Annual Report for 2022 IR 05000321/20230022023-08-0808 August 2023 Integrated Inspection Report 07200036/2023001, 05000321/2023002, and 05000366/2023002 NL-23-0624, Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis2023-08-0404 August 2023 Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis ML23202A1122023-08-0202 August 2023 Units, 1 and 2; and Vogtle Units 1 and 2 - Request to Use a Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML23201A0292023-07-20020 July 2023 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection NL-23-0566, ISFSI and Edwin I. Hatch Nuclear Plant ISFSI - Registration of Spent Fuel Cask Use2023-07-13013 July 2023 ISFSI and Edwin I. Hatch Nuclear Plant ISFSI - Registration of Spent Fuel Cask Use NL-23-0555, Request for Exemption from Physical Barrier Requirement2023-07-0707 July 2023 Request for Exemption from Physical Barrier Requirement ML23178A0012023-06-27027 June 2023 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000321 2023403 and 05000366 2023403 NL-23-0444, Quality Assurance Topical Report Submittal2023-06-15015 June 2023 Quality Assurance Topical Report Submittal NL-23-0457, ISFSI, and Edwin I. Hatch Nuclear Plant, ISFSI - Registration of Spent Fuel Cask Use2023-06-12012 June 2023 ISFSI, and Edwin I. Hatch Nuclear Plant, ISFSI - Registration of Spent Fuel Cask Use IR 05000321/20230102023-06-0909 June 2023 Focused Engineering Inspection Report 05000321 2023010 and 05000366 2023010 NL-23-0422, Inservice Inspection Program Owner'S Activity Report for Refueling Outage 2R272023-05-30030 May 2023 Inservice Inspection Program Owner'S Activity Report for Refueling Outage 2R27 NL-23-0383, SNC Response to Regulatory Issue Summary 2023-01:Preparation And.2023-05-19019 May 2023 SNC Response to Regulatory Issue Summary 2023-01:Preparation And. ML23136B2942023-05-19019 May 2023 Summary of May 02, 2023, Observation Public Meeting Held with Southern Nuclear Operating Company, Inc., Regarding a LAR for the Reactor Pressure Vessel Head Closure Bolts for Edwin I. Hatch Nuclear Plant, Units 1 and 2 NL-23-0372, Units 1 & 2, Joseph M. Farley Nuclear Plant - Units 1 & 2, Vogtle Electric Generating Plant - Units 1 & 2, Annual Radiological Environmental Operating Reports for 20222023-05-10010 May 2023 Units 1 & 2, Joseph M. Farley Nuclear Plant - Units 1 & 2, Vogtle Electric Generating Plant - Units 1 & 2, Annual Radiological Environmental Operating Reports for 2022 ML23123A2222023-05-0101 May 2023 Notification of Licensed Operator Initial Examination 05000321/2023301, and 05000366/2023301 IR 05000321/20230012023-04-26026 April 2023 Integrated Inspection Report 05000321/2023001 and 05000366/2023001 NL-23-0310, Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 20222023-04-25025 April 2023 Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 2022 NL-23-0019, GEN-ISI-ALT-2023-01, Request to Use Provision of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI2023-04-12012 April 2023 GEN-ISI-ALT-2023-01, Request to Use Provision of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI NL-23-0263, Southern Nuclear Company Submittal of Drug and Alcohol Testing Errors Identified 10 CFR 26.719(c) 30-Day Report2023-04-0505 April 2023 Southern Nuclear Company Submittal of Drug and Alcohol Testing Errors Identified 10 CFR 26.719(c) 30-Day Report NL-23-0014, Southern Nuclear Operating Co Submittal of Report on Status of Decommissioning Funding2023-03-29029 March 2023 Southern Nuclear Operating Co Submittal of Report on Status of Decommissioning Funding NL-23-0208, Independent Spent Fuel Storage Installation ISFSI, Decommissioning Funding Plan Triennial Update2023-03-29029 March 2023 Independent Spent Fuel Storage Installation ISFSI, Decommissioning Funding Plan Triennial Update NL-23-0228, Nuclear Property Insurance Coverage as of April 1, 2023 and Licensee Guarantees of Payment of Deferred Premiums (10 CFR 140.21)2023-03-20020 March 2023 Nuclear Property Insurance Coverage as of April 1, 2023 and Licensee Guarantees of Payment of Deferred Premiums (10 CFR 140.21) NL-23-0179, National Pollutant Discharge Elimination System (NPDES) Permit Renewal2023-03-13013 March 2023 National Pollutant Discharge Elimination System (NPDES) Permit Renewal ML23065A1092023-03-0808 March 2023 Correction of Relief Request HNP-ISI-RR-05-02 Allowing to Continue Operation with a Flaw Indication on One Reactor Pressure Vessel Closure Bolt Until December 31, 2025 ML23053A2182023-03-0303 March 2023 Correction of Amendment Nos. 321 and 266 Regarding License Amendment Request to Revise the (National Fire Protection Association) NFPA-805 Fire Protection Program IR 05000321/20220062023-03-0101 March 2023 Annual Assessment Letter Edwin I. Hatch Nuclear Plant, Units 1 and 2 - NRC Inspection Report 05000321/2022006 and 05000366/2022006 NL-23-0101, Cycle 28 Core Operating Limits Report Version 12023-02-23023 February 2023 Cycle 28 Core Operating Limits Report Version 1 ML23034A2462023-02-21021 February 2023 Audit Summary for License Amendment Request to Relax Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs ML22363A3932023-02-15015 February 2023 Issuance of Amendments Nos. 321 and 266, Regarding License Amendment Request to Revise the (National Fire Protection Association) NFPA-805 Fire Protection Program ML22346A1482023-02-0909 February 2023 Issuance of Amendments 320 and 265, Regarding LAR to Revise Technical Specifications to Adopt TSTF-208 and Administrative Correction for Duplicate Technical Specifications 3.4.10 2024-01-31
[Table view] Category:Licensee Event Report (LER)
MONTHYEARNL-20-0230, Edwin I. Hatch Nuclear Plant, Unit 2, Primary Containment Penetration Exceeded Maximum Allowable Primary Containment Leakage Rate (La)2020-03-0202 March 2020 Edwin I. Hatch Nuclear Plant, Unit 2, Primary Containment Penetration Exceeded Maximum Allowable Primary Containment Leakage Rate (La) 05000366/LER-2020-0012020-03-0202 March 2020 LER 2020-001-00 for Edwin I. Hatch Nuclear Plant, Unit 2, Primary Containment Penetration Exceeded Maximum Allowable Primary Containment Leakage Rate (La) 05000321/LER-2017-0042017-08-24024 August 2017 Tornado Missile Vulnerabilities Result in Condition Prohibited by Technical Specifications, LER 17-004-00 for Edwin I. Hatch Regarding Safety Relief Valves' as Found Settings Resulted in Not Meeting Tech Spec Surveillance Criteria 05000366/LER-2017-0022017-04-13013 April 2017 Emergency Diesel Generator Start Due to Inadvertent Electrical Bus De-Energization, LER 17-002-00 for Edwin I. Hatch, Unit 2, Regarding Emergency Diesel Generator Start Due to Inadvertent Electrical Bus De-Energization 05000366/LER-2017-0032017-04-13013 April 2017 LER 17-003-00 for Edwin I. Hatch, Unit 2, Regarding Primary Containment Isolation Penetration Exceeded Overall Allowable Technical Specification Leakage Limits 05000321/LER-2017-0022017-04-0707 April 2017 High Pressure Coolant Injection System Declared Inoperable Due to Degraded Inverter, LER 17-002-00 for Edwin I. Hatch, Unit 1, Regarding High Pressure Coolant Injection System Declared Inoperable Due to Degraded Inverter 05000366/LER-2016-0042017-01-0303 January 2017 Condition Prohibited by Technical Specifications Due to Inoperable PCIV, LER 16-004-00 for Edwin I. Hatch Nuclear Plant, Unit 2, Regarding Condition Prohibited by Technical Specifications Due to Inoperable PCIV 05000366/LER-2016-0022016-07-13013 July 2016 Group I Isolation Received During Turbine Testing, LER 16-002-00 for Edwin I. Hatch, Unit 2, Regarding Group 1 Isolation Received During Turbine Testing 05000366/LER-2016-0012016-06-0808 June 2016 2C EDG Fuel Oil Relief Valve Leakage Caused Train Inoperability, LER 16-001-00 for E.I. Hatch, Unit 2, Regarding 2C EDG Fuel Oil Relief Valve Leakage Caused Train Inoperability 05000321/LER-2016-0042016-05-26026 May 2016 Safety Relief Valves As Found Settings Resulted in Not Meeting Tech Spec Surveillance Criteria, LER 16-004-00 for Edwin I. Hatch Nuclear Plant Unit 1 RE: Safety Relief Valves as Found Settings Resulted in Not Meeting Tech Spec Surveillance Criteria 05000321/LER-2016-0032016-04-14014 April 2016 Reactor Coolant System Piping Has Unacceptable Weld Indication Discovered During Refueling Outage, LER 16-003-00 for E.I. Hatch, Unit 1, Regarding Reactor Coolant System Piping Has Unacceptable Weld Indication Discovered During Refueling Outage 05000321/LER-2016-0022016-04-11011 April 2016 Performance of Operations With the Potential to Drain the Reactor Vessel (OPDRV) Without Secondary Containment, LER 16-002-00 for E.I Hatch, Unit 1, Regarding Performance of Operations With the Potential to Drain the Reactor Vessel (OPDRV) Without Secondary Containment 05000321/LER-2016-0012016-04-0808 April 2016 Performance of Fuel Movement with Inoperable Rod Position Indication System in Violation of Technical Specifications, LER 16-001-00 for Edwin I. Hatch, Unit 1, Regarding Performance of Fuel Movement With Inoperable Rod Position Indication System in Violation of Technical Specifications NL-08-1906, LER 08-S01-00, for Edwin I. Hatch, Failure to Report Arrest Results in Inappropriate Access to Protected and Vital Areas2008-12-19019 December 2008 LER 08-S01-00, for Edwin I. Hatch, Failure to Report Arrest Results in Inappropriate Access to Protected and Vital Areas ML1019404552008-05-0808 May 2008 Southern Nuclear Plant E. I. Hatch - Actions for Potential Groundwater Contamination Events NL-06-2726, LER 06-S01-00 for Edwin I. Hatch Nuclear Plant, Re Contract Employee Failure to Self-Disclose Material Information for Unescorted Access2006-12-0505 December 2006 LER 06-S01-00 for Edwin I. Hatch Nuclear Plant, Re Contract Employee Failure to Self-Disclose Material Information for Unescorted Access ML17252B4401976-04-15015 April 1976 LER 76-026-00 for Hatch, Unit 1 Regarding an Occurrence of Open Links in Panel H11-P601 Defeating the Starting of All RHR Pumps After They Had Been Stopped 2020-03-02
[Table view] |
Reported lessons learned are incorporated into the licensing process and fed back to industry.
Send comments regarding burden estimate to the FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by intemet e-mail to Int ocollects.Resource@nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0104), Office of Management and Budget, Washington, DC 20503. If a means used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.
PLANT AND SYSTEM IDENTIFICATION
General Electric- Boiling Water Reactor (BWR) Energy Industry Identification System codes appear in the text as (EIIS Code XX)
DESCRIPTION OF EVENT
On 02/11/16, during the Hatch 1R27 outage, fuel movement activities were halted, due to a faulty grapple camera. Once the camera was fixed, the fuel movement activities recommenced. After a couple of minutes, the operator was unable to lower a blade guide into the core. It was discovered that a refueling interlock of the main grapple was encountered. This had occurred because 20 Rod Position Indication System (RPIS) Position Indicating Probes (PIPs) had been disconnected. The work to remove the PIPs was authorized by the Work Release Supervisor and the Unit 1 Shift Supervisor, out of sequence.
The RPIS indications were bypassed and the blade guide was lowered into the core followed by continuing fuel movement.
After a review of Technical Specification 3.9.4, Control Rod Position Indication, it was determined that fuel movement should not be performed with the RPIS probe disconnected and bypassed because the associated control rods were not hydraulically disarmed by closing the drive water and exhaust water isolation valves in accordance with the Technical Specification Bases. Fuel movement was then halted. The Unit 1 Shift Supervisor instructed the PIPs to be reinstalled.
The PIPs were installed, RPIS full-in bypass box switches for all rods (20) were un-bypassed and the fuel movement activities were resumed.
CAUSE OF EVENT
The cause of moving fuel while the RPIS "full-in" indication was inoperable was due to inadequate procedure usage. The operations Shift Manager also became involved in troubleshooting and did not maintain an oversight role. This contributed to a misinterpretation of technical specifications, leading to the inappropriate decision to bypass the (20) RPIS full-in indications prior to commencing fuel movement.
REPORTABILITY ANALYSIS AND SAFETY ASSESSMENT
This event is reportable per 10 CFR 50.73(a)(2)(i)(B) as an operation or condition prohibited by Technical Specifications (TS) 3.9.4 which prohibits performing fuel movement when one or more required control rod position indication channels are inoperable.
Refueling equipment interlocks restrict the operation of the refueling equipment or the withdrawal of control rods to reinforce unit procedures that prevent the reactor from potentially achieving criticality during refueling. The refueling interlock circuitry senses the conditions of the refueling equipment and the control rods. Depending on the sensed conditions, interlocks are actuated to prevent the operation of the refueling equipment or the withdrawal of control rods.
The disconnection of the RPIS PIPs did not result in any damage to safety related equipment, offsite radiological releases, or personnel injuries. The Control Rod Drive Pumps had been stopped, thus preventing any potential control rod movement by removing the motive force. The control rods were therefore effectively hydraulically disarmed but not as suggested by the Tech Spec Bases 3.9.4 by closing the drive water and exhaust water isolation valves. Even though this condition was contrary to Tech Spec requirements, no change in reactivity resulted and no movement of the control rods occurred. Based on this information this reported condition had very low safety significance.
CORRECTIVE ACTIONS
Immediately following the event fuel movement was halted and the PIPS were installed. Qualifications were withdrawn for the personnel involved and a "stand down" was held with the Operations department where emphasis was stated on the importance of remaining in assigned roles.
Operations training will be presented using this event as operating experience during license training prior to the next refueling outage. Special focus will be placed on the technical specifications that apply during this evolution, the importance of staying within roles, and avoidance of making decisions driven by schedule concerns. Operations training will also perform specific pre-outage training on non-routine tasks (including control rod manipulations and fuel removal) prior to the next refueling outage.
ADDITIONAL INFORMATION
Other Systems Affected: None.
Failed Components Information: None.
Commitment Information: This report does not created any new licensing commitments.
Previous Similar Events:
On 2/25/2012, with the unit in Mode 5 for refueling, the "full-in" indication for Control Rod (CR) 22-27 was noted to be inoperable, and a required action statement (RAS) for TS 3.9.4 was entered. In accordance with the RAS the control room staff visually verified that the CR was fully inserted, action was taken to electrically disarm the associated CR drive, and a tag-out was conducted as part of the disarming action. A modified probe buffer card was installed to bypass the "full-in" indication signal in order to remove the rod block. Notation of the use of the modified probe buffer card was added to an existing TS RAS to track its installation and loss of the RPIS indication. At 2121 EST on 2/28/2012, the tag- out described above was cleared (i.e., removed) without removing the modified probe buffer card and without performing a functional test of the "full-in" indication prior to moving fuel in the reactor vessel. Fuel movement occurred from the time the tag-out was removed until 0817 EST on 3/212012 when the error was discovered; resulting in a condition prohibited by TS for CR position indication. The cause of this event was attributed to less than adequate procedural controls and the failure of involved personnel to effectively "self-check" as a human error prevention technique. A procedure change was implemented to require the shift supervisor to sign a tag-out if used to comply with a TS requirement. Because the lack of a tagout was cited in the 2016 event, the corrective actions from the 2012 event would not be expected to have prevented the condition reported in this LER.
|
---|
|
|
| | Reporting criterion |
---|
05000366/LER-2016-001 | 2C EDG Fuel Oil Relief Valve Leakage Caused Train Inoperability LER 16-001-00 for E.I. Hatch, Unit 2, Regarding 2C EDG Fuel Oil Relief Valve Leakage Caused Train Inoperability | 10 CFR 50.73(a)(2)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000321/LER-2016-001 | Performance of Fuel Movement with Inoperable Rod Position Indication System in Violation of Technical Specifications LER 16-001-00 for Edwin I. Hatch, Unit 1, Regarding Performance of Fuel Movement With Inoperable Rod Position Indication System in Violation of Technical Specifications | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000366/LER-2016-002 | Group I Isolation Received During Turbine Testing LER 16-002-00 for Edwin I. Hatch, Unit 2, Regarding Group 1 Isolation Received During Turbine Testing | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000321/LER-2016-002 | Performance of Operations With the Potential to Drain the Reactor Vessel (OPDRV) Without Secondary Containment LER 16-002-00 for E.I Hatch, Unit 1, Regarding Performance of Operations With the Potential to Drain the Reactor Vessel (OPDRV) Without Secondary Containment | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000366/LER-2016-003 | 2C Emergency Diesel Generator Inoperable Due to Low Lube Oil Pressure | 10 CFR 50.73(a)(2)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000321/LER-2016-003 | Reactor Coolant System Piping Has Unacceptable Weld Indication Discovered During Refueling Outage LER 16-003-00 for E.I. Hatch, Unit 1, Regarding Reactor Coolant System Piping Has Unacceptable Weld Indication Discovered During Refueling Outage | 10 CFR 50.73(a)(2)(ii)(A), Seriously Degraded | 05000366/LER-2016-004 | Condition Prohibited by Technical Specifications Due to Inoperable PCIV LER 16-004-00 for Edwin I. Hatch Nuclear Plant, Unit 2, Regarding Condition Prohibited by Technical Specifications Due to Inoperable PCIV | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000321/LER-2016-004 | Safety Relief Valves As Found Settings Resulted in Not Meeting Tech Spec Surveillance Criteria LER 16-004-00 for Edwin I. Hatch Nuclear Plant Unit 1 RE: Safety Relief Valves as Found Settings Resulted in Not Meeting Tech Spec Surveillance Criteria | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications |
|