Pages that link to "05000280/LER-1978-028, Forwards LER 78-028/03L-0"
Jump to navigation
Jump to search
The following pages link to 05000280/LER-1978-028, Forwards LER 78-028/03L-0:
Displayed 50 items.
- ML20064B815 (redirect page) (← links)
- 05000280/LER-1978-028-03, /03L-0 on 780916:snubber Not Meeting Inspec Criteria Caused by Low Oil Level Due to Leakage at Mating Surface Between Body & End Plate.Holding Bolts Were Tightened & Snubber Was Refilled (← links)
- 05000280/LER-1978-028 (redirect page) (← links)
- 05000280/LER-1978-004-03, /03X-1 on 780305:loss of Svc Water Flow Through Charging Pump Intermediate Seal Cooler Was Caused by Corrosion of Stem of Discharge Gate Valve;Corrosion Was Galvanic(Brass Touching Bronze);Problem Will Be Studied (← links)
- 05000281/LER-1978-011, Forwards LER 78-011/03X-1 (← links)
- 05000280/LER-1978-029-03, X-1, LER 78-029-03L-0, & LER 78-031-03L-0 for Surry 2 Re Critical Below Minimum Insertion Limit on D Control Bank (← links)
- 05000280/LER-1978-027, Submit LER 78-027/03L-0 Re Seven Snubbers Not Meeting Inspection Criteria (← links)
- 05000280/LER-1978-001, Submit Licensee Event Report No. LER-78-001/03L-0 Re Hydraulic Shock Suppressor Found Inverted with Empty Reservoir (← links)
- 05000280/LER-1978-002, Submit Licensee Event Report No. LER-78-002/01T-0 Re Additional Radial Peaking Factor Surveillance (← links)
- 05000280/LER-1978-003, Submit Licensee Event Report No. LER-78-003/03L-0 Re Failed Heat Tracing, Panel 8 Circuit 24 (← links)
- 05000280/LER-1978-004, Submit Licensee Event Report No. LER-78-004/03L-0 Re Loss of Service Water Flow Through Charging Pump Intermediate Seal Cooler (← links)
- 05000280/LER-1978-005, Forwarding Licensee Event Report No. LER-78-005/01T-0 Re Westinghouses Error in LOCA-ECCS Evaluation Model, Which Will Result in Higher Calculated Peak Clad Temperature (← links)
- 05000280/LER-1978-006, Submit Licensee Event Report No. LER-78-006/01T-0 Re Seismically Disqualified Two Pipe Extensions on Fire Protection Yard Piping (← links)
- 05000280/LER-1978-007, Submit Licensee Event Report No. LER-78-007/03L-0 Re Leak on Body to Bonnet Joint Diaphragm Valve 1-CH-98 (← links)
- 05000280/LER-1978-008, Submit Licensee Event Report Nos. LER-78-008/03L-0, LER-78-009/03L-0, LER-78-010/03L-0, LER-78-011/03L-0 for Surry Unit No. 1 (← links)
- 05000280/LER-1978-012, Submit Licensee Event Report No. LER-78-012/03L-0 Re Inside Recirculation Spray Pump 1-RS-P-1A, Failure to Rotate by Hand (← links)
- 05000280/LER-1978-015, Submit Licensee Event Report No. LER-78-015/03L-0 Re Valve Cleanliness Inspection Found Foreign Material on Valve Seating Surfaces (← links)
- 05000280/LER-1978-013, Submit Licensee Event Report Nos. LER 78-013/03L-0 Re Six Snubbers Not Meeting Test Criteria, & 78-014/03L-0 Re Mount Plate Was Warped, & 3 of 8 Bolts Were Insufficiently Embedded (← links)
- 05000280/LER-1978-016, Submit Licensee Event Report No. LER 78-016/03L-0 Re Valve MOV-RH-100 Was Not Opening (← links)
- 05000280/LER-1978-017, Submit Licensee Event Report Nos. LER 78-017/03L-0 Re Not Documenting Four Electric Maintenance Procedures & Two Periodic Tests, & 78-020/03L-0 Re Suspended Air Bubbles in Reservoir Fluid (← links)
- 05000280/LER-1978-018, Sutmit Licensee Event Report No. LER 78-018/03L-0 Re Two Main Steam Safety Valves Were Not within Plus or Minus 3% of Setpoint as Required (← links)
- 05000280/LER-1978-024, Submit Licensee Event Report No. LER 78-024/03L-0 Re No Alarm During a Planned Release of Liquid Radioactive Waste (← links)
- 05000280/LER-1978-034, Update to LER 78-034/01X-2 on 781101:17 Spare Process Piping Containment Penetrations Were Not Capped.Condition Has Been Overlooked Since Const.Design Change Approved to Weld Caps on Open Ends (← links)
- 05000281/LER-1978-038-03, /03X-1 on 781030:boric Acid Flow from Boric Acid Tank to Blender Was Interrupted.Caused by Blockage of Crystallized Boron at Elbow in Line 1-CH-356-152 (← links)
- 05000281/LER-1978-033-03, /03X-1 on 780926:circulating Water Outlet Valve MOV-CW-200D Failed to Close When Operated Electrically. Caused When Actuator Cam for Shut Torque Switch Became Wedged Against Torque Switch Hold Down Screw (← links)
- 05000280/LER-1978-047-03, /03X-1 on 781211:primary to Secondary Leakage in C Steam Generator Exceeded Allowable Limit.Caused by Leakage Through Five Steam Generator Tubes,Combined Flow Resulted in Excessive Leakage (← links)
- 05000280/LER-1978-047, Forwards LER 78-047/03X-1 (← links)
- 05000280/LER-1978-038-03, /03X-1 on 781108:review of Operational Data Showed That Quarterly Calibr of Nuclear Power Range Instrumentation Had Not Been Performed Per Schedule,Due to Scheduling Error (← links)
- 05000280/LER-1978-031-03, /03X-1 on 781001:during Normal Operation,Channel I Pressurizer Level (Protection) L-I-459 Drifted High.Caused by Drift of Electronic Zero Adjustment,In Conjunction W/ Leakage Thru Transmitter Bypass/Equalizing Valve (← links)
- 05000280/LER-1978-031, Forwards LER 78-031/03X-1 & 78-038/03X-1 (← links)
- 05000280/LER-1978-041-03, /03X-1 on 781121:during Performance of PT-39-1 at Full Power,Snubber 1-WAPD-HSS-141B Had 0 Fluid Level in Reservoir,Due to Crack in Reservoir Glass (← links)
- 05000280/LER-1978-041, Forwards LER 78-041/03X-1 (← links)
- 05000280/LER-1978-049-03, /03L-0 on 781219:conduct of PT-39B Revealed 2 Snubbers W/Fluid Levels Less than Target Level.Caused by Leaking Tube Fittings (← links)
- 05000280/LER-1978-046-03, /03L-0 on 781211:during Routine Surveillance, Discovered Failure of Heat Tracing Circuit 25A (Panel 2) Unit 1 Boron Injection Tank Recirculation to Boric Acid Tank.Caused by Boric Acid Attack on Heat Tracing Circuit (← links)
- 05000280/LER-1978-045-03, /03L-0 on 781205:radiation recorder,RR-175,stopped Printing.Caused by Frozen Bushing in Print Mechanism (← links)
- 05000280/LER-1978-045, Forwards LER 78-045/03L-0,78-046/03L-0 & 78-049/03L-0 (← links)
- 05000280/LER-1978-048-03, /03L-0 on 781209:2 Control Rod Assemblies Dropped During Rod Urgent Failure Alarm Investigation.Caused by a Faulty Phase Control Circuit Card in the Rod Control Power Cabinet (← links)
- 05000280/LER-1978-050-01, /01T-0 on 781220:Westinghouse Notified VEPCO of Input Error in Current LOCA-ECCS Analysis,Increasing Peak Clad Temp 20 F.Cause Was Alternate Modeling Methodology Used in Analyzing Containment Pressure Response Effects (← links)
- 05000280/LER-1978-050, Forwards LER 78-050/01T-0 (← links)
- 05000280/LER-1978-043-03, /03L-0 on 781129:low Temp Alarm & Rapid Increase in Level Were Noted in Boric Acid Storage Tank a During Valve Line Up to Transfer Boric Acid from Storage Tank B to A.Caused by Erroneous Opening of 1-CH-74 (← links)
- 05000280/LER-1978-043, Forwards LER 78-043/03L-0 (← links)
- 05000280/LER-1978-044-03, /03L-0 on 781204:during Normal Full Pwr Oper,Loss of Flow Was Detected in Charging Pump Intermediate Seal Cooler 1-SW-E-1B.Caused by Failure of Cooler Intake Gate Valve Becoming Corroded (← links)
- 05000280/LER-1978-044, Forwards LER 78-044/03L-0 (← links)
- 05000280/LER-1978-022-03, /03X-1 on 780726:Hydro Test Pump Failed to Build Up Pressure During Attempt to Fill Safety Injection Accumulators Due to Lifting of Its Relief Valve.Valve Replaced & Checked.Accumulator Refilled (← links)
- 05000280/LER-1978-022, Forwards LER 78-022/03X-1 (← links)
- 05000281/LER-1978-041-03, /03l on 781201:failure of Heat Tracing Circuit 5A (Panel 10)Unit 2 Blender to Charging Pump Suction Due to Water Damage of Heat Tracing Circuit.Heat Tracing Tape Replaced (← links)
- 05000281/LER-1978-041, Forwards LER 78-041/03L-0 (← links)
- 05000280/LER-1978-034-01, /01X-1 on 781101:noted That 17 Spare Process Piping Penetrations on Unit 1 & 23 on Unit 2 Were Not Capped in Auxiliary Bldg.Caused by Failure to Properly Complete Capping at End of Constr (← links)
- 05000281/LER-1978-040-03, /03L-0 on 781116:routine Testing Revealed Failure of Heat Tracing Circuit 4C Unit 2 Boron Injection Tank Top Recirculation Return.Caused by Boric Acid Damage to the Heat Tracing Circuit (← links)
- 05000281/LER-1978-039-03, /03L-0 on 781115:during Normal Oper,It Was Noted That B Loop Hot Leg Temp Sensing Element TI-2-422A Was Drifting Low.Caused by Packing Leak Which Reduced Resistance of the Sensing Element (← links)