05000245/LER-1996-020, Forwards LER 96-020-02,documenting Event Occurred at Unit 1 on 960322.Supplemental Rept Provides Update to Vol Calculations.Commitment B15674-3 Updated

From kanterella
Jump to navigation Jump to search
Forwards LER 96-020-02,documenting Event Occurred at Unit 1 on 960322.Supplemental Rept Provides Update to Vol Calculations.Commitment B15674-3 Updated
ML20136J517
Person / Time
Site: Millstone Dominion icon.png
Issue date: 03/17/1997
From: Hinnenkamp P
NORTHEAST NUCLEAR ENERGY CO., NORTHEAST UTILITIES SERVICE CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20136J521 List:
References
B16212, NUDOCS 9703200128
Download: ML20136J517 (2)


LER-2096-020, Forwards LER 96-020-02,documenting Event Occurred at Unit 1 on 960322.Supplemental Rept Provides Update to Vol Calculations.Commitment B15674-3 Updated
Event date:
Report date:
2452096020R00 - NRC Website

text

.

l

,' N:rthenst moe ornm . n,e rerry na., ne,rora, er p Utilities System go 3,,128 Weierford, CF 06385-0128 i (8t4) 447-1791 l

March 17,1997 l Docket No. 50-245 B16212 Re: 10CFR50.73(a)(2)(i) 10CFR50.73(a)(2)(ii) l U.S. Nuclear Regulatory Commission Document Control Desk ,

Washington, DC 20555 i This letter forwards supplemental Licensee Event Report (LER) 96-020-02, documenting an  ;

event that occurred at Millstone Nuclear Power Station,' Unit No. I on March 22,~ 1996. This  !

LER is submitted pursuant to 10CFR50.73(a)(2)(i) and 10CFR50.73(a)(2)(ii). -

The supplemental report 96-020-01 that was submitted on December 16,1996, indicated that an additional supplement was intended. However, this was actually in error since no additional ,

supplement was intended, In order to maintain a " clean docket," this supplemental report is bemg j submitted. l This supplemental report provides an update to the volume calculatiov Accordingly, ,

Commitment No. B15674-3 has been updated. Also, the Commitment No. B15674-4 has been i supplemented.

The following are Northeast Nuclear Energy Company's (NNECO's) commitments made within  !

this letter. All other statements made within this letter are for information only.  !

B15674-1 NNECO commits to revise design calculations to correctly identify the usable volume of the condensate storage tank (CST). This will be completed prior to startup for operating cycle 16.

i B15674-2 NNECO commits to perform a review of the calculations of the rusable volume I of all safety-related tanks. This review will be completed prior to startup for operating cycle 16.

1 B15674-3 NNECO commits to revise administrative procedures to ensure at least 301,500 y 20003,1 gau ns is avaHable in the CST at aH dmes feedwater coolant injection inequired to y be operable, prior to startup for operating cycle 16. .

9703200128 970317 PDR S

ADOCK 05000245

.Nhhhh,@ ( k lL/ I PDR l I

U.S. Nuclear Regulatory Commission B16212\Page 2 of 2 B15674-4 NNECO commits to provide procedural guidance, as the long-term corrective action, for maintaining appropriate levels in the CST while the torus is drained.

NNECO will complete this prior to shutdown for refueling outage 16.

Administrative controls will remain in place to prevent torus draining, until such procedural controls for emergency core cooling system flow throttling are put in  ;

place.

Very truly yours, NORTHEAST NUCLEAR ENERGY COMPANY C ~

! l P. D. Hinnenkamp' V  !

Director, Unit Operations l

Attachment:

LER 96-020-02 l

cc: Dr. W. D. Travers, Director, Special Projects  !

H. J. Miller, Region I Administrator S. Dembek, NRC Project Manager, Millstone Unit No.1 T. A. Eastick, Senior Resident Inspector, Millstone Unit No. I 1

j