05000285/FIN-2013018-03
From kanterella
Jump to navigation
Jump to search
Finding | |
---|---|
Title | Failure to Furnish Evidence of Activities Affecting Quality |
Description | The team identified three examples of a non-cited violation of 10 CFR Part 50, Appendix B, Criterion XVII, Quality Assurance Records, associated with the licensees failure to furnish evidence of an activity affecting quality. Specifically, the licensee failed to maintain records demonstrating that: the temperature limits for structural concrete in the Auxiliary building would not be exceeded during a high energy line break event, that the predicted flood level in Room 81 during a high energy line break event would not affect required equipment, and that electrical splices inside of the containment were installed in accordance with the plant and the vendor installation instructions. The licensee performed an operability determination for the deficiencies that established a reasonable expectation for operability pending final resolution of the problems. The licensee entered these deficiencies into their corrective action program for resolution as Condition Reports CR 2013-22556, and CR 2013-12359. The licensees failure to furnish evidence of completing analyses or maintaining records for the flood level in Room 81 during a high energy line break event, the structural concrete temperatures in the Auxiliary building, and electrical splice installations, is a performance deficiency. This performance deficiency was determined to be more than minor, and therefore a finding, because it was associated with the design control attribute of the Mitigating Systems Cornerstone, and affected the associated cornerstone objective to ensure availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Using Inspection Manual Chapter 0609, Appendix A, Initial Screening and Characterization of Findings, dated July 1, 2012, the inspectors determined that the finding was of very low safety significance (Green) because the finding: (1) was not a deficiency affecting the design and qualification of a mitigating structure, system, or component, and did not result in a loss of operability or functionality; (2) did not represent a loss of system and/or function; (3) did not represent an actual loss of function of at least a single train for longer than its technical specification allowed outage time, or two separate safety systems out-of-service for longer than their technical specification allowed outage time; and (4) does not represent an actual loss of function of one or more non-technical specification trains of equipment designated as high safety-significant for greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> in accordance with the licensees maintenance rule program. The team determined that this finding does not have a cross-cutting aspect because the most significant contributor of this finding would have occurred more than three years ago, and therefore, does not reflect current licensee performance. |
Site: | Fort Calhoun |
---|---|
Report | IR 05000285/2013018 Section 1R21 |
Date counted | Dec 31, 2014 (2014Q4) |
Type: | NCV: Green |
cornerstone | Mitigating Systems |
Identified by: | NRC identified |
Inspection Procedure: | IP 71111.21 |
Inspectors (proximate) | A Vegel C Smith J Josey J Wingebach N Patel T Lighty |
Violation of: | 10 CFR 50 Appendix B Criterion XVII, Control of Purchased Material, Equipment, and Services Technical Specification |