Title | Failure to Correct Numerous Anchor Darling Double Disc Gate Valve Non-Conformances |
Description | The inspectors identified a finding of very low safety significance (Green) and an associated NCV of 10 CFR 50, Appendix B, Criterion XVI, Corrective Action for the licensees failure to correct a design non-conformance reported to the licensee through two related 10 CFR Part 21 reports. In March 2013, the licensee identified that 28 safety-related Anchor Darling double disc gate valves (ADDDGVs) may not have been assembled with an assumed amount of valve stem to wedge pre-torque before the stem was pinned into the wedge. The licensee had restored compliance to only one of these valves and had no plans to restore quality to the remaining 27 valves prior to the inspection. The licensee entered the inspectors conclusions into their corrective action program (CAP) as AR 201710399. At the end of this inspection the licensees plan was to restore compliance by either correcting the Part 21 issue or changing the design to accept the stem not having any pre-torque into the wedge.The performance deficiency was determined to be more than minor because if left uncorrected could become a more significant safety concern. Specifically, the failure to correct the design deficiencies could result in the valve pin breaking and consequential valve damage if the valves were operated at a high enough torque and/or thrust value(s). The finding screened as of very low safety significance (Green) because it did not result in the loss of operability or functionality of Mitigating Systems. Specifically, the licensee performed an operability determination which concluded that all 28 valve wedge pins had not sheared based upon the known historic operational history, pin material properties, and for using stem to wedge thread friction in some cases. The inspectors determined that this finding was not indicative of recent performance and therefore did not have a cross-cutting aspect assigned. |
Site: | Cook |
---|---|
Report | IR 05000315/2017004 Section 1R12 |
Date counted | Dec 31, 2017 (2017Q4) |
Type: | NCV: Green |
cornerstone | Mitigating Systems |
Identified by: | NRC identified |
Inspection Procedure: | IP 71111.12 |
Inspectors (proximate) | J Ellegood T Taylor M Domke M Garza T Go M Holmberg J Park J Benjamin J Bozga J Mancuso K Riemer |
Violation of: | 10 CFR 21, PART 21-REPORTING OF DEFECTS AND NONCOMPLIANCE 10 CFR 50 Appendix B Criterion XVI |
INPO aspect | |
' | |