05000313/FIN-2009004-06
From kanterella
Jump to navigation
Jump to search
Finding | |
---|---|
Title | Failure to Implement Troubleshooting Procedure During Troubleshooting Activities |
Description | The inspectors documented a self-revealing finding for failure to follow Procedure EN-MA-125, Troubleshooting, Revision 3. Specifically, the procedure was not implemented, as work conditions dictated, and failed to prevent maintenance from blowing a fuse while performing troubleshooting activities in the steam generator blow down tank level switch circuitry. This resulted in the energizing of pressurizer backup heaters, loss of automatic operations of the main feedwater pump lube oil temperature and loss of the first stage pressure input, requiring operator action to regain control of systems. The performance deficiency was determined to be more than minor because it was associated with the configuration control attribute of the Initiating Events Cornerstone and affected the objective to limit the likelihood of those events that upset plant stability and challenge critical safety functions during power operations, and is therefore a finding. Using Inspection Manual Chapter 0609, Phase 1 Worksheets, the finding was determined to be of very low safety significance because the finding did not contribute to both the likelihood of a reactor trip and the likelihood that mitigation equipment or functions would not have been available. It was determined that the finding had a crosscutting aspect in the area of human performance associated with work practices H.4(b), in that the licensee failed to define and effectively communicate expectations regarding procedural complianc |
Site: | Arkansas Nuclear |
---|---|
Report | IR 05000313/2009004 Section 4OA3 |
Date counted | Sep 30, 2009 (2009Q3) |
Type: | Finding: Green |
cornerstone | Initiating Events |
Identified by: | Self-revealing |
Inspection Procedure: | IP 71153 |
Inspectors (proximate) | C Graves T Mckernon A Sanchez J Josey J Clark B Larson M Bloodgood T Pate S Hedger J Rotton |
CCA | H.8, Procedure Adherence |
INPO aspect | WP.4 |
' | |
Finding - Arkansas Nuclear - IR 05000313/2009004 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Finding List (Arkansas Nuclear) @ 2009Q3