ML20214Q561

From kanterella
Jump to navigation Jump to search
Insp Repts 50-498/87-08 & 50-499/87-08 on 870309-0410. Violations Noted:Failure to Follow Procedures for Testing & Inadequate Cleanliness Controls Over Open Rcs.Major Areas Inspected:Tmi & Generic Ltr 83-28 Action Items
ML20214Q561
Person / Time
Site: South Texas  STP Nuclear Operating Company icon.png
Issue date: 05/29/1987
From: Bundy H, Carpenter D, Chamberlain D, Constable G, Cummins J, Hildebrand E, Johnson W, William Jones, Luehman J, Madsen G, Greg Pick, Reis T, Tapia J, Renee Taylor
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20214Q539 List:
References
RTR-NUREG-0737, RTR-NUREG-737, TASK-***, TASK-TM 50-498-87-08, 50-498-87-8, 50-499-87-08, 50-499-87-8, GL-83-28, NUDOCS 8706050075
Download: ML20214Q561 (80)


See also: IR 05000498/1987008

Text

. ,

APPENDIX B

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

NRC Inspection Report: 50-498/87-08 Construction Permits: CPPR-128

50-499/87-08 CPPR-129

Dockets: 50-498

50-499

Licensee: Houston Lighting & Power Company (HL&P)

P. O. B)x 1700

Houston, Texas 77001

Facility Name: South Texas Project, Units 1 and 2 (STP)

Inspection At: STP, Matagorda County, Texas

Inspection Conducted: March 9 through April 10, 1987

'

N

Inspectors:

.

- -

.Ma7penter, Senior Resident Inspector D(te /

/f'7

Project Section C, Reactor Projects Branch

w

- flD

,T. heis, Resident Inspector, Project

'

Daf.e

Section C, Reactor Projects Branch

.fl2f/S7

H. F. Bundy, Project lYispector, Project Date

Section C, Reactor Projects Branch

WP

J. I. Tai >1a, ReactorInspector, Operations

f/17/N 7

Date

Section, Reactor Safety Branch

G706050075 870529

PDR ADOCK 05000498

E_ __0 PDR __ _ _ _ _ _ _ _ _ _ _

._ _ ___-________________ - - ________ ___ ___________

.

.

. ..

  • o

2

h

J.~ G. Lu man, Seniof Resident Inspector

587/77

Date

'

Project Section C, Reactor Projects Branch

I

r J. E. Cummins, Senior Resident Inspector D(ate /2Fb 7

Project Section B, Reactor Projects Branch

l

fW

D. D. Chamtierlain, Serrior Resident Inspector

Tb W97

Date

/ Project Section A, Reactor Projects Branch

.fbfA'?

~

W. D. Johns'on~~Senio Resident inspector Date

Project Section B, Reactor Projects Branch

i

.

fAllfff7

G. L. Madsen, Reae dr Inspector, Operations (Tate ~

Section, Reactor Safety Branch

. B. Jon s, Reside ( Inspector, Project ate

Section A, Reactor Projects Branch

- . Y% Al,14 A

G. A. c , Reactor inspector, Operations Dat(

Secti n, Reactor Safety Branch

I

. ,

3

/ $

C P. fit Tde' brand, React 6r Inspector Date

29 ~ ~7

Operations Section, Reactor Safety Branch

P

R. G.

s b, Project Inspector, Project

4/o

Dite/

Section , Reactor Projects Branch

Consultants: M. Bishop, F. Jagger, N. Jensen, R. Picker, J. Stachew,

J. Seherman, J. McGhee; EG&G Idaho Inc.

NRC Coop

Student: J. Lara

Approved:

i4.

_ -c<

onstable, Chief, Project Section C

("

Da(e

e ~)

Reactor Projects Branch

Inspection Summary

Inspection Conducted March 9 through April 10, 1987 (Report 50-498/87-08;

$0-499/87-08)

Areas Inspected: Routine, unannounced inspection of Technical Specifications (TS),

the structural integrity and integrated leak rate tests (SIT and ILRT),

preoperational test procedures, preoperational test results, the startup

testing program, the as-built plant to documentation reconciliation, the

residual heat removal (RHR)/ component cooling water (CCW) water hammer incident,

operational staffing, training and qualification programs, the reactor coolant

system loss of cleanliness recovery program, the Three Mile Island (TMI) and

GL 83-28 action items, licensee action on previous inspection findings, site

tours, review of the manual trip circuit, and procedures review.

Results: Within the areas inspected, two violations of NRC requirements were

identifled (failure to follow precedures for testing and inadequate cleanliness

controls over an open reactor coc!}qt .S/ stem, paragraphs 8 and 11, respectively).

L.__.__.

-

. .

4

DETAILS

1. Persons Contacted

  • R. W. Chewning, Special Assistant Nuclear Group l
  • S. M. Head, Lead Engineer, Licensing
  • D. L. Smith, Management Services Manager
  • G. L. Jarvela, Manager, Health and Safety Services
  • M. A. Ludwig, Maintenance Manager
  • T. E. Underwood, Chemistry Manager
  • G. L. Parkey, Technical Support Manager
  • J. W. Loesch, Plant Superintendent
  • M. T. Sweigart, General Supervisor, Operations Quality Control (QC)
  • W. H. Kinsey, Flant Manager
  • J. J. Eldridge, Operations Supervisor
  • W. P. Evans, Project Compliance Engineer

J. T. Westermeier, Project Manager

F. A. White, Lead Licensing Engineer

R. J. Daly, Startup Manager

J. D. Green, Operations Quality Assurance (QA) Manager

V. E. Geiger, Nuclear Assurance Manager

M. Robinson, Director, Independent Safety Evaluation Group

D. L. Cody, Manager, Nuclear Training

M. E. Smith, Outage Manager

J. Hooper, Employment Counselor

D. Leazur, Reactor Performance Supervisor

T. Godsey, Technical Support Engineer

  • Denotes those individuals attending the exit interview conducted on

April 10, 1987.

The NRC inspector also interviewed other personnel of HL&p, Bechtel Power

Corporation, and Ebasco Service, Inc.

2. TS Review

The NRC inspectors and EG&G Idaho consultants reviewed the Proof and

Review copy dated February 12, 1987, of the STP Unit 1 TS. In performing

this review, the following techniques were employed:

o Comparison with NUREG-0452, Revision 5, " Standard Technical

Specifications for Westinghouse Pressurized Water Reactors."

o Comparison with TSs for other recently licensed Westinghouse plants

(Wolf Creek Generating Station and Byron, Unit 1).

o Walkdown of selected systems and components to verify as-built

configurations were reflected in the TS.

o Verification that numerical values of setpoints, operating criteria,

and equipment operating parameters agreed with FSAR and/or

engineering specification values.

_ _ _ - ._ _

. _ _ . . _ - - _ - . - _ _ _ - - - -

. .

5

Resulting comments were discussed with the licensee and forwarded to the

NRR project manager by memorandom on March 25, 1987. l

i

No violations or deviations were identified,

t

3. SIT and ILRT

An inspection was conducted of the containment SIT procedures, test

performance and test results in order to determine consistency with

regulatory requirements and licensee commitments. The purpose of the SIT

is to demonstrate the ability of the containment structure to withstand

internal loads imposed by pressurizing to 1.15 times the design pressure

of 56.6 psig or 65.0 psig. Bechtel Specification Nos. 20019S50009,

'

Revision 2, " Instrumentation For Structural Integrity Test of Containment

Structures," and 2C0195S1013, Revision 1, " Specification For The

Performance of Structural Integrity Test on Reactor Containment Building,

Unit 1," were reviewed by the NRC inspector.

Prior to pressurization of the containment, the NRC inspector toured the

containment and inspected the placement of instrumentation for the SIT.

The containment was subsequently pressurized in five equal pressure

increments. During the 1-hour hold periods between pressure levels,

strains, and deflections were recorded. Surface crack patterns of cracks

. larger than 0.01 in width were recorded at atmospheric pressure before the

test, at the maximum pressure level, and at atmospheric pressure after the

f test.

The NRC inspector monitored the acquisition of data during the maximum

pressure level holding period. Subsequent data analysis determined that

the deflection pattern and strain measurements of the containment were

within predetermined design acceptance criteria. No reportable cracks

were identified.

I

At the completion of the SIT, the containment was depressurized to

31.8 psig to perform the ILRT.

The preoperational containment ILRT conducted using the Absolute Method

(as described in ANSI N45.4-1972, " Leakage Rate Testing of Containment

l Structures for Nuclear Power Plants," and ANSI /ANS-56.8 1981, " Containment

i

'

System Leakage Testing Requirements,") was also addressed during this

inspection. The inspection involved procedure and records review, test

witnessing, and independent calculations by the NRC inspector. This ILRT

was conducted in accordance with approved procedures and satisfied the

specified acceptance criteria contained in 10 CFR Part 50, Appendix J,

" Primary Reactor Containment Leakage Testing for Water Cooled Power

Reactors," and in the Plant TS.

Preoperational Test Procedure No. 1-RC-P-03, Revision 0, " Containment

Integrated Leak Rate Test," incorporates the referenced requirements and

criteria. This procedure was reviewed by the NRC inspector and no

_ - -

. .

6

discrepancies from the specified requirements and criteria were noted.

The review provided verification that the following test attributes were

correctly addressed:

o Containment interior and exterior requirements specified

o Instrument locations justified by area surveys

o Instrument calibration requirements specified

o Instrument loss / test abort criteria delineated

o Instrument error analysis performed

o Type B and C test results correction to Type A test results specified

o Venting of internal isolated volumes required

o Isolation valve closing mode specified to be the normal mode

o Proper postaccident system alignment to prevent creation of

artificial leakage barriers specified

o Quality control inspection specified

o Test log entries required for repairs needed to complete test

o Acceptance criteria specified

o Data acquisition requirements specified

o Data analysis technique specified

o Method of depressurization specified

The NRC. inspectors verified that the instrument calibration certifications

traceable to the U.S. National Bureau of Standards for the resistance

temperature detectors, humidity measuring devices, pressure gauges, and

the flowmeter used in the verification test had been reviewed. The

guidelines of ANSI /ANS-56.8-1981 were used to select the instruments for

the ILRT. The formula from the Instrumentation Selection Guide (ISG) was

used during the ILRT to ensure that the data acquisition system accuracy

was sufficient to provide reliable test results. This formula utilizes

the systematic error of each sensor to determine an overall value for the

data acquisition system. The instrumentation system for the ILRT was

based on a computer controlled data acquisition system capable of reading

all sensors rapidly, storing the information and then outputting to the

computer for conversions and calculation of the data. Bechtel Calculation

No. 2R569MC5887, Revision 0, "CLRT Volume Fractions," provided the

. - _ _ _. . - - - - . . . . .. - - - .- .

. ,

7

calculational basis for the volumetric distribution of the resistance

temperature defectors located throughout the containment. This

calculation was reviewed by the NRC inspector. -

Af ter a period of 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> at 31.8 psig to allow for degassing of

structures and components inside containment subsequent to the SIT,

,

pressurization of the containment for the ILRT commenced. After the

internal pressure reached 37.5 psig, the compressors were shut down and

'

isolated and the stabilization period commenced. The atmosphere is

considered stabilized when the rate of change of containment temperature

,

averaged over the last 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> minus the rate of change in containment

temperature averaged over the last hour is less than 0.5 F/ hour. After

the stabilization criteria was satisfied, the ILRT test director declared

the start of the official 24-hour test. Continuation of the test

indicated convergence of the calculated leak rate and the upper confidence

limit below the allowable leakage. At completion of the 24-hour test, the-

4-hour superimposed leak verification test was performed. The NRC

'

inspector also witnessed this portion of the ILRT and the result between

.

the calculated and imposed leakages was found to be within the 25 percent

l

allowable leakage (La) limit.

r

1 .

Subsequent to the performance of the test, the NRC inspector obtained the

! raw data and computed the leakage rate in accordance with the Mass Point

i

Data Analysis technique. The computations performed were compared with

! the licensee's results for the purpose of verifying the calculational [

4

procedure and confirming the results. This analytical technique confirmed

.

the acceptability of the results obtained by the licensee. The data

! providing the as-left values for the type B and C tests were also

, reviewed.

No violations or deviations were identified,

f

4. Preoperational Test Procedures

, The NRC inspector reviewed preoperational test procedures which

,

demonstrated the response of the plant's engineered safety features under

.

both normal accident and accident coincident with the loss of offsite

l power conditions. The tests were scheduled to be performed in late

j April 1987. The tests were reviewed for compliance with FSAR commitments

! and adherence to Regulatory Guide 1.68 principles. Within the scope of

i the inspection, the procedures were found to comply with the stated

requirements. The specific tests reviewed were:

1-SF-P-01, Safeguards Systems Response - No Blackout

1-SF-P-02, Safeguards Systems Response - Plant Blackout

No violations or deviations were identified.

,

,

I

i

. .c_-..----..,. - _ _ _ _ . _ . - _ _ . , y7 , ,,_ ,. ._._. _ _ _ ..m- _ , . . . --._., .,,._ .,,- ,__ -, ,- , ~,. ,,.. ,4 .. ,,--

.__ ___________________ - _ - _

f

.' ,

8

5. Preoperational Test Results Review

The NRC inspectors began the review of results for selected completed

preoperational tests. The reviews were done to verify that the testing of

systems met specified acceptance criteria, problems encountered during

testing were properly resolved, appropriate reviews of tests results were

performed by the licensee, and approved administrative controls were

followed during the conduct of testing. The tests reviewed included:

1-MS-P-02-01, Main Steam Isolation Valve Logic

1-MS-P-03-01, Main Steam Power Operated Relief Valves and Main Steam

Dump

1-PK-P-03-01, IE AC Power Distribution Train C

1-RC-P-01-01, RCS Cold Hydrostatic Test

l- 1-RC-P-05-00, RCS Pressurizer Relief Tank

l 1-RC-P-13-00, RC Pump Check

l

l

4 1-RH-P-01-01, RHR System Train A

1-RH-P-02-01, RHR System Train B

1-RH-P-03-01, RHR System Train C

1-RM-P-01-00, Reactor Makeup Water System

1-RS-P-02-00, Rod Control System

1-SI-P-01-01, SI Train A/B/C and Common Logic

1-SI-P-02-00, SI Accumulators

1-SI-P-04-00, SI Train (A,B,C) Performance

1-SP-P-01-00, Reactor Protection Logic

'

, 1-SP-P-02-00, Reactor Protection Master Relay

1-VA-P-02-01, 120V AC Class IE Vital Power Channel II

Based on the reviews of the above tests, the NRC inspectors had the

,

following comments.

a. The NRC inspectors noted a large number of instances in which the

"

administrative requirements of Startup Administrative

Instruction (SAI) 18, "Preoperational Testing," were not followed.

The instances included failure to use the test change notices (TCN)

,

_ _ _

re

-

--

. .

9

to correct procedure errors, failure to make chronological log

entries for events specified in SAI 18, and a person other than the

person making a verification entry in a test procedure correcting

that entry. These administrative problems were discussed with the

licensee's startup manager and members of his staff. They stated

}thattherequirementsofSAI18havebeengraduallyputinplace

through the five revisions of the procedure, and that future

,

preoperational test procedures should demonstrate stricter adherence

to the present administrative requirements.

b. In at least two procedures (1-SI-P-01 and 1-PK-P-01), TCNs were

generated to change test requirements, but the TCNs made no

references to the document or drawing that justified the change.

Justification for changing Steps 7.9.67 and -71 of 1-SI-P-01 from 15

to 19.4 and Step 7.5.95.2 of 1-PK-P-01 from black to red is

considered an open item pending HL&P providing the needed

justification and is identified as 498/8708-03.

c. The acceptance criteria for Steps 7.3.2, 7.3.41, 7.3.44, 7.4.20,

7.6.2, and 7.9.41 of 1-SI-P-04 were not met during testing, and the

NRC inspectors had two concerns with the dispositioning of these

nonconforming conditions. First, in each case, the test engineer

signed-off the step even though the acceptance criteria were not met.

The NRC inspectors were told by the licensee that the accepted

practice is to sign off the step as having been performed whether or

not acceptance criteria were met. The NRC inspectors could not find

any procedural guidance to support or prohibit this practice.

In the case of each step specified above, once unacceptable test

results were obtained, testing continued. SSP-8 requires that for

testing to continue after discovering a nonconforming condition, a

'\ conditional release must be obtained from the startup manager and the

quality assurance manager or a determination must be made that the

nonconformance will not affect continued testing. There was no

documentation of either of these conditions being met, and the NRC

inspectors could find no procedural guidance concerning who could

make the above determination.

The licensee explained that, although not documented, in each case

the test engineer made such a determination and, though not

proceduralized, a decision on the part of the test engineer was what

was intended by SSP-8. The NRC inspectors emphasized the need to

properly document the basis for continuing testing. This relates, in

part, to a and b above.

d. The NRC inspectors noted that in almost all procedures reviewed, the

" Witness" blocks, used for verifying the removal of temporary jumpers

used for testing, were signed days, weeks, and, in one case, months

after the test. This practice raised two questions. First, how

could someone witness jumper removal days after it was performed?

Second, how was the licensee realizing the full intent of the second

..

.. . .

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _

. .- _ ._ - - - . _ .

d

'

. .

10

.

verification of jumper removal if a missed jumper could remain in the

system for long periods, potentially invalidating further testing?

The licensee responded to the first question by saying that the

initial blocks for jumper removal should have been more properly

labelled " Verification" rather-than " Witness." In response to the

second question, the licensee will review the practice of delaying

verification of jumper removal.

Two specific cases of contradicting verification dates will require

formal resolution. In 1-RC-P-13, QC verification signatures were

made 1 day later than the test engineer's verification in

Sections 7.5.28-30 and -32, and 7.6.73, .74, .76, .77, .79, and

,

.80. In 1-MS-P-02, QC verification signatures were made 1 day

i

'

earlier than the test engineer's verification in Sections 7.1,

7.16.32 .39, 7.17.1 .36, 7.19, and 7.20. These two cases of

contradicting entries are considered an open item (498/8708-04).

6. Startup Testing Program

i

During this inspection period, the NRC inspectors began reviewing the

startup testing' program. The NRC inspectors crovided the licensee

a listing of 23 Regulatory Guide 1.68 line items which could not be

4

closed. Major issues were as follows:

. a. Licensee's system for taking credit for preoperational testing and

i some surveillance-tests as coverage for RG 1.68 line items.

'

b. The need for additional involvement of operations and Plant

Operations Review Committee (PORC) in the evaluation of acceptability

>

of preoperational tests for satisfaction of RG 1.68 requirements.

'

The licensee committed to developing additional information which will be

>

tracked as Open Item 498/8708-05.

f

No violations or deviations were identified.

.

7. As-Built Plant to Documentation Reconciliation

The NRC inspectors inspected selected systems to determine that they were

L installed in accordance with commitments contained in the FSAR and

'

referenced drawings and specifications. In performing this inspection,

mechanical and fluid system walkdowns were performed. Also, draf t TS

surveillance test procedures were checked to be sure they could be

accomplished for the as-built system. Portions of the controls and

instrumentation were verified to conform to the descriptions contained in

the FSAR. The following systems were selected for walkdowns:

o Reactor Coolant System (RCS)

4

, , _ ... _ _ . _ _ - _ . . _ _ _ , _ _ . -

. ..

11

o  : Chemical Volume Control System

o Reactor Water Makeup System

o RHR System

o .High. Head Safety Injection System

o Low Head Safety Injection System

o Accumulator Injection System

o Containment Spray & Spray Additive Systems

o Control Room Emergency Air Cleanup System

o Auxiliary Feedwater System

o Emergency Diesel Generator Support Systems - Air, Lube Oil, and

Fuel Oil

o 480 VAC MCC EIA1

o Fuel Building Exhaust (HVAC) System

o -Containment Ventilation Subsystems

o Essential Cooling Water System

Selected systems generally conformed to the FSAR descriptions. For the

few discrepancies observed, the NRC inspectors verified that appropriate

design change packages existed and action had been taken to update the

FSAR drawings and descriptions.

No violations or deviations were observed.

'

'8. RHR/CCW Water Hammer Incident

a. Description of Incident

During hot functional. testing (HFT) on Unit 1, the RCS was being
maintained at 350 F and 350 psig with four reactor coolant pumps in

i operation. CCW was in service with all three pumps operating and all

! three RHR heat exchangers on line. Trains A and C of the essential

'

cooling water (ECW) were in service supplying only Trains A and C

ECW/CCW heat exchangers. Minimal heat loads and mixing of CCW in the

i common portions of the system allowed operation of the B train CCW

i pump without its associated ECW train in operation. Preparations

r

were underway to place Trains B and C RHR in service to support

Preoperational Test 1-RH-P-04, "RHR Thermal Performance Test."

l

t

. . . ._. _ - . . - - .

. .

12

The incident occurred while an operator was placing two trains of RHR

in service to support the performance of the preoperational test.

>- .The controlling HFT procedure directed that this operation be

performed in accordance with Operations Work Order

Request (0 WOR) 1-RO-RH-236. This 0 WOR is a modified version of the

normal Operating Procedure IP0P02-RH-0001, Residual Heat Removal

System Operation, for use during HFT only. While performing this i

procedure, the operator failed to close the RHR Heat Exchanger Outlet -

Valves (RH-HCV-865/866) as directed by the procedure. This resulted

in initiation of flow of hot RCS fluid (350 ) through the RHR Heat

Exchangers when the Cold Leg Injection valves were subsequently

opened. Since CCW to the heat exchangers had been terminated at the

verbal direction of the Startup Test Director to enhance heatup of

the RHR loops, no cooling medium was provided and rapid heatup and

void formation of the CCW in the heat exchangers occurred.

L When the RHR Heat Exchanger CCW Outlet Isolation valves were

reopened, CCW flow was established to the C Train RHR Heat Exchanger

only. This occurred because CCW Pump B had been secured to clear

flow alarms on CCW Trains B and C. This resulted in Train B RHR Heat

Exchanger being without cooling water for a longer period of time.

This prolonged no flow condition permitted a greater degree of

heating and void formation in the B RHR Heat Exchanger which

contributed to a' greater degree of water hammer on that train.

f

This incident was caused by the operator's failure to follow

procedures in that he skipped two steps in Procedure 1-RO-RH-236 and

the Startup Test Director's failure to follow procedure by verbally

directing a change.in the approved preoperational test procedures

instead of using the authorized TCN method. These actions constitute

'

an apparent violation (498/8708-01). This incident resulted in minor

water hammer in Train C CCW and a greater water in Train B CCW. The

Train B water hammer resulted in damage to pipe hanger, supports, and

the CCW piping itself. The system was not breached nor was it

overstressed, based on engineering analysis. The licensee took

prompt corrective action on problem analysis and system repairs.

Further review of this incident will be documented by the licensee in

the final 10 CFR 50.55(e) Report and Station Problem Report.

,

b. Technical Review

l The NRC inspector examined two runs of CCW system piping supplying

i

the jacket side of RHR Exchanger 1B that was involved in a water

hammer incident on March 11, 1987, during a preoperational test.

Based on the examination and interviews with licensee personnel, the

NRC inspection initially concluded that there was no apparent damage

.

to either the piping or connected components. Several pipe supports

l

were damaged to varying degrees which have been identified and

addressed on nonconformance reports. The licensee reported the event
pursuant to 10 CFR 50.55(e) on March 12, 1987. Pending conclusion of

!

!

_.- _ _ . . _ . - - . . . _ _ _ . . . . _ _ _ . . - , _ . - _ _ _ _ _ _ _ , _ _ _ . . _ . , _ . _ , . . . _ _ _ _ ____ _____ ___

. .

13

the licensee's evaluation of this matter, which is to be documented

in a report to the NRC, this matter will be considered an open item

(498/8708-06).

No additional violations or deviations were observed.

9. Operational Staffing

The NRC conductad a review of the organizational staffing and staff

>

qualifications of personnel assigned to the operational phase for Unit 1.

Discussions with appropriate personnel, reviews of organization charts,

reviews of 55 personnel resumes, and reviews of certification records

indicated that the operational staffing was in accordance with the STP

FSAR and the licensee's commitments to ANSI N18.1 with the following noted

exceptions:

a. The Manager of Reactor Operations position is vacant. This vacancy

and the overall level of nuclear plant operational experience

requires further evaluation.

b. The Independent Safety Engineering Group (ISEG) has not been fully

staffed. The Director of ISEG has been named; however, the

additional four engineers have not been selected. The licensee is

committed to the formation of the ISEG prior to fuel loading of

Unit 1.

c. The Operational QA organization described in Amendment 54 to the FSAR

differs from the in place organization. Discussion revealed that an

Amendment 58 to the FSAR is in preparation for submittal to NRR. A

review of the draft Amendment 58 revealed the proposed organizational

submittal to be in accordance with the existing organizational

structure.

Filling the Reactor Operations position, completing evaluation of

operational experience, and implementation of ISEG will be tracked

collectively as Open Item 498/8708-07.

No violations or deviations were identified.

10. Training and Qualification Programs

The NRC inspectors reviewed the licensee's training programs for licensed

operator and nonlicensed staff to verify that regulatory requirements and

license commitments are being met or that programs have been developed to

implement the training requirements and commitments. The administrative

programs to ensure that classroom and simulator training is based on

up-to-date training materials that reflect the as-built condition of the

plant and approved procedures were also reviewed.

.

The licensee has clearly established responsibilities for administering

the training programs including evaluating, scheduling, assigning

. .

14

qualified instructors, examining, retraining, and record keeping. The

Manager, Nuclear Training oversees the implementation of the training

program and is assisted through direct line responsibility by the Training

Manager, Operation Training Division; Training Manager, Staff Training

Division; and the General Supervisor, Program / Administration Support

Section. The NRC inspector noted after discussions with training

management personnel that the licensee has established a strong commitment

to provide qualified personrel to operate and maintain STP. One example

of this commitment is that the licensee is presently greater than

70 percent complete with the program development for the 10 Institute for

Nuclear power Operations (INPO) training programs needed for

accreditation.

The NRC inspectors reviewed the licensed operator training program and

verified that the following program elements have been established and

implemented when required for:

o new reactor operators (RO);

o upgrading R0 licenses to senior reactor operator (SRO) licenses;

o qualifying instructors and shift technical advisors (STAS); and

o requalification of R0s and SR0s in accordance with the requirements

of 10 CFR 55, Appendix A.

The licensee has demonstrated their commitment to provide an effective

' licensed operator training program as evidenced by the NRC first cold

license exams. The results of the exams were that 41 of 46 SRO candidates

passed the exam and the only R0 candidate passed the exam. The first

requalification cycle for these individuals began in April of this year.

The licensee has completed the first cycle training material for the

requalification program. The first group of plant equipment operators is

presently going through the RO training program. The progress of each

license candidate is being evaluated by weekly written and/or oral exams.

The results of these evaluations are used to determine what additional

training the individual requires or if any other actions should be taken.

The licensee also utilizes a fully operational reactor simulator located

at the STP site. The presence of the simulator should enhance the overall

effectiveness of both the initial and requalification training programs.

j

l The NRC inspectors reviewed the licensee's program for nonlicensed staff

i training and verified that personnel are being trained in the areas of

administrative controls, industrial safety, fire fighting, and QA. The

licensee demonstrated a strong commitment to the training of nonlicensed

staff personnel; however, development of the on-the-job training (0JT)

l

program has not been completed. The complete development of this program

j will require a concerted effort between the applicable user groups and the

t training department. The NRC inspectors noted that the licensee has

dedicated several training personnel to complete the OJT program in the

j

past few months.

!

!

!

!

. .

15

Because of the manhours required to complete the 0JT program, the licensee

does not believe the task can be completed adequately prior to their

projected fuel load date. The NRC staff places great importance on

licensees' programs which provide training for personnel in the

performance of specific tasks such as complicated surveillance tests,

major equipment repair, major plant systems tests, and other special

procedures for which the DJT program is an integral part of that training

program. Based on the importance of the OJT program, the licensee must

provide supplemental training to plant personnel in the area that will be

covered by the DJT program until the OJT program has been developed and

implemented. The implementation of the supplemental training program

pending completion of the OJT program is an open item (498/8708-08). The

training of QC inspectors is presently being carried out through the QA

department. The training department has planned to take over the training

of QA/QC inspectors and to also provide training for engineering support

personnel such as ISEG. The development of these training programs will

be reviewed during subsequent NRC inspections.

The NRC inspectors also reviewed the licensees administrative programs for

ensuring that classroom and simulator training is based on up-to-date

training materials that reflect the as-built condition of the plant and

approved operating procedures as well as events or conditions identified

by the NRC, INPO, or other facilities. The licensee has established a

program for implementing changes to the facility and procedures into the

lesson plans. In addition, STP personnel can request training through

their supervisor through the use of the " Request For Training Assistance"

form, Modifications to the simulator were also reviewed and found to lag

only 5 months behind changes to the Unit 1 control panel which

demonstrated that plant modifications were being incorporated into the

simulator.

No violations or deviations were identified. ,

11. Reactor Coolant System - Loss of Cleanliness Recovery Program

On April 6,1987, the resident inspector accompanied by a regional reactor

inspector entered the reactor coolant system to independently verify

damage incurred by the resistance temperature detectors (RTDs) and to

inspect for screen remnants lost during HFT. During their entrance, the

NRC inspectors noted a general disregard of the principles of foreign

material exclusion and personnel and material accountability. At that

time various work, internal to the reactor coolant system, was being

performed via a startup work request (SWR). Rework via an SWR subsequent

to system turnover from the construction activity requires the

implementation of SSP-22. Section 2.2 of SSP-22 clearly defines the

applicability of the procedure.

Section 5.4.2 of SSP-22 applies to cleanliness controls of

,

systems / components after turnover from the construction activity and

requires the following:

_ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ - _ _ _ - _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

.. .

16

o 5.4.2.1 Performance of activities associated with a SWR shall

require additional attention to internal cleanliness as

outlined within this section.

o 5.4.2.2 Upon receipt.of a SWR, the appropriate discipline field

engineer (DFE) shall determine the following to preclude

entry of debris / contaminants into a system, if activity

exposes internal surfaces:

(a) Specific area controls required.

(b) Special methods to be utilized for entering the

system.

(c) Special methods required for maintaining system

cleanliness during performance of the activities.

The NRC inspectors discovered these requirements were clearly violated.

The reactor cavity and all hot and cold legs were open to a cluttered

construction type environment. Workmen entering the system did not have

their personal items and tools lanyarded to themselves and area controls

were insufficient. This is an apparent violation of Criterion V of

Appendix B of 10 CFR 50, which is implemented by the STP project GA plan

Section 5.2.1, in that the licensee failed to follow established

procedures for maintaining cleanliness (498/8708-02).

This situation was brought to the attention of project management the same

evening and management's response was that controls were deliberately

dropped because recleaning would have to be performed subsequent to

further work on the system. On April 7, 1987, Operations QC was notified

of the situation. They agreed that the ongoing work was not in

conformance with SSP 22 and issued Nonconformance Report (NCR) SN-03315 on

April 8, 1987. The NCR reiterated the deviations from SSP 22 and

ANSI N45.2.1-1973. On the evening of April 7, 1987, the NRC inspectors

further discussed the situation with the project manager, the deputy

project manager, and the startup manager. The NRC inspectors acknowledged

understanding of the logic behind the decision to abort cleanliness and

accountability control, but expressed concerns that cleanliness level B

was not formally relaxed and that present cleanliness controls were

inadequate and not in compliance with approved procedures.

No other violations or deviations were observed.

12. TMI and GL 83-28 Action Items

The NRC inspector and consultants examined the licensee's conformance with

the requirements set forth in NUREG-0737 and GL 83-28. The following

describes the NRC's position, observations, conclusions, and current

status of the TMI and GL 83-28 action items:

. .

17

(Closed) Generic Letter 83-28 Item 1.1 Post-Trip Review

Licensees and applicants shall describe their program for ensuring that

unscheduled shutdowns are analyzed and that a determination is made that

the plant-can be restarted safely.

A review was conducted of the applicant's response to item 1.1 of GL 83-28

(Salem ATWS) Post-Trip review process. It was determined by a point by

point review, that the STP Procedure OPGP03-ZO-0022, " Post-Trip Review,"

meets the requirements of 83-28 Item 1.1 in all areas.

Item 1.1 of GL 83-28 is considered closed.

(0 pen) TMI Item II.K.1.10 Operability Status of Safety-Related Systems

Review and modify as necessary your maintenance and test procedures to

ensure that they require:

o Verification, by test or inspection, of the operability of redundant

safety-related systems prior to the removal of any safety-related

system from service

o Verification of the operability of all safety-related systems when

they are returned to service following maintenance or testing

o Explicit notification of involved reactor operational personnel

whenever a safety-related system is removed from and returned to

service

The following procedures were examined to see if they fulfill the

requirements stated in the NRC position:

o OPGP03-Z0-0004, Part 4.10.6.1

o OPGP03-Z0-0001, Part 5.2.1.a

o OPGP03-ZO-0004, Part 4.10.7

o OPGP03-Z0-0003, Parts 4.10.3 and 4.10.23

.

l The examined procedures meet the intent of the NRC position, with one

'

deficiency. The wording in OPGP03-ZO-0004 and OPGP03-ZO-0001 uses

"should" where a stronger "shall" would be more appropriate since the

verification in question is mandatory, not optional. Until the wording

l choice of "should" rather than "shall" is resolveu, this is an open item

i (493/8708-09).

! (Closed) TMI Item I.C.6 Verification of Correct Performance of Operating

Activities

i

The applicant will have a procedure for verifying the correct performance

of operating activities. The Shift Supervisor, or, in the absence of the

Shift Supervisor, the Unit Supervisor (an SRO) should be responsible for

releasing equipment for testing, maintenance, or modifications. Following

, .

18

such activities, a qualified person from the shift crew (who does not have

to be a licensed operator) should be assigned to independently verify the

proper positioning of valves, circuit breakers, and control switches of

the systems that are important to safety,

o STP Procedure OPGP03-ZA-0010, Revision 2, " Plant Procedure

Compliance,' Implementation, and Review," sets forth the methods and

requirements for ensuring proper procedure compliance and independent

verifications.

o STP Procedure OPGP03-ZA-0039, Revision 3, " Plant Procedures Writers

Guide,"_ provides the guidelines for writing a procedure to include

the proper precautions (e.g. permissions required and independent

verifications).

o STP Procedure OPGP03-Z0-0005, Revision 0, " Reactor Operations

Division Conduct of Operations," was reviewed. The review indicated

the Shift Supervisor and Unit Supervisor have proper authority to

release equipment for testing, maintenance, or modifications.

Based on the above information it is concluded that the applicant has met

the requirements for Item I.C.6. Therefore, Item I.C.6 is considered

closed.

(Closed) TMI Item I.C.5. Feedback of Operating Experiences

Each applicant for an operating license shall prepare procedures to assure

that operating information pertinent to plant safety originating both

within and outside the utility organization is continually supplied to the

operators and other personnel and incorporated into training and

retraining programs.

o An interview was conducted with the Lead Engineer of the STP

Regulatory Compliance Group. During the interview, he displayed the

methods used to track, classify, and route inside and outside events

to the various facility departments according to STP

Interdepartmental Procedure IP-2.2Q, Revision 2, " Operating

Experience /In-House Experience Review." He also displayed, from the

License Commitment Tracking System (LCTS), how the operations

department responds to action items of the LCTS.

o The Training Department procedures for LCTS action items was

described by the Manager of Operator Training. The methods used by

the Training Department cover both initial training and retraining of

operators.

On the basis of the above information, it is concluded that the applicant

has coa: plied with NUREG-0737 Item I.C.5. Therefore, Item I.C.S. is

considered closed.

. .

19

(Closed) TMI Item I.C.8 Pilot Monitoring of Selected Emergency Procedures

for Near-Term Operating License Applicants

Applicants will be required to correct any deficiencies identified by an

NRC sample audit of selected emergency operating procedure (EOPs) before

full power operation.

o STP SER (NUREG-0781) Section 13.5.2.3 states, "This pilot monitoring

program was used on an interim basis for evaluation of applicant's

E0P's before staff approval of generic technical guidelines and staff

development of the long-term program for the upgrading of E0P's.

This is no longer necessary because the NRC has approved the

Westinghouse Emergency Response Guidelines (ERG's) and the applicant

has committed to develop E0P's based on the ERG's."

o The applicant has in place all applicable E0Ps, as recommended by the

Westinghouse ERGS. The effective dates for these procedures are

01-05-87 (42 procedures) and 02-23-87 (6 procedures).

o Four STP E0Ps were reviewed and found to be in compliance with the

format, intent, and content of the Westinghouse ERGS. These

procedures are:

o IPOP05-E0-E000, Revision 1, " Reactor Trip or Safety Injection"

o IPOP05-E0-E010, Revision 1, " Loss of Reactor or Secondary

Coolant"

o 1 POP 05-E0-ES02, Revision 1, " Natural Circulation Cooldown"

o 1 POP 05-E0-EC00, Revision 1, " Loss of All AC Power"

Item I.C.8 is considered closed.

[0 pen) TMI Item I.D.1 Control Room Design Review

All licensees and applicants are required to conduct a detailed control

room design review (DCRDR) to identify and correct design deficiencies.

o STP Safety Evaluation Report (SER), NUREG 0781, states in Section 18

that the applicant shows a commitment to comply with the requirements

of this item. However, the SER further states that to complete the

DCRDR activities, the following items must be resolved:

o Provide the results of the verification and validation program

for the final E0Ps to confirm that the instrumentation and

control needs have been adequately identified and satisfied.

o Provide the results of the investigation of the green

Roto-tellite indicating lights in the control room under actual

operating conditions.

.- .. - - - .-. -

. - , _ - - - . . - - _ . . - . _ _ - . - - -

-

, ,

20

o Provide the results of the surveys of the lighting, sound,

meter, and communication system, when planned work in the

control room is completed.

o A letter from M. R. Wisenburg, STP Deputy Project Manager to

. Vincent S. Noonan of the NRC Pressurized Water Reactor (PWR) Project

Directorate No. 5, dated December 26, 1986, (ST-HL-AE-1864) contains

Addendt.m 1 to the Human Engineering Deficiency (HED) Resolution

Report and Addendum 2 to the Executive Summary. These documents

include the results of the green Roto-tellite indicating light

investigations in the control room under actual operating conditions

(Pages A-7 and A-8 of the HED report and Page S-1 of the Executive

Summary) and conclude that, after modifications, the visibility of

these lights under actual operating conditions is acceptable.

o A letter from M. R. Wisenburg, STP Deputy Project Manager to

Vincent S. Noonan of the NRC PWR Project Directorate No. 5, dated

December 23,1986, (ST-HL-AE-1860) contains the initial submittal of

the E0P Validation Report. Control panel deficiencies and problems

identified during the E0P validation each have an associated

resolution identified with them. E0P problems encountered during the

validation process are documented, and their resolutions are

.

addressed in the STP Procedures Generation Package (PGP).

Item I.D.1 remains open (498/8708-10) pending submittal of the results of

the surveys of the lighting, sound, meter, and communication system

, referred to in the STP SER.

l (Closed) TMI Item I.A.1.1 Shif t Technical Advisor (STA)

Each licensee shall provide an on-shift technical advisor to the Shift

Supervisor. The STA may serve more than one unit at a multiunit site if

'

qualified to perform the advisor function for the various units.

I o STP SER 13.2.2 provided the conclusion that the-STA Training program

', was acceptable.

l o A review of STP Station Procedure OPGP03-ZO-0008, Revision 0, " Shift

'

Technical Advisor," outlining the duties, responsibilities, training,

experience, and retraining, was conducted and found to satisfy the

requirements of NUREG 0737.

! o An interview was performed with an STP Reactor Engineer qualified as

STA to determine the scope of STA training, present functions, and

'

the staffing levels of the STAS (present and near future). The

interview provided information that the STA program is following the

training program and station procedures.

Item I.A.11 is considered closed.

!

l

!

i

. .

21

.( Closed) TMI Item I.A.2.1.4 Immediate Upgrade of R0 and SRO Training and

Qualifications - Modify Training

Licensees and applicants shall review their training programs and upgrade

them, as necessary, to include items relating to TMI-2 lessons learned.

Any necessary training program modification must be in place prior to fuel

load.

o STP SER (NUREG 0781) concludes in Section 13.2.1.3 that the STP

training program meets the requirements of I.A.2.1.

o STP TS 6.4.1 requires that the training program shall include the

requirements of Sections A and C of Enclosure 1 of the March 28,

1980, NRC (H. R. Denton) letter to applicants and licensees

concerning qualification of reactor operators,

o STP Interdepartmental Procedure IP-8.8, Licensed Operator Training

Program, stipulates operator and instructor selection criteria and

licensed operator training requirements. These were reviewed and

found to be consistent with the requirements of STP TS 6.4.1.

o STP Interdepartmental Procedure IP-8.9, Licensed Operator

Requalification, provides instruction for the conduct of licensed SRO

and RO requalification. This procedure was reviewed and found to be

consistent with the requirements of TS 6.4.1.

Item I.A.2.1.4 is considered closed.

[Open) TMI Item I.C.4 Control Room Access

Licensees are to assure instructions are in place which cover the

authority and responsibilities of the person in charge of control room

access, and establish clear lines of authority and responsibility in the

control room during emergencies,

o STP' SER (NUREG-0781) Section 13.5.1.2 states that the applicant has

committed to limit access to the control room,

o STP Procedure OPGP03-ZO-0005, Revision 0, Reactor Operations Division

Conduct of Operations, Section 4.1, was reviewed with the following

findings.

o Section 4.1.1 states that if the Unit or Shift Supervisor deems

the number of people in the control room to be excessive, he has

authority to direct excess people to leave and may require

personnel who need further entry to obtain his prior approval,

o Section 4.1.2 states that the individual screening for control

room access shall be controlled by the security system.

__ _-

. .

22

o Section 4.1.3 states that during a reactor trip or other plant

abnormality "it is recommended that all personnel not directly

involved with the recovery leave the control room. Assistance

from other persons shall be determined and requested by the

Shift Supervisor, Unit Supervisor, or the Reactor Operator."

The language used in Section 4.1.3 of OPGP03-Z0-0005 is not strong enough

to " establish clear lines of authority and responsibility in the control

room during emergencies." Conspicuously absent are directions which

require all nonessential personnel to leave the control room during

emergencies; instructions which stipulate who, specifically, is

responsible and authorized to control access during emergencies; and

instructions which specify who, specifically, may enter the control room

during emergencies (e.g. licensed operators, the STA, the NRC resident

inspector). Item I.C.4 remains open (498/8708-11) pending clarification

of control room access requirements during emergencies.

(Closed) TMI Item I.C.2 Shift and Relief Turnover Procedures

Licensees are to revise plant procedures for shift and relief turnover to

ensure that each oncoming shift is made aware of critical plant status

information and system availability,

o STP procedure OPGP03-ZA-0063, " Reactor Operations Shift Turnover,"

was reviewed and found to meet the intent of NUREG 0694, Item I.C.2,

as the applicant had committed to in the STP SER Item 13.5.1.4.

o Direct observations were made of the shift relief process, including

discussion with on-duty R0, as to how the turnover check lists were

used and process of turnover accomplished. In addition, the

on-coming crew briefing was observed. The observations indicated

that the procedure noted above is being used to accomplish shift

turnovers and personnel are being made aware of system availability

and critical plant status information prior to assuming control of

the plant.

1.C.2 is considered closed.

(Closed) TMI Item I.C.7 NSSS Vendor Review of Procedures

Applicants are required to obtain reactor vendor review of their low

power, power ascension, and emergency procedures as a further verification

4

of the adequacy of the procedures.

o STP SER (NUREG-0781) 13.5.2.3 was reviewed and states that because

the applicant has committed to implement procedures based on the NRC

approved ERGS, the staff does not consider an additional NSSS vendor

review of the E0Ps necessary. Furthermore, this section states that

STP committed to have the low power testing procedures and power

ascension testing procedures reviewed by Westinghouse.

_ _

- - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ __ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _

- -_ .-. . _ - _. _ - _ - _ _- -

. .

23

I

o Four STP E0Ps were reviewed and found to be in compliance with the

format, intent, and content of the Westinghouse ERGS. These

procedures are:

i o IP0P05-E0-E000, Revision 1, Reactor Trip or Safety Injection

o IPOP05-E0-E010, Revision 1, Loss of Reactor or Secondary Coolant

,

o 1 POP 05-E0-E502, Revision 1, Natural Circulation Cooldown

o IPOP05-E0-EC00, Revision 1, Loss of All AC Power

,

o The Lead Engineer, STP Regulatory Compliance Group, indicated after

4

conversations with an STP Technical Support Supervisor that all

IPEPO4-series procedures (Initial Startup Test Procedures) were

reviewed by Westinghouse. This conforms to the requirement in STP

Procedure OPGP03-ZA-0002 Plant Procedures, Addendum 2, Step 3, which

states that Westinghouse shall be designated to review and comment on

the initial issuance of the initial startup test procedures.

o An STP Reactor Engineer indicated in conversation with the Lead

Engineer, STP Regulatory Compliance Group, that all, or parts of, the

following procedures were submitted to Westinghouse for review and

comment, based upon design features which are unique to STP:

o IPOP05-E0-FRC1 Response to Inadequate Core Cooling

,

o IPOP05-E0-FRC2 Response to Degraded Core Cooling

l o IP0P05-E0-F002 Core Cooling Safety Function Status Tree

a o IP0P05-E0-E000 Reactor Trip or Safety Injection

j o IPOP05-E0-ES13 Transfer to Cold Leg Recirculation

'

Additionally, he indicated that informal constructive interchange between

STP and Westinghouse was ongoing thrauchout the development of the E0Ps.

i TMI Item I.C 7 is considered closed.

,

(0 pen) TMI_ Item _II.E.1.2 Auxiliary Feedwater System Automatic Initiation

! and Flow Indications

i

, The applicant will provide an auxiliary feedwater system (AFWS),

, initiation and flow monitoring capabilities.

.

. o A review was conducted of the STP SER. The staff concludes that the

l AFWS meets the guidelines of NUREG-0737 concerning reliability and

that the AFWS is compatible with staff guidance for unavailability

per Standard Review Plan (SRP) Section 10.4.9.

.

,

o An interview was conducted with two STP startup engineers (SEs) to

i determine the functional capabilities demonstrated by the AFWS system

! during the recent HFT. Both SEs stated, when questioned, that the

AFWS logic, power supplies, flow indication, and valves functioned as

j designed. However, the integrated safeguards test (IST) which will

i

!,

4

l __

. .

( 24

complete the automatic circuitry testing in regard to loss of power,

auto sequenci19, and automatic safety injection actuation remains to

be completed,

o A review was conducted of the training department lesson plans and

system descriptions involving the AFWS to determine if NUREG-0737

items were addressed. The training department's lesson plans covered

all areas of the AFWS design, operation, and procedures. The depth

of training was describe!d as systems training, classroom work, and

simulatortrainingbythhManagerOperationsTrainingandSupervisor

Operations Training.  ;

Item II.E.1.2 remains open (498/8708-12) pending the completion of the IST

and submittal of results and acceptance by NRC.

(Close_d) TMI Item II.E.3.1 Emergency Power for Pressurizer Heaters / Upgrade

Power Supply

Applicants shall provide the capability to supply, from either the offsite

power source or the emergency power source (when off site power is not

available), a predetermined number of pressurizer heaters and associated

controls necessary to establish and maintain natural circulation at hot

standby conditions,

o STP Procedure IPOP05-E0-E000, Revision 1, states the conditions when

the pressurizer heaters are to be loaded onto the emergency diesels.

o An interview was conducted with three STP SEs. They indicated that

the pressurizer heater modifica tion was installed and functioning

properly on the Engineered Safety Features (ESF) power supply,

o STP Plant Electrical Drawing 9-E-PLAA-01, Revision 6, and

9-E-PLAA-01, No. 1, Revision 9, " Single Line Diagram 480V Class IE

Load Center," both show heater groups power coming from ESF supplie:.,

Heater Group "A" from Bus EIA1, and Heater Group "B" from Bus E1C1.

o A review of the training departnent lesson plans indicated that the

training department has ensured operators have received proper

training on the pressurizer heaters.

On the basis of the above information Item II.E.3.1 is considered closed.

(Closed) TMI Item I.A.1.2 Shift Supervisor Responsibilities - Delegate

Non-Safety _ Duties

Administrative functions that detract from, or are subordinate to, the

management responsibility for assuring the safe operation of the plant are

to be delegated to other operations personnel not on duty in the control

room.

_

. .-

25

o Section 13.1 of the STP FSAR, Organizational Structure of Applicant,

was reviewed. It was found that provision is made in the STP

organization for an on-shift administrative aide who reports

functionally to the shift supervisor of the assigned work shift.

o The job description applying to the administrative aide position was

reviewed and found to include administrative responsibilities which

should significantly reduce the burden on the shift supervisor caused

.

by ancillary responsibilities.

!

o Four individuals are currently filling Administrative Aide positions

on shift. The Manager of Administrative Services stated that these

( individuals are assigned to a three-shift rotation such that an

Administrative Aide is assigned on-shift at all times.

Item I.A.1.2 is considered closed.

(Closed) TMI Item II.K.1.17 Trip Per Pressurizer Low Level Bistable

Facilities which use pressurizer pressure for automatic initiation of

safety injection into the reactor coolant system must trip the low

pressurizer level setpoints such that, when pressurizer pressure reaches

the low setpoint, safety injection will be initiated regardless of the

pressurizer level.

o Drawing No. 5Z-10-9-Z-42112, Revision 7, "SSPS Logic Diagram," was

reviewed. It was ascertained from this review that STP does not

utilize pressurizer water level coincident with pressurizer pressure

for automatic initiation of safety injection. When any two of four

channels of pressurizer pressure decrease to a predetermined value

which corresponds to the low pressurizer pressure safety injection

setpoint, automatic safety injection will be initiated. Therefore,

TMI Item II.K.1.17 does not apply to STP.

TMI Item II.K.1.17 is considered closed.

(Closed) TMI Item I.C.3 Shift Supervisor Responsibilities - Corporate

Directive

Applicants and licensees shall revise their procedures to assure that

duties, responsibilities, and authority of the shift supervisor and

control room operators are properly defined,

o STP SER (NUREG-0781) concludes in Section 13.5.1.1 that the

applicant's plans for organization and conduct of the operating shift

crews meet the requirements of 10 CFR 50.54 and NUREG-0694

Item I.C.3. It is the position of the staff, however, that a letter,

signed by the Vice President - Nuclear Plant Operations, be reissued

on an annual basis to all station personnel directing that each shift

. .

26

supervisor has the responsibility of directing the licen ed

activities of licensed operators on the supervisor's shift, pursuant

to 10 CFR 50.54(1).

o STP Procedure OGP03-ZO-005, " Reactor Operations Division Conduct of

Operations," Revision 0, was reviewed and found to include the

duties, responsibilities, and authorities of all licensed on-shift

personnel,

o A letter from J. H. Goldberg to all Nuclear Group Personnel, dated

February 18,1987, " Command Authority for Direction of Licensed

Operations Activities South Texas Project Electric Generating

Station," was reviewed. This letter was found to contain explicit

and clearly defined direction concerning the command authority and

responsibility with which the cognizant shift supervisor is charged.

TMI Item I.C.3 is considered closed.

(Closed) TMI Action Item I.C.1 Guidance for the Evaluation and Development

of Procedure for Transients and Accidents

The licensee should reanalyze and propose guidelines and revise procedures

for small break (SB) loss of coolant accident (LOCA), inadequate core

cooling, and transients and accidents.

o STP FSAR 13.5.2.1.4 indicates the Westinghouse Owner's Group (W0G)

and ERG would be the basis for STP E0Ps.

o SER 13.5.2.3 and NUREG-0737, Supplement 1, identify the need for and

current staff review of PGP. The staff response will be in a

subsequent supplement to the SER (NUREG-0781).

o SSER 1 and 2 indicate that the staff response to I.C.1 is still

pending.

o I.C.1.1.1, Small-break LOCA. The STP Station Procedure IPOP05-E0-E000,

Revision 1, approved January 2, 1987, by the plant manager is " Reactor

Trip or Safety injection," and is said to include the SB LOCA

'

response. Procedure IPOP05-E0-E000, Revision 1, does indeed include

SB response such as verify AFW, leck PRZR PORV, check if steam

generator (S/G) tubes are intact, verify RCS subcooling margin, verify

secondary heat sink, and check for reactor coolant pump (RCP) trip.

There are contingency actions identified of the check results in

negative findings, for example, can't confirm secondary heat sink.

There are cautions to alert the operator to the need for designating

the condition as a site emergency condition when certain criteria are

met; and there are actions and contingency actions to support

maintenance of critical safety functions.

i

!

l

_ _ . _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

. .

27

o I.C.1.2.B. Inadequate Core Cooling. The STP Station Procedures for

inadequate core cooling are:

o IP0P05-E0-F002, Revision 1, " Core Cooling Safety Function Status

Free," approved February 14, 1987, by the plant manager,

o IPOP05-E0-FRC1, Revision ^1, " Response to Inadequate Core

Cooling," approved January 2, 1987.

l o IPOP05-E0-FRC3, Revision 1, " Response to Saturated Core

l Cooling," approved January 2, 1987.

o 1 POP 05-E0-FRC2, Revision 1, " Core Exit TC's Less Than

755 degrees F."

The Core Cooling Safety Function Status Tree indicates which

procedure to activate depending on core exit thermocouples (TCs) less

than 1200 F, RCS subcooling, RVWL upper plenum, and core exit TCs

less than 755 F. The " Response to Inadequate Core Cooling" procedure

meets the requirements of GL 82-33, Supplement 1 to NUREG-0737,

" Requirements for Emergency Response Capability.

o Per GL 82-33, STP has developed " Plant Procedures Writer's Guides,"

for E0Ps as follows:

o OPGP03-ZA-0027, Revision 1, " Emergency Operating Procedures

Preparation, Approval, and Implementation," approved May 15,

1986, by the plant manager.

o OPOP01-ZA-0006, Revision 2, " Emergency Procedures Writer Guide

and Verification," approved August 14, 1986, by the plant

manager.

o Reviewed ST-HL-AE-1848, " Response to NRC Comments on the Procedures

Generation Package," in which an attachment demonstrated how

OPGP03-ZA-0027, Revision 1, (see 6 above) was used to achieve a

completed procedure for " Steam Generator Tube Rupture,"

OPOP09-E0-E030.

o Per GL 82-33, NRC approval of the PGP is not necessary prior to

upgrading and implementing the E0Ps (7.2.b.).

o HL&P All Sets and Volume Procedure Listing indicates that 48

individual E0Ps have been developed and approved to comply with

I.C.1.3.B. " Transients and Accidents Procedure Revision."

Based on the results of the above review the Item I.C.1 is considered

closed.

l

_ _ _ - _ _ _ _ _ _ _ _ _ _ .-.

. .

28

!

l

(0 pen) TMI Item I.A.1.3 Shift Manning

Applicants shall include in their administrative procedures provisions

governing required shift staffing to assure that qualified personnel are

readily available to man the operational shifts in the event of an

abnormal or emergency situation. These procedures shall also set forth a

policy, the objective of which is to operate the plant with the required ,

staff and develop working schedules such that the use of overtime is j

avoided, to the extent practicable, for those persons who perform '

safety-related functions (e.g. , SR0s, R0s, health physicists (HPs),

auxiliary operators (A0s), and key maintenance personnel),

o STP Procedure OPGP03-ZO-000S, Revision 0, " Reactor Operations

Division Conduct of Operations," was reviewed and found to be in

compliance with the staffing and overtime requirements of NUREG-0737,

Item I.A.1.3. Minimum staffing requirements are delineated for all

modes of plant operation including refueling operations, and

direction is stipulated which effectively limits the amount of

overtime authorized to be worked by any individual. TMI

Item I.A.1.3.2, Implement Minimum Shift Crew Requirements, is

considered closed.

o Interviewed the Manager of Management Services Business Support Group

on March 17, 1987. He indicated that a system for tracking

individual overtime to ensure limits are not exceeded is not yet in

place. A procedure for which he is responsible, OPGP02-ZA-0060,

" Overtime Approval Program," is being typed and should be approved

for issuance in the near future. This procedure, when implemented,

will facilitate tracking of overtime for SR0s, R0s, HPs, A0s, and key

maintenance personnel. TMI Item I.A.1.3.1, Limit Overtime, will

remain open (498/8708-13) pending implementation of a verifiable

system for supervisors and other responsible personnel to track

individual overtime worked, and thereby limit overtime usage to

within specified maximum requirements.

(0 pen) TMI Item I.D.2 Plant Safety Parameter Display Console

Each applicant and licensee shall install a safety parameter display

system (SPDS) that will display to operating personnel a minimum set of

parameters which define the safety status of the plant. This can be

attained through continuous indication of direct and derived variables as

necessary to assess plant safety status,

o Reviewed Letter ST-HL-HL-36428, dated February 12, 1987, concerning

an audit by NRC of the STP SPDS. This audit lists five deficiencies

(significant findings) in the SPDS. They are:

o A validation of the capability of the SPOS to rapidly assess the

safety status of the plant should be performed, preferably

before fuel load.

O e

29

o Parameters to determine the status of the (NUREG-0737)

Radiological Control Critical Safety Function (CSF) should be

included in the SPDS.

o Administrative controls sitould be placed on modification to the

SPDS software to insure that the system's capability to provide

a rapid and reliable assessment of plant safety status is not

jeopardized.

o The SPDS should provide continuous display of the status of the

CSFs.

o No formal review of system requirements versus NUREG-0737

requirements was performed.

o Reviewed Letter ST-HL-AE-1934, which is HL&P's response to NRC

concerning noted deficiencies in the SPDS. All of the responses to

audit concerns will require further review by HL&P.

Based upon the two letters above, concerns raised from an audit of SPDS

have not yet been resolved. This item will remain open (498/8708-14)

until the SPDS audit concerns are acceptably resolved.

(Closed) TMI Item II.K.3.12 Confirm Existence of Anticipatory Reactor Trip

Upon Turbine Trip

Licensees and applicants must confirm that their plants have an

anticipatory reactor trip upon a turbine trip. The licensee for any plant

where this trip is not present should provide a conceptional design and

evaluation for the installation of this trip.

o STP SER (NUREG-0781) concludes in Section 7.2.2.4 that the STP

design, which includes an anticipatory reactor trip on a turbine trip

above 50 percent of rated thermal power (P-9 interlock) is in

compliance with the TMI Action Plan Guidelines.

o Drawing No. 5Z-10-9Z-4211 " Reactor Trip Signals Logic Diagram" was

reviewed and found to include logic which feeds the automatic reactor

trip circuitry whenever turbine EHC fluid pressure drops below a

predetermined setpoint (2/3 coincidence) or all four turbine throttle

stop valves are closed (2/4 coincidence), and reactor power is above

a predetermined setpoint (P-9) as sensed by Nuclear Instrument

Channels N41, N42, N43, and N44 (2/4 coincidence).

TMI Item II.K.3.12 is considered closed.

(0 pen) TMI Item I.B.1.2 Evaluation of Organization and Management

Applicants shall establish an on-site ISEG to perform independent reviews

of plant operations.

._ _ _ _ _ _ . .- _ . _ _ .. _-

I

, .

30

o STP SER (NUREG-0781) concludes in Section 13.4.4 that the HL&P

organizations which perform review and audit functions for STP

(including ISEG) are in conformance with applicable guidelines and

standards (including NUREG-0737).

o STP TS (proof and review copy) Section 6.2.3 regarding ISEG was

reviewed and found to be in conformance with the requirements of

NUREG-0737, Item I.B.1.2.

l

o STP ISEG Operating Philosophy Document (OPD), dated February 9,1987, f

was reviewed. This document, prepared by the Director - ISEG, and

'

approved by the Chairman - Nuclear Safety Review Board (NSRB),

4

delineates how the ISEG plans to carry out its functions. It does

not, however, present an item-by-item discussion of how the group

satisfies every stated requirement. The following ISEG OPD

inclusions, relevant to NUREG-0737, Item I.B.I.2, were found to be

in conformance with the requirements of Item I.B.1.2:

o Staffing and Reporting Relationship - The ISEG will have a

multi-disciplimary, five-member technical staff located at the

STP site. The ISEG Director reports to the chairman of the

NSRB, located in Houston, Texas. This reporting relationship

provides the ISEG with a high-level forum for the review of its i

'

determinations.

o ISEG Functions - The ISEG will review the operations at STP with

particular emphasis on assessing the activities which impact

i nuclear safety. These assessments will carry recommendations

for NSRB consideration which will focus on the root causes of

'

events, problems, or undesirable trends. The ISEG will maintain

appropriate relationships with other similar operating plants

and will participate in industry-sponsored groups which bring

together utility personnel performing functions similar to the

STP ISEG.

o On March 16, 1987, the Director - ISEG, was interviewed. He provided

information indicating that the specific procedures relative to

actual performance of ISEG duties have yet to be written, and that

four full-time engineers have yet to be integrated into the ISEG to

satisfy the minimum staffing requirement of NUREG-0737 Item I.B.1.2.

At that time, the ISEG will be considered fully operational.

TMI Item I.B.1.2 remains open (498/8708-15) pending completion of the

following two items which will make the ISEG operational:

o Attaining a minimum staff of five dedicated, full-time engineers

(including the Director - ISEG), located onsite at STP.

l o The issuance of approved procedures which specifically address the

responsibilities and duties of the ISEG.

1

{

!

i

-

. .

31

(Closed) TMI Item II.B.1 Reactor Coolant System Vents

Each applicant shall install RCS and Reactor Vessel Head High point vents

remotely operated from the control room,

o STP FSAR Appendix 7A addresses NUREG-0737, Item II.B.1, in regard to

safety analysis of design for seismic and LOCA events, with

10 CFR 50.44 and 10 CFR 50.46 as the acceptance criteria.

o STP SER Section 5.4.12 concluded that the STP design of the RCS High

Point Vents was satisfactory and meets the requirements of

NUREG-0737.

o STP procedure IPOP05-E0-FRI3, Revision 1 " Response to Voids in

Reactor Vessel," was reviewed to determine the degree of guidance

provided to the operator. This procedure does provide necessary

information to the operator for initiating and terminating vent usage

in emergency conditions.

o STP Procedure 10P02-RC-0003, Revision 1. " Filling and Venting the

Reactor Coolant System," and 10P03-ZG-0001, Revision 2, " Plant

Heatup," provide procedural steps for vent valve lineup and

operations when cold,

o STP TS 3.4.11 provides the operability requirements of the Reactor

Vessel Head Vent System (RVHVS).

o STP Orawing SR149F05001, Revision 6, shows the piping and valve

arrangement of the RVHVS. This arrangement meets the design

requirements as stated in the STP FSAR and was accepted by the staff

in the STP SER,

o The following electrical one-line diagrams were reviewed;

9-E-DJAA-01, Revision 8; 9-E-DJAC-01, Revision 8; 9-E-DJAE-01,

Revision 10; and 9-E-RC19-01, Revision 4. From these drawings it was

determined that the RVHVS is supplied power from a Class IE power

supply.

o The HL&P Company " Pump and Valve Inservice Test Plan" lists the RVHVS

valves with information provided as to class of valves, category of

system, fati position, normal position, and test requirements.

o A tour of the Unit 1 control room was made to determine if the RVHVS

could be operated from the control panels. Indication and control is

available from the control panels.

Item II.B.1 is considered closed.

_

. .

32

(0penj TMI Item _II.B.4 Training for Mitigating Core Damage

_

_

Applicants are required to develop a training program to teach the use of

installed equipment and systems to control or mitigate accidents in which

the core is severely damaged. They must then implement the training

program.

o STP FSAR Appendix 7A states that training is provided as described in

FSAR Section 13.2.1.1.

o The staff concludes in the STP SER that the applicant has met

item II.B.4, which includes all subjects in Enclosure 3 of

H. R. Denton's letter of March 28, 1980. Also, the STAS and all

operating personnel including licensed operators, appropriate

managers, instrument and control (I&C) technicians, HP technicians,

and chemistry technicians shall receive training commensurate with

their responsibilities,

o A review of two lesson plans (CLT 006.03, Revision 0, Small Break

LOCA and CLT 006.02, Revision 0, Post Accident Cooling) used to teach

Mitigating Core Damage to licensed operators (plant manager through

the operations chain) was conducted. The lesson plans met the

requirements of NUREG-0737.

o A telephone interview was conducted with the Staff Training Manager

to determine the training provided to the I&C technicians on

Mitigating Core Damage. He stated that the I&C technicians receive

training from Lesson Plan ICT9.21. This lesson plan adequately

covers the requirements for the !&C technicians.

o An interview was conducted with the Radiation Protection Supervisor

concerning training of HP personnel. He provided a completed, but

unapproved, lesson plan, RPT001.61, " Radiological Aspects of a Core

Damage Accident." The lesson plan coverage is adequate, but the

actual implementation time was not available. In addition, he

provided lesson plan CATTP phase 3, " Radiological Aspects of a Core

Damage Accident," for the chemistry technician, which is implemented

for all chemistry technicians and is adequate in coverage.

Item !!.B.4 is to remain open (498/8708-16) pending verification that the

HP training has been implemented.

f(Closed)T$ystemTMI

soIFio Item !!.K.3.1.8 Testing /_ Installation __of Automatic PORV

The applicant must provide a system which will automatically cause the

power operated relief valve (PORV) block valve to close when the RCS

pressure decays after the PORV has opened,

o FSAR Appendix 7A,Section II.K.3.1, states that automatic PORV block

valve closure is not required in the STP design. The basis for this

.- .. __._ -_-__ - , _ - . __ .. . _ - _ _ _

. .

I 33

i

is found in a study performed by Westinghouse for the WOG in response

i to TMI Item II.K.3.2 - Report On Overall Safety Effect of

Power-Operated Relief Valve Isolation System. The results of this

study, WCAP-9804, concluded that with the incorporation of specific

post-TMI modifications, which have been or will be impleme.ited on

STP, the reduction in PORV of LOCA frequency is such that an

automatic PORV block valve closure system is not required.

o STP SER (NUREG-0781) concludes in Section 15.6.1 that WCAP-9804 is

acceptable on a generic basis, and that the STP design, hardware, and

j

PORV setpoint is acceptable.

'

TMI Item II.K.3.1.B is considered closed.

(Closed) TMI Item II.E.4.1 Dedicated Hydrogen Penetrations

Plants using external hydrogen recombiners or purge systems for

post-accident combustible gas control must have containment penetrations

dedicated to that service only,

o STP design includes two redundant, 100 percent capacity electric

hydrogen recombiners located inside the containment. Therefore, the

requirement for dedicated penetrations for this system does not apply

to STP.

o Procedure IPOP-CG-001, Electric Hydrogen Recombiners is in place,

which addresses post-LOCA startup, verification of operation, placing i

in standby, and returning the recombiners to pre-LOCA condition. ,

,

o The following procedures, which contain steps directing operation of

I the hydrogen recombiners when containment hydrogen concentrations

j reach specified levels, are in place:

o 1 POP 05-E0-FRI3, Revision 1 - Response to Voids in Reactor Vessel

'

o 1 POP 05-E0-FRC1, Revision 1 - Response to Inadequate Core Cooling

o 1 POP 05-E0-FRZ1, Revision 1 - Response to High Containment

Pressure

o In Procedure 1 POP 05-EO-FRZ1 Steps 7.3 and 10.2 both erroneously

.

'

refer to Procedure 1 POP 02-CM-0001. This procedure does not exist;

the references should be to IPOP02-CG-0001.

1 o In Procedure 1 POP 05-E0-FRC1, Step 8.3 erroneously refers to

Procedure 1 POP 02-CM-0001. Again, this procedure does not exist; the

reference should be to Procedure 1 POP 02-CG-0001.

TMI Item II.E.4.1 is considered closed. Open item (498/8708-17) will

i track the procedural errors noted above, it should be noted that the

j

I

l

,

t

_ _ _ _ _ _ _ _ - .- - _ . - ._

. .

34

.

described error exists in all three copies of each procedure; i.e.,

supervisor's copy, primary operator's copy, and secondary operator's copy.

[

(0 pen]TMIItemII.E.4.2ContainmentIsolationDependability

Applicants must comply with the Containment Isolation Dependability by

providing improved diverse isolation, minimum containment pressure

setpoints for isolation, containment purge valve changes, and closure of

purge valves on high radiation,

o STP SER was reviewed with the following acceptable conclusions of the

i

staff: "the applicant has complied with the provisions regarding

i diversity in parameters sensed for initiation of containment

i isolation, identification of essential and nonessential systems,

, automatic isolation of nonessential systems, and closure of

{ containment purge and vent isolation valves on a high radiation

! signal."

. o By a letter dated October 30, 1985, the applicant committed to equip

!' the outboard isolation valves for supplementary purge system supply

and exhaust lines with pneumatic operators. Configuration Control

l Package (CCP) No. IMST0115 was reviewed to determine the status of

valve installation. The CCP shows a Field Notification of Change

Completion dated March 4, 1987.

o A visual check of the plant showed that the valves stated above are

installed in the system indicated.

,

o STP TS were reviewed to verify the required position of the 48-inch

i

'

containment purge valves during power operation, startup, hot

standby, and hot shutdown. TS 3.6.1.7 requires that these valves be

sealed closed and TS 4.6.1.7 provides the surveillance requirements

that the valve positions be verified periodically.

Procedure IPSP03-ZQ-0002, Revision 0, " Routine Passive Instrument

Surveillances for Modes 1, 2, 3, and 4," covers the requirement of

l TS 4.6.1.7. ,

t

o Containment pressure setpoint that initiates containment isolation is ;

i to be reduced to the minimum value compatible with normal operating l

l conditions. The setpoint value and justification is to be provided

by the applicant to the NRC staff in conjunction with the development

of the plant TS per STP SER Section 6.2.4 page 6-13. The setpoint

'

value currently included in the proof and review TS is 5.8 psig. The

NRC staff is reviewing this value for acceptability. ,

l o Procedure IPOP02-HC-0001, " Containment HVAC " was reviewed and found

I to be lacking a General Precaution on maintaining containment

'

I

ressure between the TS limits. Procedure IPOP02-HC-0003,

p' Supplementary Containment Purge," was reviewed and found to have

incorrect values for containment pressure in the General Precaution

section.

I

.

__

_ _ _ -- . .

. ,

,

35

The following subitems of II.E.4.2 are closed:

II.E.4.2.1-4

11.3.4.2.6

II.E.4.2.7 -

II.E.4.2.8

The following are to remain open pending resolution as follows:

o II.E.4.2.5B: All drawings identified in CCP 1-M-ST-0115 are issued

as revised drawing which incorporate the modification changes.

o Procedures IPOP02-HC-0001 and IP0P02-HC-0003 are revised to

incorporate statement and correct values, respectively, as above.

These items will be tracked collectively as Open Item 498/8708-18.

,

(0 pen) TMI Item I.G.1.3 Training Requirements During Low Power Testing

Training will be provided during low power test programs to provide " hands

on" experience for plant evaluation and off-normal events for each

operating shift. It is not expected that all tests will be required to be

conducted by each operating shift. Observation by one shift of training

of another shift may be acceptable. The results of this training will be

documented.

This item requires training during low power testing, and the reporting of

l the results. This item will remain open (498/8708-19) since it cannot be

! completed until low power testing is performed.

(0 pen) SALEM ATWS 2.2 Equipment Classifications and Vendor Interfac_e

(Programs For AITSafe_ty-Related Components), Generic Letter (GL) 83-28

l Licensees and applicants shall submit a description of their programs for

, safety-related equipment classification and vendor interface including

I criteria for identifying components, a description of the information

handling system, station personnel use of the handling system, management

controls, and a demonstration of design verification and qualification for

procurement.

o ST-HL-AE-1274, June 28, 1985, " Response to NRC Generic Letter 83-28,

! Required Actions Based on Generic Implications of Salem ATWS Events,"

2.2, commits to the requirements of GL 83-28, 2.2.

o The Project Q-List identifies systems, structures, and components

that are safety-related. The Project Q-List, 5A479NQ1000, is

consistent with FSAR Table 3.2.A-1, Balance of Plant Quality

Classification of Structures, systems and Components.

o The Project Q-List, Table 1, Item 1.20.0, does not identify any

Q-List items for the Gaseous Waste Processing System (GWPS).

i

_ _ _ _ - . _ _ - _ _ _ _ _

, ,

'

a

of , ,

36

However, FSAR Table 15.7-1, GWPS Failure Analysis (P15.7-6),

identifies that the whole body gamma dose would exceed 0.5 Rem at

both the Exclusion Zone Boundary and the Low Population Zone

Boundary, and therefore, at the site boundary. FSAR Section 3.2 as

,

' well as the Project Q-List identifies that failure of systems, i

'

<

structures, or components that would result in greater than 0.5 Rem

'

a whole body dose at the site boundary should be Safety Class 3 if not

already Safety Class 1 or 2. The Q-List designation of non-nuclear

!

'

safety (NNS) for the GWPS appears incorrectly designated since Safety

, Class 3 would make it a Q-List item. The HL&P Licensing Group stated

'

that the GWPS was designed NNS per RG 1.26, Revision 3, C.2.d, which

t exempts radioactive waste management systems from the 0.5 Rem

criteria. HL&P will pursue a change to the FSAR Section 3.2, and the

Q-List to correct the statement that all systems are inclusive in the

,

0.5 Rem whole body dose criteria.

, o The licensee identified in ST-HL-AE-1274 that it intends to implement

!j the recommendations of the INPO Nuclear Utility Task Action

r

Committee (NUTAC) program for the handling of vendor technical

information, Vendor Equipment Technical Information Program (VETIP).

The NRC inspector interviewed a consultant for HL&P, Operations

l Support Engineering, on the vendor interface. The " Design

Finalization Program Executive Summary" statuses the startup field

validation of safety-related vendor manuals and transmittal of vendor

bulletins and advisories. The consultant stated that replacement

,

vendors and equipment are sought when an existing vendor ceases

l business. Interdepartmental Procedure, Control of Vendor Documents,

STPEGS IP-1.80, Revision 2, approved August 8, 1986, establishes a

'.

single program for the receipt, review, statusing, and distribution

,

of vendor supplied technical information. Interdepartmental

'

Procedure, Nonconformance Control, IP-4.10, approved September 2,

1986, describes resolving nonconformances.

t

o STP Station Procedure OPGP03-ZN-0003, Revision 8, approved March 17,

,

1987, by the Plant Manager, establishes guidance for assigning a

safety classification to maintenance. This procedure is also the

mechanism for corrective action for safety-related equipment that has

defects, deficiencies, deviations, or malfunctions.

o The applicant did not provide any response for the following:

o Plant and corporate managements' oversight activities over

safety-related structures, systems, or components,

o Planned and periodic audits over activities impacting

<

safety-related equipment.

o Verification that vendor-recommended modifications were

implemented on the Reactor Trip System (RTS) breakers.

\,

(

'

i

i

\

o ,

37

o Implementation of a preventive maintenance program for

components where there is inadequate traceability of component

performance to the vendor (vendor can't be identified, went out

of business, or won't supply required information),

i

o Procedures to provide instructions for assigning a safety

l classification to operating and surveillance procedures.

o GL 83-28, Item 2.2, will remain open (498/8708-20) pending resolution

of designation of GWPS components in the Q-List and responses to the

items immediately above.

(0 pen) SALEM ATWS, 3.1, Post-Maintenance Testing (Reactor Trip System

Components)

Applicants shall submit their review of test and maintenance procedures

and TS to assure post maintenance operability testing and submit their

check of vendor and engineering recommendations to ensure that any

appropriate guidance is included in test and maintenance procedures.

Applicant shall identify any TS requirements for post-maintenance testing

that degrade rather than enhance safety.

o STP's response to this position is in ST-HL-AE-1274 and commits to

implementing the requirements.

o EGG-NTA-7159, February 1986, was reviewed and it was found that the

applicant met the requirements of 3.1.3 -- that no TS for

post-maintenance testing degrade safety for the RTS.

o STP Station Procedure OPGP03-ZE-0020, Revision 0, approved January 7,

1987, by the plant manager, describes the post-maintenance testing

program, including initiating requests, criteria and responsibilities

for review and approval, criteria and responsibility for designating

the activity as safety-related, and guidance for determining the

testing to be performed. Section 5.3.1 of OPGP03-ZE-0020,

Determination of Applicable Components, gives guidance on_ identifying

components that should have post-maintenance testing. It was noted

that the master document for identifying safety-related components,

the Project Q-List, is not referenced in Section 5.3.1 of

OPGP03-ZE-0020.

o STP's, " Post-Maintenance Testing Reference Manual," Revision 0,

approved February 28, 1987, describes 17 types of post-maintenance

tests and lists their requirements (e.g., Auto Start Test, Pump

Operability Test, Valve Leakage Test, etc.).

o STP Station Procedure OPGP03-ZM-0003, Revision 8, approved March 17,

1987, by the Plant Manager, establishes criteria and responsibilities

for review and approval of maintenance.Section V of the Maintenance

Work Request Form requires a yes or no indication for i

post-maintenance testing.

,

l

..

- _ _ _ _ _ _

, .

38

GL 83-28, Item 3.1, will remain open (498/8708-21) pending completion of a

change to Procedure OPGP03-ZE-0020 to include reference to the Q-List as

discussed above.

(0 pen) SALEM ATWS GL 83-28/4.5 Reactor Trip System Reliability (Safety

Functional Testing)

On-line functional testing of the reactor trip system, including

independent testing of the diverse trip features, shall be performed on

all plants. (On-line is Modes 1 through 6).

o The NRC inspector reviewed Station Procedure " SSPS Logic Train R

Functional Test," 1 PSP 02-SP-0001R, Revision 0, which was approved

January 25, 1987, by the plant manager.

o The Train S Procedure, IPSP02-SP-00015, Revision 0, was on the plant

procedure computer printout list and was approved.

o FSAR Section 7.2.2.2.3.10.4, Testing of Reactor Trip Breakers, and

Figure 7.1-2 are not consistent with IPSP02-SP-0001R. The bypass

breaker designations in the FSAR, 52/BYR and 52/BYS, have been

interchanged in the procedure, 1 PSP 02-SP-0001R. That is, in the

FSAR, Reactor Trip Breaker 52/RTR is bypassed by Bypass

Breaker 52/BYR and Breaker 52/RTS is bypassed by 52/BYS. But in

IPSP02-SP-0001R Reactor Breaker 52/RTR is bypassed by 52/BYS and

Reactor Breaker 52/RTS is bypassed by 52/BYR. The licensee indicated

that 1PSPS02-SP-0001R is written to agree with wording in the

,

Westinghouse Maintenance Manual and not wording in the FSAR. The

'

FSAR wording, 1 PSP 02-SP-0001R, and Westinghouse Maintenance Manual

should be made consistent to avoid misinterpretation by the operating

staff. On page 39 of 48 of IPSP02-SP-0001R, Step 7.9.12.b should

read " Train R Reactor Trip Breaker-0 pen / Tripped position" not

" Train S Reactor Trip Breaker-0 pen / Tripped position." This requires

a change to Procedure 1 PSP 02-SP-0001R and appropriate review and

approval per TS 6.5.1.6a before this item can be closed out.

o Preoperational Test Procedure 1-RS-P-03 " Reactor Trip Switchgear" was

reviewed. Section 7.6 of this procedure, performed December 12,

1986, satisfactorily demonstrated that opening a Reactor Trip Breaker

with its respective Bypass Breaker closed does not cause a loss of

voltage to the Rod Control Power Cabinets.

GL 83-28. Item 4.5, will remain open (498/8708-22) pending resolution of

inconsistent wording between FSAR and IPSP02-SP-0001R and completion of

IPS02-SP-001R procedure change.

(Closed) SALEM ATWS Item GL 83-28/2.1 Equipment Classification and Vendor

Interface (Reactor Trip System Components)

,

Licensees and applicants shall confirm that all components whose

j functioning is required to trip the reactor are identified as

l

_ - _ _

-.. .

. ._ __ _

. .

39

safety-related on documents, procedures, and information handling systems

used in the plant to control safety-related activities, including

maintenance, work orders, and parts replacement. In addition, for these

components, licensees and applicants shall establish, implement, and

maintain a continuing program to ensure that vendor information is

complete, current, and controlled throughout the life of the plant, and

appropriately referenced or incorporated in plant instructions and

procedures. Vendors of these components should be contacted and an

interface established. Where vendors can not be identified, have gone out

of business, or will not supply the information, the licensee or applicant

shall assure that sufficient attention is paid to equipment maintenance,

replacement, and repair, to compensate for the lack of vendor backup and

to assure RTS reliability. The vendor interface program shall include

periodic communication with vendors to assure that all applicable

information has been received. The program should use a system of

positive feedback with vendors for mailings containing technical

information. This could be accomplished by licensee acknowledgement for

receipt of technical mailings. The program shall also define the

interface and division of responsibilities among the licensees and tFe

nuclear and non-nuclear divisions of their vendors that provide service on

RTS components to assure that requisite control of and applicable

instructions for maintenance work are provided.

o The NRC inspectors examined Letter ST-HL-AE-1274, which states that

HL&P has reviewed all components whose functioning is required to

trip the reactor and these components have been properly classified

in the design documents.

o A technical evaluation report (Supplemental SER (SSER) 1, Appendix N)

states that applicable RTS components were verified to be properly

classified. SSER 1 states that the program meets the requirements of

GL 83-28/2.1 (Part 1) and is acceptable.

o A technical evaluation report (SSER 2, Appendix T) states that STP is

a participant in the Westinghouse interface program for the RTS.

SSER 2 states that the program meets the requirements of GL 83-28/2.1

(Part 2) and is acceptable.

Based upon the above information, this item is considered closed.

(Closed) Salem ATWS Item GL 83-28/1.2 Post-Trip Review - Data and

Information Capability

Licensees and applicants, shall have or have planned a capability to

record, recall, and display data and information to permit diagnosing the

causes of unscheduled reactor shutdowns prior to restart and for

ascertaining the proper functioning of safety-related equipment.

_ _ _ _ _ _ _ _ _

. . ... -

.

. .

40

o The NRC inspectors reviewed Letter ST-HL-AE-1274 dated June 28, 1985.

This letter contains a description of the capabilities of the Proteus

Computer System and The Emergency Response Facilities Data

Acquisition and Display System (ERFDADS).

o. STP SSER 1 includes a conclusion that the applicant's post-trip _ 1

review data and information capabilities are acceptable.

,

o The CRTs and typers associated with Proteus Computer System and

ERFDADS were inspected in the Unit 1 control room. The status of the

systems was discussed with a control room operator. Although testing

is continuing on the systems, the CRTs and typers are operating and

it appears the systems will function as described in

Letter ST-HL-AE-1274.

Documentation and inspection indicate the facility has planned the

required capability for post-trip data and information. This item is

considered closed.

{ Closed) Salem ATWS GL-83-28 Item 4.3 Reactor Trip System Reliability

(Automatic Actuation of Shunt Trip Attachment for Westinghouse and B&W

Plants)

Westinghouse and B&W reactors shall be modified by providing automatic RTS

actuation of the breaker shunt trip attachments. The shunt trip

attachments shall be considered safety-related (Class 1E).

o Procedure IPSP02-SP-00012, Revision 0, was reviewed. STP SER Item 5

of Page 15-22, requires that quality assurance criteria set forth in

Appendix B to 10 CFR 50 be met. During a meeting with the QC General

Supervisor and the Audit / Surveillance Supervisor the QA program was

described concerning operational testing of equipment. The program

meets the requirements as indicated in GL 83-28.

,

'

o Procedure IPSP03-RS-0002, Revision 0, " Manual Reactor Trip TAD 0T,"

was completed. It was determined that this procedure meets the

operability test requirements to verify contacts and wiring of the

manual trip circuit before startup after each refueling outage.

Item 4.3 is considered closed.

'

(0 pen) Salem ATWS Item GL 83-28/4.1 Reactor Trip System Reliability

(Vendor-Related Modifications)

All vendor-recommended reactor trip breaker modifications shall be

reviewed to verify that either: (1) each modification has, in fact, been

implemented, or (2) a written evaluation of the technical reasons for not

,

implementing a modification exists.

<

!

o STP has Westinghouse type DS-416 reactor trip breakers installed.

STP SSER 1 (NUREG-0781 Supplement No. 1) states in Section 15.8.2

, .- __ ._. _ . . _ _ _ . __ __ _ _ _ - . _ _ _ , _ , _ , _. - _.

. . _

-. .

41

under Action Item 4.1 that the applicant has committed to implement

all vendor-related modifications before. fuel loading, and that the

applicant's position on Item 4.1 is acceptable.

o Letter ST-HL-AE-1274 was reviewed. It indicated on Page 14 of 18 in

i

Section 4.1 that "HL&P has been informed by Westinghouse that a

~

design discrepancy had been identified in the undervoltage attachment

-

and that Westinghouse intended to replace the undervoltage

attachments on DS-416 reactor trip switchgear. Field change

notices (FCNs) have been issued by Westinghouse for installation and

adjustment of the replacements."

o STP FCN TGXM-10563, Shop Order No. 386, indicates that the

undervoltage trip assemblies in the raattor trip switchgear have been

replaced. This FCN was closed on January 28, 1986.

o Westinghouse Nuclear Service Division Technical Bulletin 83-03 was

reviewed and found to provide the Westinghouse recommendation for a

single method of independently verifying the function of the shunt

^

trip and the undervoltage trip mechanisms of the Reactor Trip

Breakers. It was not intended that a utility would follow this

general procedure verbatim, but would first parform a thorough review

of the general procedure against the plant specific system.

. o STP Procedure ISP02-SP-0001R, Revision 0, " Solid State Protection

System (SSPS) Logic Train R Functional Test," date January 29, 1987,

was reviewed and found to include appropriate procedure steps fo"

testing the Undervoltage Trip Attachment and the Auto Shunt Trip

Function independently of one another.

o Westinghouse Nuclear Service Division Technical Bulletin 84-02 was

reviewed and found to advise all affected plants of a condition which

may exist on DS or DSL Class 1E circuit breakers used for Reactor

Trip or Safeguards Power Breakers. This condition, which should be

. investigated, involves rotential wire damage on the left side,

.

particularly ,in the vicinity of the wire retainer which forms the

extreme lef t coundary of the breaker, f acing the breaker front.

Instruction for dealing with this conditicn (replacement of damaged

wires and providing additional rigidity and mechanical support) are

i' also included in this fechnical Bulletin. STP Procedure OPMP05-NA-0008,

Revision 1, Westinghouse 480 Volt Breaker Test, dated February 24,

,- 1987, was reviewed and found to include a procedural step to insoect

breaker wiring, witn a precautionary note dealing with the left side,

facing the front of-the breaker. Westinghouse Nuclear Service

Division Technical Bulletin No. NSD-TB-84-02, Revision 1, "DS/DSL

Breakers - Potential Wire Damage For Reactor Trip or Safeguards Power

Breaker," is referenced in this procedure. An attempt was made to

ascertain that inspection of Reactor Trip Breakers had actually been

performed and the inspection results documented, but this information

was not made available.

._.

_, __, ,_. -

.__ ___ _ _ _ _ _ _ _ _ - ____ _ . _ . ~.. _. -

.- - - .-

-

.i

42

Salem ATWS Item GL 83-28/4.1 will remain open (498/8708-23) pending STP

submittal of verifiable evidence that inspection of the Reactor Trip

Breakers for potential wire damage has been completed and any deficiencies

noted have been corrected.

13. Licensee Action on Previous Inspection Findings

(Closed) 498/8620-01 - This item concerned the use of ambiguous terms such

as " extent necessary" for criteria in certain preoperational procedures

without offering guidance as to what constitutes " extent necessary." The

specific procedures have been changed to delete such phases. The

procedure changes were reviewed by the NRC inspectors and deemed

sati sfactory. This item is considered closed.

(Closed) 498/8620-02 - This item concerned using acceptance criteria in

, procedures without guidance as to what is acceptable. The specific case

involved fuel handling trolleys and hoists which were required to be

operated without excessive vibration. The criteria in this instance was

found to be superfluous as such abnormalities are routinely watched for

and covered by SAI 18, paragraph 5.3.4. The procedure was changed and

deemed satisfactory by the NRC inspectors.

14. Site Tours

The NRC inspectors conducted site tours independently. These tours were

made to assess the protection on inplace safety-related equipment, plant

status, and to observe testing. The areas toured included: Unit 1 -

Mechanical and Electrical Auxiliary Building (MEAB), Reactor Containment

Building (RCB), Fuel Handling Building (FHB), and the Emergency Diesel

Generator Building. With the exception of the violation noted in

paragraph 11, the NRC inspectors noted a marked improvement in the

maintenance of areas and equipment turned over to the Nuclear Plant

Operations Department (NPOD).

r

! No additional violations or deviations were identified.

15. Review of The Manual Trip Circuit

,

Because of a drawing error relative to the electrical location of the

manual trip circuit in relation to the output transistors Q3 and Q4 in a

'

l similar Westinghouse designed plant with a SSPS, the NRC inspector inspected

,

facility Drawings 14926-0387(2)00171-BWN and 14926-0387(2)00172-BWN.

'

These drawings correctly depict the manual trip circuit downstream of the

output transistors Q3 and Q4. .

16. Procedures Review

The NRC procedure review team by review of selected procedures, personnel

interviews, and system walkdowns, assessed the applicant's procedures for

adequate administrative controls, technical accuracy, and compliance with

, , ,--r--. , - . , , , , , , , -,- - - . , --,n- , - , - - - . ,,, , , , - , --n- - ,--,n.

. . . ___ _ __ _ _ _ _ _ _ _ _ _ _ _ _ _ __

4

o. .

-

43

regulatory requirements. A selected number of the procedures reviewed

were field verified by walking down the applicable system and verifying

that the procedure reflected as-built conditions.

Procedures in~ the following areas were selected for review:

i

'

a. Plant

b. Operating

c. Maintenance

d. Emergency Operating

e. Off-Normal Operating and Alarm Response

f. Surveillance

Following is a discussion of the NRC inspection effort in each of'these

areas including a list of the specific procedures reviewed and NRC

i inspector observations and findings. (The above letters identify the

discussion for the corresponding procedure category below.):

'~

a. Plant Procedures

(1) Review Of Program For 10 CFR Part 50.59 Safety Evaluations

The NRC inspector reviewed administrative procedures to

ascertain whether responsibilities have been assigned to

i appropriate personnel to ensure that plant procedures will be

reviewed, updated, and approved as required and to ensure that

the revision process includes provisions for 10 CFR 50.59

considerations.

Procedures reviewed were as follows:

o OPGP03-ZA-0002, Revision 8, " Plant Procedures"

,

l o OPGP03-ZA-0003, Revision 4, " License Compliance Review"

I .o OPGP03-ZA-0010, Revision 2, " Plant Procedure Compliance,

Implementation and Review"

o OPGP03-ZA-0033, Revision 0, "10 CFR 50.59 Safety

Evaluations"

'~

These procedures define the procedure revision process for all

plant procedures with the exception of plant organization, plant

policies, and emergency operating procedures. They define the

'

responsibilities of personnel to ensure that each procedure is

reviewed within a 24-month interval and is revised, if required,

4 and that revisions are approved by the plant manager.

NRC inspector observations / concerns are discussed below:

l

l

I

-

_ . _ _ . . _ , _ _ .

.- .

.- ,

44

'

(a) OPGP02-ZA-0010, Revision 2, " Plant Procedure Compliance,

Implementation and Review." This procedure requires that

plant procedures be reviewed within 24-month intervals.

This review of plant procedures determines whether a

'

revision needs to be generated. However, once a procedure

revision has been determined to be necessary, there are no

guidelines to ensure that the procedure will be revised in

a timely manner. These guidelines should be written to

ensure that a procedure that is determined, by the review,

to need revising is not used while it is being revised.

This is an open item (498/8708-24).

F

(b) OPGP03-ZA-0033, Revision 0, "10 CFR 50.59 Safety

Evaluations." This procedure is included in the procedure

review process to ensure that procedure reviews include

10 CFR 50.59 considerations. The inspector noted that the

technical support superintendent is responsible for the

review of 10 CFR 50.59 Safety Evaluations. However, there

is no technical support superintendent within the

operations department. Pending correction, this is an onen

item (498/8708-25).

(c) Procedures OPMP08-ZI-0065, Revision 0, " Field Testing .of

Power Supplies and Over Voltage Protectors," and

OPMP07-SP-0001, " Revision 0, "SSPS Decoder Printed Circuit

Board Test and Rework." The NRC inspector determined that

these procedures had been reviewed on July 29, 1986, but

they had not been revised at the time of the NRC inspection

8 months later, even though the applicable procedure

biennial review form, OPGP03-ZA-0012-2, stated that these

procedures required revision to correct inadequacies. This

L is contrary to Step 3.3.2.3 of Procedure OPGP03-ZA-0002,

Revision 3, " Plant Procedure Compliance, Implementation,

and Review" which states, "The cognizant DM shall ensure

that identified procedural inadequacies are corrected in

accordance with OPGP03-ZA-0002 (Plant Procedures)." This

failure will be tracked as an open item pending resolution

by the licensee (498/8708-26).

(2) Review Of Standing Order and Short Term Instruction Programs

The NRC inspector verified that administrative controls were

established for STP standing orders and short term

instructions (STIs).

The administrative controls for standing orders were defined in

PRO-1, Revision 2, " Standing Orders," which provided a mechanism

for their issue and distribution. The standing orders were

required to be reviewed and updated quarterly; however, there

was no mechanism to document the review. Pending the applicants

establishing a method to document the quarterly review of

_ _ _ . _ _ _ _ . - _ _ _ _ _ . _ _ _ _ _ _ _ _ _ _ _ _ . . _. ,__.

_ _ _ . .- __

'

, .

45

standing orders, this is an open item (498/8708-27).

,

Responsibility was assigned to the Unit 1 operations supervisor

to issue, distribute, review, and update standing orders. PRO-1

established a limitation on the type of instructions that could

be issued as a standing order.

The administrative controls for STIs were defined in PRO-25,

Revision 0, "Short Term Instructions," dated March 31, 1987.

The standing order provided a mechanism for the issue,

distribution, review, and updating of STIs. The shift

,

supervisor was assigned responsibility for control of STIs

including reviewing and maintaining them. The standing order

provided limitations on the type of activities that could be

accomplished by STIs. Issuance and cancellation of STIs may be

accomplished by signature of the shift supervisor, operations

supervisor, or the reactor operations manager. The NRC

inspector reviewed selected standing orders and STIs to verify

they met the guidance specified and did not perform activities

that should be covered by procedures. The applicant's Standing

Order PRO-1 states that standing orders shall not be used in

,

lieu of procedures. The below listed standing orders were

reviewed:

Number Revision Subject

'

PRO-1 2 Standing Orders

PRO-2 1 Required Reading Program

PRO-18 0 Event Reports

PRO-23 0 Work Control Guidelines

PRO-25 0 Short Term Instructions

From discussions with a shift supervisor and after comparison of

the guidance contained in Procedures OPGP03-ZA-0002, Revision 8,

" Plant Procedures" and OPGP03-ZA-0003, Revision 4, " License

Compliance Review," the NRC inspector determined that the shift

supervisor was knowledgeable of the steps necessary to make

temporary changes to procedures.

!

(3) Control Room Logbooks

, The NRC inspector verified that OPGP03-ZQ-0001, Revision 0,

i " Maintenance of Reactor Operations Logbooks," provided guidance

for preparation and review of logbooks. The procedure described

the usage, control, and type of logbooks maintained in the

control room. The requirements for retention in the quality

assurance vault and maintenance and storage in the control room

were specified.

NRC inspector observations made during the review of

OPGP03-ZQ-0001 are discussed below:

l

l

l

'

_ _ _ _ _

_ _ . _ . . --

._ __ _ _ _ .. _ _ _ . . _ _ _ _ __ _ _

. ._ - . - - - . .

l

.. ,

46

o There was a typographical error (typo) in Step 6.5.6 in

that the statement "only to reference the procedure" was

not needed. The step should match Step 6.2.7.

o The steps in Section 6.5 were apparently misnumbered since

Step 6.5.5 was missing.

Plant Procedure OPGP03-ZA-0063, Revision 0, " Reactor Operations

Shift Turnover," described how the shift relief and turnover was

'

to be conducted and what documentation was to be generated and

-

retained. This procedure detailed the requirement for a Shift

Relief and Turnover Log. Observation on this procedure is:

Typo in Step 4.1.3.6.3, " Shift turnover of prior to end of

shift," should not include the first "of!"

b. Operating Procedures

This area of inspection was conducted in order to confirm that plant

operating procedures are prepared and approved to control

safety-related operational activities. An index of all current

procedures dated March 10, 1987, was reviewed for plant operating

procedures identified in Regulatory Guide 1.33, Revision 2, in the

following categories:

. o Administrative Procedures

o General Plant Operating Procedures

, o Procedures for Startup, Operation, and Shutdown of

Safety-Related Systems

Also, a sample: review of plant operating procedures in the above

categories was conducted to verify that the appropriate format was

used and that each procedure was technically adequate-to accomplish

the stated purpose.

The results of the reviews in each category are documented below:

(1) Administrative Procedures

(a) The following procedures were not issued as of March'13,

1987:

o OPGP03-ZA-0064, "NPOD Preshift Briefing"

o OPGP03-ZQ-0001, " Maintenance of Reactor Operations

!

Logbooks"

o OPGP03-CN-0001, " Radio Communication"

l

!

!

l

!

. _ _ - . - . - . ,_- - , _ , .. _ ,, . _ , , _ . _ . - . _ . , _ - . _ _ _ _ , , . _ _ . . - , , ,-- _

. . _ ~

-_______________ _

. .

47

o 0PGP03-CN-0002, " Telephone Communication"

o OPGP03-CN-0003, " Plant Public Address and Alarm

System"

o OPGP03-CN-0004, " Pocket Pager System"

o OPGP03-CN-0005, " Communications Console System"

o OPGP03-CN-0006, " Communications System Test Program"

Pending issuance of the above procedures, this is an open

item (498/8708-28).

'

(b) Procedures Reviewed

Procedure No. Revision Title

OPGP03-ZA-0002 8 " Plant Procedures"

0PGP03-ZA-0010 2 " Plant Procedure Compliance.

,

Implementation and Review"

l

OPGP03-ZO-0001 3 " Equipment Clearance"

i

OPGP03-ZO-0003 3 " Temporary Modifications and

Alterations

OPGP03-ZA-0055 0 " Plant Surveillance

Scheduling"

0PGP03-ZE-0004 3 " Plant Surveillance Program"

OPGP03-Z0-0004 0 "Flant Conduct of

Operations"

0PGP03-ZA-0033 0 "10 CFR 50.59 Safety

Evaluations"

(c) NRC Inspector Observations / Concerns

1) OPGP03-ZA-0002, Revision 8, " Plant Procedures"

o There is no limit on the number of " field change

requests" (FCRs) that can be issued / approved for

a procedure before the procedure must be revised.

o There is no requirement to incorporate permanent

FCRs into procedure' revisions.

.- ,

48

o The procedure does not describe a program for

controlling the expiration dates on FCRs (i.e.,

is the FCR deleted or must it be evaluated for

procedure incorporation).

o There are no administrative controls for the use

of FCRs (i.e., mark up controlled procedure to

reference FCRs, page for page replacement, sign

off on FCR or controlled procedure, etc.).

o The approved FCRs are not listed in the master

procedure listing /index.

o There is no required time limit for FCRs to

receive final approval. The administrative limit

of 14 days (should procedure) is not being

followed as evidenced by FCN 87-21 (initial

approval 1/21/87), FCN 87-055 (initial

approval 2/13/87), and FCN 87-064 (initial

approval 2/19/87) not receiving final approval as

of March 13, 1987.

Pending resolution of the above concerns related to

the control of temporary procedure changes, this is an

open item (498/8708-29).

2) OPGP03-Z0-0003, Revision 3, " Temporary Modifications

and Alterations"

,

o The procedure makes statements in Steps 1.2 and

1.3 which appear to allow other programs to be

used for temporary modifications. This appears

to allow circumventing of the required controls

for temporary modifications.

o The procedure steps cannot be followed in

sequence as required by administrative procedure.

o There is no requirement for the shift supervisor

to acknowledge that the temporary modification

has been installed.

o The procedure allows the use of one tag on the

outside of a panel door for several temporary

jumpers or lifted leads.

l-

o The inclusion of the startup temporary alteration

! program in the plant operations program procedure

causes unnecessary complications of this

procedure. A simple reference to the startup

procedure and requirement for shift supervisor

l

!

t

< ..- , , , - - . ~ , - -

,.,-....---mm- . . , . - - - - . . - - - - - - , - . ~ . - . . , _

-

- _ _ . _. - _ - _ _ _ -_ _ _ _ _ .- _

o .

49

I

approval of temporary alterations and for all

temporary alterations to be converted to

temporary modifications would be sufficient. All

required temporary alterations should be

converted to temporary modifications prior to

operating license issuance. See

paragraph ~16.b.(2)(b)2) for further concerns

regarding modifications and alterations.

o The procedure allows the use of plastic screws

,

and washers for lifted leads with no inventory

requirements to assure that they are removed.

Pending resolution of the above concerns, this is an

open item (498/8708-30).

3) OPGP03-Z0-0004, Revision 0, " Plant Conduct of

Operations"

o Step 4.2.3 of this procedure indicated that only

4 an RO is required in the control room during

operating Modes 1 through 4 while TS

Section 6.2.2.b requires an RO in the control

room during all modes (with fuel in reactor) and

an R0 and SRO in the control room during Modes 1

through 4.

o Step 4.10.3 states that entry into limiting

conditions of operations (LCOs) as required by TS

be controlled in accordance with approved

procedures; however, there is no procedure for

tracking and controlling of LCOs by plant

operations.

'

Pending resolution of the above concerns, this is an

open item (498/8708-31).

4) A general concern identified during the review of

administrative procedures was the apparent overuse of

the word "should" which denotes a recommendation

rather than a strict requirement. The NRC inspector

is concerned that this will lead to procedure abuse

,

and a loss of control. This was discussed with

licensee management and discussed again during the NRC

exit meeting. The plant manager stated that

!

individual managers are expected to enforce the

"should" statements in procedures and that the

licensee QA organization would issue QA findings in

areas where lack of control is evidenced. The NRC

inspector cited the specific example of the final

, approval of FCNs to procedures exceeding the 14-day

, _. - _ . - - - .. - _ - _ . - . . -- .

. . .

50

i

time limit as a lack of control. Also, the following

examples of inappropriate "shoulds" in procedures were

noted by the NRC inspector:

t

o Step 4.10.3.1 of OPGP03-ZO-0004 states, "The

Shift Supervisor should be informed of TS

surveillance tests that have failed to meet their

, acceptance criteria . . . ." ,

1

o Step 4.10.1.2 states, "The operator who completed

the checklist should sign and date the checklist

and present the checklist to the supervisor who

directed the checklist be completed. For

components that are safety-related, supervisory

personnel should direct that an independent

verification be performed. When the independent

verification is completed, the operator who

performed the independent verification should

sign and date the checklist."

,

o Step 4.10.1.3 states, "The completed checklist

should be reviewed by the shift supervisor, unit

supervisor, or chemical operations foreman, as

appropriate, to verify that the directed actions

were completed and to note any exceptions or

unusual conditions. The completed checklist

should be inserted in the control room system *

4 status file or the watchstation system status

'

file, as appropriate. The superseded checklist

>

should be forwarded for record retention or

i discarded as appropriate."

i

Pending resolution of this concern related to the use

~

of "shall" and "should", this is an open item

,

(498/8708-32).

I No additional concerns or comments were identified during

the review of administrative procedures.

(2) General Plant Operating Procedures

(a) Procedures Reviewed

i

Procedure No. Revision Title

,

'

OPGP03Z0-0022 0 " Post Trip Review"

1 POP 03-ZG-0001 2 " Plant Heatup"

1 POP 03-ZG-0004 1 " Reactor Startup"

,

4

5

F

, , . , - - - - ~ - ,- - - - r--r.--w, w # w , w way -, - - - -,_-..--.mi,, - , ,

-

..---,r--.r -- - . - , . --

__ _ _ _ . . _- _ _ . - _ _ _ _ _ . - - _ _ _ _. . ._. __ ___ _

m

i

i

! . .

51

4

j IP0P03-ZG-0005 0 " Power Operations"

IP0P03-ZG-0006 0 " Plant Shutdown To

,

Hot-Standby"

l (b) NRC Inspector Observations / Concerns

1) Generally, there were several inconsistencies noted

with signoffs of steps and sections (i.e., _some action

steps not initialed, some prerequisites not signed

_

off, and the location of signoff blocks varied which

i

creates confusion as to what is being signed off).

Pending resolution, this is an open item

(498/8708-33).

2) During the review of Procedure 1 POP 02-EW-0001,

Revision 2, " Essential Cooling Water Operation," it

was noted that FC 87-092 to the procedure had been

. issued because of " leads landed on plastic during

S/U." The NRC inspector asked for the temporary

'

.

modification documentation to support these lifted

leads. Temporary Modification Nos. T1-EW-8710, -8711,

and -8712 were provided to the NRC inspector. A

review of these modifications revealed that the

j emergency load sequencing capability of the essential

cooling water system components had been disabled by

the installed modifications. The " License Compliance

Review Forms" completed for the modifications

incorrectly stated these modifications did not involve

j

'

a change to the facility as described in_the FSAR and

do not require a change to the TS when, in fact, the

installed modifications do change the facility as

! described in the FSAR and would require a change to

the TS. These installed modifications would also

require a 10 CFR 50.59 Safety Evaluation to be

performed which was not accomplished. This failure to

identify a facility modification which involved an

, unreviewed safety question was discussed with licensee

,

personnel and they stated that all temporary

i modifications existing at fuel load would have been

reevaluated per 10 CFR Part 50.59 for unreviewed

safety question determinations. This will be
evaluated by the NRC during closure of the Open

Item 498/8708-30 on conversion of temporary

,

alterations to temporary modifications. Pending the

4 licensee's response which should address the steps

i taken to assure that all previous License Compliance

j Reviews have been performed properly or that controls

are in place to assure that needed

! reevaluations / reviews are performed, this is an open

item (498/8708-34).

$-

, - . . .- .. -. - - . - _ - . _ - - . . - . _ . - - . - - _ _ - - _ .

.m

-

. ..

52

3) IPOP03-ZG-0001, Revision 2, " Plant Heatup"

The prestartup checklist does not include related

activities such as emergency shutdown system readiness

or the performance of Procedure 1 POP 02-SI-0001,

" Safety Injection Accumulators," for filling and

venting the safety injection accumulators. This is an

open item (498/8708-35).

4) IPOP03-ZG-0004, Revision 1, " Reactor Startup"

There is no requirement to verify that the neutron

count rate on the source range instruments is above a

set minimum. This is an open item (498/8708-36).

5) 1 POP 03-ZG-0008, Revision 0, " Power Operations"

The purpose and scope section is incomplete. There.is

nothing listed after . . . "following:". This is an

open item (498/8708-37).

No other concerns were identified during the review of

general plant operating procedures.

(3) Procedures For Startup, Operation, and Shutdown Of Safety-Related

Systems

(a) The following procedures were not issued as of March 13,

1987:

o IP0P02-CG-0001, " Electric Hydrogen Recombiners"

o 1 POP 02-CZ-0001, " Electric Hydrogen Recombiners"

o IPOP02-DB-0005, " Technical Support Center Diesel

Generator"

o 1 POP 02-II-0001, "Moveaule Incore Detector System

Operation"

o 1 POP 02-SB-0001, " Steam Generator Blowdown System"

Pending issuance of these procedures, this is an open item

(498/8708-38).

(b) Procedures Reviewed

Procedure No. Revision Title

1 POP 02-SI-0002 2 " Safety Injection System

Normal Lineup"

.. .. _ _ _ .- .

_ _ _ . . _ - . . _

. .

',

53

'

.1 POP 02-AF-0001 1 " Auxiliary Feedwater"

1 POP 02-CS-0001 1 " Containment Spray

Standby Line-up"

- IPOP02-CV-0001 1 " Makeup To the Reactor

Coolant System"

1 POP 02-DG-0001 1 " Emergency Diesel -

' Generator No. 11"

1 POP 02-EW-0001 2 " Essential Cooling Water

j

Operation"

i

IPOP02-RH-0001 1 " Residual Heat Removal

System Operation"

1 POP 02-SI-0001 1 " Safety Injection

Accumulators"

-

. (c) Generic NRC Inspector Observations / Concerns

l o There are no procedural instructions provided for

j filling and venting certain systems (i.e., auxiliary

, feedwater and safety injection systems). This is an

l open item (498/8708-39).

l- o There are no procedural requirements provided for

disposition of exceptions identified during system

'

lineups. There is a page for listing exceptions but

no requirement to evaluate each identified exception.

.

This is an open item (498/8708-40).

!

~

! o There were inconsistencies between the procedures

l- valve lineups for identifying that pipe caps were

l installed on vents, drains, and test connections. At

! least one procedure identified pipe caps while others

did not. This is an open item (498/8708-41).

l 0 It is recommended that operating procedures for TS 1

i

'

systems reference the applicable TS sections. It was

noted that some procedures did reference TS sections

I,

'

and others did not. This is an open item

(498/8708-42).

! o There were inconsistencies with required signoffs on

! different procedures (i.e., IPOP02-CS-0001 did not

require signoffs for control board lineups while other

procedures did). This is an open item (498/8708-43).

l

i

i

, ,

,, e. , - ~ - ---- --w . , _ . .n, ,~,,,,. - _ . - , , - . . , . . . ,,,_._y. ,m .-,,.mn -, m ,w _ ww,,. ,-,._.,,-.,..,,---,,--,n, -,-

.. -- - _ - . .- -.

j. . .-

54

,

c. Maintenance Procedures

The NRC inspectors reviewed selected applicant maintenance and

administrative procedures to verify that the procedures were in the

appropriate format, that they were technically adequate, and that

maintenance activities would be controlled in accordance with

regulatory requirements. The procedures were divided into the areas

of maintenance and measuring and test equipment (M&TE) for this

review. A number of Unit 1/ common maintenance procedures (as

indicated in the table below) had not been issued at the time of the

i NRC procedure review. Prior to licensee issuance, the NRC will

review the number and types of procedures not issued to determine if

this would impact plant operations. The numbers in the table below

were taken from a computer maintenance procedure listing dated

April 7, 1987. Pending a subsequent NRC review, this is an open

item (498/8708-44).

Total No.

Total No. of In Review Total No.

Procedure Volume Procedures Process Apprcved

"

PMP01-Maintenance Adminis-

trative Procedures 5 1 3

! PMP02-Maintenance General

Procedures 8 0 7

PMP05-Electrical Maintenance

i Procedures 438 21 384

PMP06-Metrology Lab

Calibration Procedures 321 46 236

i

PMP07-I&C Maintenance Procedures 155 1 51

PMP08-I&C Calibration Procedures 613 27 328

4

PSP 02-I&C Functional Test

Surveillance Procedures 129 17 119

PSPO4-Mechanical Surveillance

Procedures 3 1 1

'

PSP 05-I&C Calibration Surveil-

lance Procedures 160 8 142

! PSP 06-Electrical Surveillance

Procedures 22 1 20

!

PSP 13-Response Time Surveil-

lance Procedures 20 0 0

! .

!

!

.-- -, , - . - - - . - , - - , - - . . - . , , , - _ , . . . - .._ - - - . - . - . . - - , . . . - - - , - .-

. .

55

(1) Maintenance Procedures

(a) Procedures Reviewed

Procedure No. Revision . Title

OPGP03-Z0-0007 2 " Conduct of Maintenance"

OPMP01-ZA-0004 4 " Maintenance Procedures"

OPGP03-ZM-0003 7 " Maintenance Work Request

Program"

OPGP03-ZA-0010 2 " Plant Procedure Compliance,

Implementation, and Review"

1 PSP 06-DJ-0001 0 "125 Volt Class IE Battery

7-Day Surveillance Test"

l

1 PSP 06-DJ-0002 0 "125 Volt Class 1E Battery

Quarterly Surveillance-

Test"

OPGP03-ZO-0004 0 " Plant Conduct of Operations"

OPMP04-AF-0001 3 " Auxiliary Feedwater Pump

Maintenance"

OPMP04-CC-0001 3 " Component Cooling Water

Pump Maintenance"

0PMP04-DG-0004 0 " Standby Diesel Generator

Starting Air Compressor

Maintenance"

OPMP04-DG-0005 0 " Standby Diesel Generator

Maintenance"

OPMP04-FC-0001 1 " Spent Fuel Pit Cooling Pump

Maintenance"

OPMP04-FW-0003 1 "Atwood-Morrill Air Assist

20-Inch Feedwater Check

Valve Maintenance"

OPMP04-J F-0001 0 " Fuel Handling Machine

Inspection"

OPMP04-MS-0001 1 " Main Steam Safety Valve

Removal and Installation"

l

.

.. .

i

. .

56

l

OPMP04-MS-0002 2 " Main Steam Dump Valve

Actuator Maintenance"

0PMP04-MS-0003 1 " Main Steam Dump Valve

Actuator Removal and

Reinstallation"

1PMP05-DJ-006 0 " Battery Charger

Maintenance-Class 1E

125 VDC Distribution Panels"

1PMP05-VA-002 0 " Inverter /Reclifier Mainten-

ance Westinghouse 7.5 KVA"

1PMP05-PM-1101 0 "Switchgear Maintenance-

MCCEIAl"

1PMP05-PK-1014 0 "Switchgear Maintenance-

Bus E1A Cubicle 14"

1PMP05-PK-2014 0 "Switchgear Maintenance-

Bus EIB Cubicle 14"

1PMP05-PK-3014 0 "Switchgear Maintenance-

Bus E1C Cubicle 14"

OPMP04-SN-0002 1 " Hydraulic Snubber Removal

and Installation, Fluid

Addition and Sampling"

0PMP04-SN-0006 0 " Anchor Darling Model 151

Mechanical Snubber

Maintenance"

OPMP04-RC-0003 1 " Reactor Coolant Pump

Maintenance"

OPMP04-RC-0007 0 " Pressurizer Spray Valve

Maintenance"

OPMP04-RX-0001 1 " Reactor Vessel Head Removal

For Non-Rapid Refueling"

OPMP04-SI-0002 1 "High Head Safety Injection

Pump Maintenance"

OPMPO4-ZG-0006 3 "Limitorque Operator

Removal and Installation"

OPMPO4-ZG-0017 0 " Pacific Gate Valve Mainten-

ance (Bolted Bonnet)"

.

. .

57

(b) NRC Inspector Observations / Concerns

1) OPGP03-ZM-0003, Revision 7, " Maintenance Work Request

Program"

o Step 2.5 rather than stating "see addenda" could

more appropriately specify the applicable addenda

for this step.

o Step 3.1.1 is worded in such a way that a number

of people other than the shift supervisor

(control room) would have the authority to

release installed systems for maintenance. The

work start approval authority needs to be more

clearly defined so that the shift supervisor is

clearly the control point for releasing installed

components / equipment. Pending clarification of

the approval authority for release of systems

that could affect the plant, this is an open

item (498/8708-45).

o Step 4.1.7 should include words to the effect

that deletions should be lined once through,

initialed, and dated.

2) OPGP03-ZO-0004, Revision 0, " Plant Conduct of

Operations"

Step 4.10.6 states, "The shift supervisor or Chemical

Operations Foreman, as applicable shall authorize work

start approval for all maintenance, test, and other

activities that may affect the operation of the plant

or the status of plant structures, systems, and

components." The "as applicable" should be more

definitive to insure the shift supervisor controls

installed components / equipment. Pending clarification

of the "as applicable," this is an open

'

item (498/8708-46).

3) OPMP04-AF-0001, Revision 3, " Auxiliary Feedwater Pump

Maintenance"

" Documentation" section required by Addendum 3 of

Procedure OPMP01-ZA-0004 was missing.

4) OPMP04-CC-0001, Revision 3, " Component Cooling Water

Pump Maintenance"

o There was a possibility of placing wrong data on

data sheet due to dats Steps 5.12.5 and 5.12.4

being out of sequence.

. - --

. - ,

. . _ . . .. ~ _ . _ _ _ - .-. . _ _ - .. . _ ._

. .

58

'

!

,

o One fastener torque value was different from that

recommended in vendor manual. The procedure

required torquing of the motor mounting bolts to

324 ft-lbs while the vendor manual required

torquing to 70 ft-lbs.

.i Pending correction of the above items, this .is an open

item (498/8708-47).

5) OPMP04-FC-0001, Revision 1, " Spent Fuel Pit Cooling

Pump Maintenance"

o " Documentation" section required by Addendum 3 of

Procedure OPMP01-ZA-0004 was missing.

4 o Part numbers in parenthesis after the part name

'

refer to items on the figure in Addendum 1;

I however, there was no reference to the addendum

at the start of the procedure (Step 5.7).

l o Steps 5.13.24 and 5.13.26 are incorrectly

i identified as 5.13.25 and 5.13.27 on the data

,

sheet.

,

o Step 5.12.9 should note the total indicated ,

runout to be less than 0.002-inch.

! Pending resolution of the above items, this is an open  !

! item (498/8708-48).

! 6) OPMPO4-FW-0003, Revision 1, "Atwood-Morrill Air Assist

20-Inch Feedwater Check Valve Maintenance"

" Documentation" section as required by Addendum 3 of

Procedure OPMP01-ZA-0004 was missing.

7) OPMP04-JF-0001, Revision 0, " Fuel Handling Machine

Inspections"

o Items located on the data sheet did not have an

,.

asterisk and corresponding note nor any notation

'

within the main body to identify information

required to be recorded,

o Step 3.1 was apparently misnumbered, since on

the data sheet it was a chart for making not

n applicable undesired sections while in main body

of the report, it was a prerequisite for

obtaining a cleaning solvent.

.

i

w.-.m,.,----.-m--,-,%-+,.-,,.e,cy----,& --,,---.---,--------ewy -m y-----w-- , - - , -v-yy, --, , - - -r,,,,+w,-

.--n - ,, -e , - - - . tm-

,

. .

59

o Step 6.1 is not numbered on the data sheet as it

should be to be consistent with other procedures.

Pending resolution of the above items, this is an open

item (498/8708-19).

8) IPMP05-DJ-006, ~ Revision 0, " Battery Charger

Maintenance-Class IE 125 V DC Distribution Panels"

Step 4.4 should specify minimum accuracy requirements

for M&TE.

9) IPMP05-JA-0002, Revision 0, " Inverter / Rectifier

Maintenance Westinghouse 7.5 KVA"

o Data Sheet -1, Step 6.9 should read "3CB Input DC

Breaker in lieu of 3CB AC Input DC Breaker."

o Step 4.3.1 M&TE requirements should include a

second torque wrench to be used when low torque

values are required.

o Step 6.17 should include instructions to include

data sheets from referenced procedures as part of

the required documentation.

Pending resolution of the above items, this is an open

item (498/8708-50).

10) IPMP05-PM-1101, Revision 0, "Switchgear Maintenance -

MCCEIAl"

o Step 4.3.2 should specify accuracy requirements

for M&TE.

o Torque wrench should be of 15-80 foot pound range

to correspond to Addendum 1.

o Quality Control should be notified prior to

performing any torquing on bolted connections.

Pending resolution of the above items, this is an open

,

item (498/8708-51).

i 11) IPMP05-PK-2014, Revision 0, "Switchgear Maintenance -

Bus ElB Cubicle 14."

i- .

i Step 4.5.3 should include opening of breakers for

containment spray and component cooling water pumps.

i

!

i

i

- _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ ___ . _ _ _ .

a .

60

12) IPMP05-PK-3014, Revision 0, "Switchgear Maintenance -

Bus E1C Cubicle 14."

o Step 4.5.3 should place 4.16 KV Bus E1C Cubicle I

supply breaker in "Open" position and overcurrent

lockout relay in " Reset" position. Procedure

states them in reverse.

o Overcurrent lockout relay should be identified as

"86B" and not as " Breaker" under the " Comp. Name"

column in Step 4.5.3.

o "86A" relay should be identified as " Generator

Differential Lockout Relay" in Step 4.5.3. This

same comment applies to Procedures 1PMP05-PK-1014

and 2PMP05-PK-2014.

Pending resolution of the above items, this is an open

item (498/8708-52).

, 13) OPMP04-DG-0004, Revision 0, " Standby Diesel Generator

Starting Air Compressor Maintenance"

o " Documentation" section as required by Addendum 3

of Procedure OPMP01-ZA-0004 is missing.

o It was unclear as to what " GAP (New)" and

" Installed" meant in the table on the data sheet

for Steps 5.1.3.4 through 5.1.3.7 when the

procedure called for compression ring " gap" and

" location".

Pending resolution of the above items, this is an open

item (498/8708-53).

14) OPMP04-DG-0005, Revision 0, " Standby Diesel Generator

Engine Maintenance"

o " Documentation" section as required by Addendum 3

of Procedure OPMP01-ZA-0004 was missing.

o On Page 82, Step 5.7.5 currently reads 5.5.7.

o QIP designations were missing to left of QA/QC Rep

line in Steps 5.16.16.1, 5.24.12, 5.29.13,

5.34.7.1, 5.34.12, and 5.38 on data sheet.

o Step 5.16.5 (on page 26) would be clearer with

addition of "by tightening air starting valve

nut."

- - _ _ _ _ _ _ _ _ _ _ _ _ _ _

. o

61

o QIP designations were missing to left of

Step 5.33.5 in main body of procedure and on data

sheet.

o Step 5.29.8 regarding QIP should read 5.29.8 in

lieu of 5.8.29.

o Step 5.13.3 would be clarified it if referenced

figure 7.

o Section 5.16 should have QC verify cleanliness if

item would be enclosed after assembly,

o Step 5.16.5 was unclear as to the desired torque

value.

o Clarity would be increased if during reassembly

references to figures were included.

The applicant stated that this procedure was going to ,

be deleted and activities accomplished using other

procedures. Pending its deletion, this is an open

item (498/8708-54).

15) OPMP04-ZG-0017, Revision 0, " Pacific Gate Valve

Maintenance (Bolted Bonnet)"

o " Documentation" section as required by Addendum 3

of OPMP01-ZA-0004 was missing.

o It was unclear regarding which column was to be

used on the torque chart in Addendum 6.

Pending correction of the above items, this is an open

item (498/8708-55).

16) OPMP04-SN-0002, Revision 1, " Hydraulic Snubber Removal

and Installation, Fluid Addition and Sampling"

o Step 5.1.18 in the main body appeared as

Step 5.1.17 on the data sheet.

o " Documentation" section as required by Addendum 3

of OPMP01-ZA-0004 was missing.

17) OPMP04-SN-0006, Revision 0, " Anchor Darling Model 151

Mechanical Snubber Maintenance"

The note and corresponding asterisks to the left of

steps with data sheet entries was not used for all

but one other of the procedures in the OPMP04 group.

.

_

. .

62

Pending correction of the above item, this is an open

item (498/8708-56).

18) OPMP04-SI-0002, Revision 1, "High Head Safety

Injection Pump Maintenance"

o After reviewing the corresponding vendor manual,

there appeared to be a discrepancy in the

acceptance criteria for Step 5.12.3.50. The

criteria given was .008 to .012 inches and that

stated in the vendor manual for the " Head and

bowl bearing running clearance" was .013 to

.020 inches.

o Step 5.13.6 in the procedure should be asterisked

and the data sheet should contain entries

pertaining to torquing of the fourth stage

through seventeenth stage bowl fasteners.

o After comparing the vendor manual torque chart

to the procedure required torque values, the

inspector identified discrepancies in the

following steps:

-

5.13.5.7 and 5.13.6

-

5.13.8.2

-

5.13.9.2

-

5.13.10.10

o For the smaller torquing values called for in the

procedure there was not a prerequisite for a

torque wrench that has that value fall into the

upper half of the scale.

Pending resolution of the above items, this is an open

item (498/8707-57).

19) OPMP04-ZG-0006, Revision 3, "Limitorque Operator

Removal and Installation"

" Documentation" section required by 0PMP01-ZA-0004

was missing.

20) OPMP04-RC-0007, Revision 0, " Pressurizer Spray l

Valve Maintenance" l

" Documentation" section required by

OPMP01-ZA-0004 was missing.

_

. . . _ _ _ _ . _ _ - .__ _ - ___ _ _. _ . _ _ _. _ ____ _ __

i .- .

. 63

.

21) Generic Comments

i o Some of the procedures appeared to have too

many references. Elimination of references

that are not necessary for the performance

of the procedure would simplify the '

procedure and make it more_ user oriented.

'

Examples of this were Procedure OPMP03-ZO-0004,

i' Revision 0 (40 references), .

Procedure OPGP03-ZM-0003, Revision 7 (40

, references), and Procedure OPMP01-ZA-0004,

{ Revision 4 (11 references).

I

o The NRC inspector investigated the

j licensee's controls over torquing of

l- safety-related fasteners. Torquing of

4

fasteners at STP followed the information

,

located in each component's respective

! vendor manual. If there was no information

I given, but the determination that torquing

of fasteners would be required, then Plant

Procedure OPMP02-ZG-0004, " Fastener Torquing-

l and Detensioning," was required to be

utilized.

I

l The NRC inspector compared 10 vendor manuals

to their respective procedures out of a

l sample of 18 procedures. It was determined

I that the corrective maintenance procedures

I satisfactorily reflected the information

contained in the manuals.

o The NRC inspector reviewed the licensee's

l

process for adding quality control hold

points to corrective maintenance procedures.
In the procedures reviewed, the licensee had

"

hold points to verify cleanliness of the

component and parts before enclosing the part

and/or system. QC was in the review cycle,

and had the option during maintenance work

i request review to add additional hold points

! as required.

5 o Referencing other procedures and documents

. by revision number could be confusing,

t Administrative controls could be used to

I require use of the latest revision, except

'

in the cases where a specific revision to a

document is applicable (i.e., a commitment).

i

l

.

,

'.----... *

_ - - _ _ . . . _ _ _.

.,.

i

i

. s.

,

&

64

(2) Procedures For Control of M&TE

The NRC' inspector reviewed plant maintenance procedures to

ascertain whether-the licensee's measuring and test control

program adequately provides. controls for the calibration,

testing, and checking of instrumentation and equipment.

Calibrating and testing procedures were reviewed to verify that

each was in the appropriate format as defined in administrative

control procedures and was technically adequate to accomplish the

stated purpose.

The NRC inspector reviewed Procedure OPGP03-ZM-0001, Revision 9,

a " Measuring and Test Equipment Control Program," which provides

, program guidelines for the control of M&TE. For the purposes of

' J' this procedure, M&TE does not include permanently installed

<

4

plant instrumentation. Calibration and testing of plant

r instruments is addressed by " Plant Instrumentation Sealing

Program," Revision 2. This procedure is applicable to devices

which require calibration or testing by the instrumentation and

i controls section of the maintenance division. This procedure

delineates controls for calibration and-status

verification / notification of installed permanent plant

instruments. Thirteen calibration and testing procedures were

i reviewed to verify conformance to administrative guidelines and

<

technical adequacy. The procedures reviewed were found to be

'

technically adequate. They defined step-by-step instructions to

accomplish their stated purpose. The NRC inspector did note

some procedures needed to be reviewed and revised to conform to

administrative guidelines. The NRC inspector held discussions

with various personnel during the review of the procedures.

4c These discussions indicated that they were familiar with program

guidelines and requirements. NRC inspector observations were

discussed with appropriate licensee personnel.

(a) Procedures Reviewed

,

Procedure No. Revision Title

IPMP05-YA-0001 1 " Vital Distribution Panel

Tests"

i

OPMP05-ZE-0104 0 " Frequency Transducer

Calibration"

OPMP05-ZE-0034 1 " Calibration of ITE-27

Relays"

{-

" Insulation Resistance

'

OPMP05-ZE-0203 2

!

Testing-4.16K and 13.8K

'

Volt Motors"

. ._ - - .._-_ ___ .. - _ _ . _ ~ _ - - - - _ _ _ _ _ - _ . - . . . - - ~-- _ _ . . _ -

_ _ _ _ - _ _ _ __-___-____ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ -

9

.. .

65

OPMP05-ZE-0206 0 " Potential Transformer Tests"

OPMP06-ZT-0186' 2 " Calibration of the

Westinghouse Relay Test Set"

0PMP06-ZT-0279 0 " Calibration of General

Resistance RTD-100 RTD

Simulator"

.0PMP06-ZT-0293 0 " Calibration of Fluke

80I-600 Clamp-On Current

Transformer"

'

OPMP07-SP-0001 0 "SSPS Decoder Printed Circuit

Board Test and Rework"

OPMP08-ZI-0011 2 " Generic Temperature Switch

l Calibration (Filled

-

Element)"

OPMP08-ZI-0065 0 " Field Testing Of Power

Supplies and Over Voltage

Protectors"

0PMP08ZI-0203' 2 " Pressure or Differential

Pressure Indicator

'

Calibration"

, s -n IPMP08-SI-0861 0 "RHR/LHSI Pump.1.A Discharge

,

c, -

Pressure Calibration

lo.lJ-

'

A?

(P-0861)"

', N f;

OPGP03-ZM-0011 2 " Plant Instrumentation

Scaling"

0PGP03-ZM-0016 0 " Installed Plant

Instrumentation Calibration

'

L

g. ]gf '

Verification Program"

l ,

(b) NRC Inspector Observations / Concern _s

"

1) OPMP05-ZE-0104, Revisfeb u, " Frequency Transducer

Calibration"

o Step 6.6.5 data sheet should read " Transducer

removed from service."

o Precautions should include instructions to verify

equipment clearance, if applicable.

.

_

. .

66

2) OPMP05-ZE-0034, Revision 1, " Calibration of ITE-27

Relays"

Precautions should include instructions to verify

equipment clearance,'if applicable.

3) OPMP05-ZE-0203, Revision 2, " Insulation Resistance

Testing-4.16 K and 13.8 K Volt Motors"

o Steps 6.12 through 6.15 should be incorporated

into Restoration / Documentation sections.

o Procedure should specify actions to take if

acceptance criteria is not met.

4) OPMP07-SP-0001, Revision 0, "SSPS Decoder Printed

Circuit Board Test and Rework"

o Procedure should include instructions on how to

complete and process test documentation.

o Precautions should include instructions to verify

equipment clearance, if applicable,

o Though this procedure is technically adequate to

accomplish its stated purpose, it should not be

used until it is revised due to inadequate

procedure guidelines and instructions. Procedure

was in the review and revision process at.the

time of the NRC inspection.

Pending completion of this procedure revision, this is

an open item (498/8708-58).

5) OPMP08-ZI-0011, Revision 2, " Generic Temperature

Switch Calibration (Filled Element)"

o Precautions should include instructions to verify

equipment clearance, if applicable,

o Step 7.4.3 states " proceed to Step 7.3," which is

incorrect.

6) IPMP08-SI-0861, Revision 0, "RHR/LHSI Pump 1A

Discharge Pressure Calibration (P-0861)."

Addendum 1 does not identify V2 per Step 7.3.1.2.

7) OPMP08-ZI-0065, Revision 0, " Field Testing of Power

Supplies and,0vervoltage Protectors"

_ - . . ._ _

'

. .

4~

67- l

1

l

This procedure should be clarified in the following

-areas:

o Procedure should define responsibilities of

personnel.

o Procedure should define actions to be taken if

-acceptance criteria is not met.

o Precautions should include

restoration / documentation instructions.

o Procedure should specify M&TE accuracy

requirements.

'

o Procedure should identify references where

acceptance criteria can-be found.

'

.'

o Procedure should not be used until a revision is

issued do to inadequate procedure guidelines and

instructions. Revision 0 is in the review and

revision process.

Pending resolution of the above items, this is an open

item (498/8708-59).

d. Emergency Operating Procedures

(1)' Purpose

! The purpose of this inspection was to determine whether E0Ps had

been prepared in accordance with the PGP and whether they were

technically adequate to control safety-related functions in the

event of system or component malfunction. At the time of this

inspection, the PGP had been submitted to the NRC Office of NRR,

but the NRC staff review of PGP was not yet complete.

i

(2) Procedures Reviewed

i The following procedures were reviewed during this inspection:

o OPGP03-ZA-0027, Revision 1, " Emergency Operating Procedures

Preparation, Approval, and Implementation"

o OPOP01-ZA-0006, Revision 2, " Emergency Procedures Writers

, Guide and Verification"

i

o 1 POP 05-E0-E000, Revision 1, " Reactor Trip or Safety

Injection"

,

'.

!

, - , . . - , . . . _ . . . . _, , _ . _ _ ~ _ - . _ , - . . - - _ _ . _ . . _ _ - - . . . . - . _ , . , _ . - . . . .

. _

._- _ . . . _

,

c.^ ,

-

S 68

s

o IPOP05-E0-E010, Revision 1, " Loss of Reactor or Secondary

Coolant"

o 1 POP 05-E0-EC00, Revision 1, " Loss of All AC Power"

o IPOP05-E0-FRH1, Revision 1, " Response to Loss of Secondary

Heat Sink"

(3) Status Of Completi2n

The NRC inspector compared the index of the applicant's E0Ps to

the index of the 40G ERGS. This index indicated that E0Ps had

been prepared ano approved for all WOG ERGS. One additional E0P

was in preparati>n in response to the fire hazards analysis.

This E0P was scheduled to be approved prior to loading fuel.

i ,

(4) Technical Adequicy

The NRC inspector assessed E0P technical adequacy by comparing

the E0Ps to the WOG ERGS and plant piping and instrumentation

drawings. While'no major technical inadequacies were

<

identified, several errors and discrepancies indicating the ,

-applicant's failure to develop E0Ps appropriate to the

. circumstances as required by 10 CFR 50 Appendix B, Criterion V,

I were identified. These are listed below:

(a) Statior, Procedure 1 POP 05-E0-E000, " Reactor Trip or Safety

Injection"

o Step 10 did not state how many essential cooling water

pumps should be running.

o Step 11.1 required ' transfer' of reactor containment

fan cooling to component cooling water. This step

should have verified that automatic transfer had

,

occurred.

l

j o Step 22.2 listed incorrect equipment designations for

the pressurizer spray valves,

o Step 31.2 incorrectly directed the secondary operator

to sample the steam generators. This function should

be performed by plant chemists, as directed by the

Unit Supervisor.

(b) Station Procedure IPOP05-E0-E010, " Loss of Reactor or

.

Secondary Coolant," had an incorrect reactor coolant system

pressure referenced in Entry Condition 3.

.

e e v -1* y,.-.~.-, - - .--- ,. .-,-y ,~. _.. - .,____, e--,-,..,,,,m. ,-,..r,,,,_,2 . - _ . _ _.---._,.-,.r._..-2.-_,,, c.,.v. - - r m.m.-e_.2

p

r

- .

69

(c) Station Procedure IPOP05-E0-EC00, " Loss of All AC Power,"

failed to include the desired entry step of the referenced

procedure in the contingency action statement of Step 27.1.

(d) Station Procedure IP0F05-E0-FRH1, "Resperse to Loss of

Secondary Heat Sink."

o The step 9 caution statement stated, ". . . establish

RCS heat by RCS bleed and feed." The word ' Removal'

should be inserted after ' heat'.

o The Step 19 caution statement contained an incorrect

procedure number reference.

o The note before Step 22 was repeated before Step 23,

deleting the proper note which should have been placed

before Step 23, "After closing a PORV, it may be

.necessary to wait for RCS pressure to increase to

permit stopping high-head SI pumps in Step 22."

Pending licensee response, the above deficiencies will be

tracked as an open item (498/8708-60).

(5) Deviations from WOG ERGS

Section II of the STP PGP dated May 16, 1985, stated, "As the

procedure writer prepared the E0P, deviation between the WOG

ERGS and the plant specific procedure caused by plant design or

preferred due to control board layout were documented on form

! (4) of the writer's guide. Reasons for deviations were also

documented on the same form." Section 2.3.1 of Station

Procedure OPOP01-ZA-0006, " Emergency Procedure Writers Guide and

Verification," states, "When preparing the E0Ps, situations may

arise where the intent specified by the guidelines may have to

be altered . . . due to the STP design. When this happens, the

, writer shall complete the documentation for changes to the WOG

'

Guidelines or 'EOP Step Justification / Verification Form' (-4)."

The NRC inspector reviewed the E0P verification packages for

Revisions 0 and 1 of the E0Ps listed above. The Step

l'

Justification / Verification (SJ/V) forms completed during

procedure preparation and revision were included in these

packages. For a small number of deviations from the WOG ERGS,

the NRC inspector found that the SJ/V forms provided a very good

. justification for the deviation. However, many deviations from

! the WOG ERGS were not documented and justified on SJ/V forms and

'

there were inadequate basis or justification for scme of the

deviations which were documented on SJ/V forms. Pending

licensee resolution, the lack of documentation o' deviations

from the WOG ERGS will be tracked as an open item (498/8708-61).

.

a

. ..

70

The NRC inspector found that SJ/V forms were generally not used

to document and provide a basis for plant specific information

~

inserted into the E0Ps where the WOG ERGS used a notation such

as, " Establish main feedwater flow [-Enter plant specific

means]."

It should be noted that the lack of SJ/V forms was frequently

, documented by. reviewers in the procedure verification process

using E0P Discrepancy / Comment forms from Station

Procedure OPOP01-ZA-0006. In these cases the resolution of the

comment provided some justification of the deviation from the

WOG ERGS.

(6)' Plant Specific Values

One plant specific value from each of the four E0Ps was selected

for verification. The reference for plant specific values.was

the HL&P Emergency Operation Procedure Setpoint Document,

Revision 1, dated November 10, 1986. No problems were

identified in this verification. Applicant representatives

informed the NRC inspector that Revision 2 of the Setpoint

Document has been issued but not yet incorporated into the E0Ps.

They plan to incorporate the latest setpoints into-the E0Ps

prior to loading fuel.

(7) Compliance With Writers Guide

The NRC inspector reviewed the four E0Ps listed above to

determine whether they had been written in accordance with the

guidance provided in Station Procedure OPOP01-ZA-0006,

" Emergency Procedure Writers Guide and Verification." General

conformance was noted with the exceptions listed below:

(a) Section 3.1.2.1 of the writers guide required that each

operator copy of an E0P present the user information and

steps on the left page and the non-user information on the

right page when opened. The NRC inspector noted that

action steps identified as being performed by the Unit

Supervisor were not included with the non-user information

on the right page of the operator's copies of the EOPs.

(b) Section 5.4 of the writers guide required maintenance of a

direct horizontal relationship between the related action

steps in the left column and the contingency action steps

in the right column. The NRC inspector found that the

contingency action step associated with action Step 5.3 of

Station Procedure IPOP05-EO-E010 was aligned horizontally

with action Step 5.2.

-(c) Section 17.4 of the writers guide required that missing

information shall be listed on a separate punchlist at the

. ,

71

end of the written procedure body. The NRC inspector found

that no punchlist was attached to Station

Procedure 1 POP 05-E0-EC00 although Steps 15 and 16 of this

procedure were missing information which should have been

identified on a punchlist. The missing information related

to contingency actions for filling the auxiliary feedwater

storage tank using the fire water system and local

operation of steam dump valves.

(d) Section 18.2 of the writers guide required that the

appropriate emergency action level be entered into the E0P

at the earliest possible point. The NRC inspector found

that Station Procedure IPOP05-EC-FHR1 contained no

reference to emergency action levels which had been

reached. Station Procedure OEPP01-ZA-0001, " Emergency

Classification," Addendum 3, indicated that reaching

Step 9.0 of 1 POP 05-E0-FRH1 was the emergency action level

for declaration of a General Emergency.

Pending licensee response, the above exceptions to the writers

guide will be tracked as an open item (498/8708-62).

(8) Verification and Validation

The NRC inspector reviewed the verification packages for

Revisions 0 and 1 of the E0Ps listed above, the Emergency

Operating Procedure Validation Report dated December 22, 1986,

and the checklists and deficiency sheets associated with the

validation program. An applicant representative stated that

the final validation report was in preparation at the time of

this inspection. It appeared that the verification and

validation program was conducted in accordance with the PGP and

associated plant procedures. However, some weakness in this

program was indicated by the dis ~crepancies discussed above. .

(9) Other Comments

(a) During the review of E0P verification packages, the NRC

inspector noted that one individual signed a License

Compliance Review Form (OPGP03-ZA-0003-1) as both preparer

and reviewer. While this action was not prohibited by

Plant Procedure OPGP03-ZA-0003, the NRC inspector stated

that this was not a generally accepted practice. Applicant

representatives stated that they had recognized this as a

problem and that corrective action was underway.

(b) Step 6.3.1.6 of Station Procedure OPGP03-ZA-0027 appeared

to be incomplete.

(c) The E0Ps included no statement of purpose or scope.

( NUREG-0899, Section 5.4.3 states, "Each E0P should contain

l

l

. .. , _

_ _ _ --

. . . - . . -- - . ~ . . .- ~ . -

l'

. .

72

.

a brief statement that describes what it is intended to

accomplish. In many cases it may be possible to include

the scope in the title of the E0P without making the title

too long." While the PGP indicated that the writers guide

was based on NUREG-0899 (and other references), the writers

guide did not require E0Ps to have a statement of purpose

or scope. The NRC inspector noted that the WOG ERGS each

i begin with a statement of purpose, some of which provide

considerably more information about the purpose of the.

procedure than does the procedure title. This comment is

,

expected to be resolved during the process of NRC review

and approval of the PGP.

i e. Off-Normal Operating and Alarm Response' Procedures

The NRC inspector reviewed selected applicant off-normal. operating

j- procedures and annunciator response procedures to verify they were in

'

the required format and that they were technically adequate to

perform the designated function. The NRC inspector walked down

selected procedures to verify that the 'as-built' conditions were

compatible with the plant procedures.

.

(1) Procedures Reviewed

(a) Off-Normal Procedures

,

t ~

Procedure No. Revision Title

1 POP 04-RC-0001 2 "High Reactor Coolant

,

System Activity"

i

1 POP 04-FW-0001 1 " Loss of Feedwater Flow

or Control"

1 POP 04-CR-0001 1 " Main Condenser-Loss of

Vacuum Off-Normal'

Procedures"

I IPOP04-RC-0002 1 " Loss of Reactor Coolant

Pump"

!

(b) Operating Procedures

a

4

Procedure No. Revision Title

4 1 POP 02-CV-0004 1 " Chemical & Volume

i Control System"

1

\

f

4

y -w r-'vm,w.--.",. ,,,-.,,,,---r-v -,,, -----,~-r,,,

- , rm, y--.,y--r--,,,---,,,.w,,,,,-e-v- r=w e ,- ,, m mw e me e w- ----m , sr e w -- --v- . ~w- m

_ _ _

. ~ _ - - . . . . . . . . - . --. .-- -. .- . .- -.

1

. .

73

- (c) Annunciator Response Instructions

IPOP09-AN-04M8-D-4 0 "LETDN HX OUTLET FLOW

HI/LO"

1 POP 09-AN-04M8-D-3 0 "LETDN HX TEMP HI DEMIN

DVRT"

1 POP 09-AN-04M8-D-1 0 " SEAL WTR INJ FILTER

DR HI"

1 POP 09-AN-04M8-C-4 0 "LETDN HX OUTLET PRESS

HI"

1 POP 09-AN-04M8-C-3 0 "LETDN HX OUTLET TEMP ,

HI"

1

1 POP 09-AN-04M8-C-2 0 "BTS DEMIN DP HI"

1 POP 09-AN-05M2-E-1 0 "RCP CCW FLOW LO"

1 POP 09-AN-05M2-E-2 0 "RCP TRIP"

1 POP 09-AN-05M2-E-3 0 "Rx VSL FLNGE LEAK TEMP

HI"

1 POP 09-AN-05M2-C-1 thru 0 "RCP UPPR OIL RSVR LVL

IPOP09-AN-05M2-C-4 HI/LO"

1 POP 09-AN-05M2-D-1 thru 0 "RCP LOWR OIL RSVR LVL-

1P0P09-AN-05M2-D-4 HI/LO"

1P0P09-AN-07M3-E-7 0 " MAIN COND VACUUM LO"

1 POP 09-AN-07M3-F-6 0 "F.W. S/V PMP L. O. AUX

PMP TRBL"

,

IPOP09-AM-07M3-F-8 0 " SEAL LEAK OFF TNK LVL

l HI"

l

l

These annunciator response instructions were walked down in

j- the plant.

' (2) NRC Inspector Observations / Concerns

i

. (a) IPOP02-CV-0004, Revision 1, " Chemical and Volume Control l

System"

!

i

!

!

i

..,,,--,,-,1--- . , _ , , , , . . _., .,_.m --- ,,,.---- - ... ,_-_--,_.-_-....----m-_.,-..,,_,,,_-,.., , , , . . . , - . . _ _ , . , , . . , - _ , , ~ , - - . . . , , - -

-. ..

74

o In Step 11.3 there is an incorrect valve designation

in the valve lineup in that in Cation Bed Demin IA

valve line up should read "1*CV-129A" in lieu of

"1*CV-129B".

o In Step 11.5 'MAB' should be 'MEAB'.

(b) IPOP04-FW-0001, Revision 1, " Loss of Feedwater Flow or

Control"

According to the instructions in Steps 4.3 and 4.4 of

' Procedure OPOP01-ZA-0007, Revision 1, "Off-Normal

Procedures Writer's Guide," there is a conflicting use of

" Note" versus " Caution" statements. An example of this is

the following " Note" located after Step 4.3 which should be

a " Caution" statement:

" Reducing turbine load too rapidly may cause an unnecessary

reactor trip due to the effects of SG shrink."

Pending resolution, this is an open item (498/8708-63).

(c) IPOP04-RC-0002, Revision 1, " Loss of Reactor Coolant Pump"

The following " Note" which occurs at Step 4.0 in the

procedures is an instruction statement (i.e., action step).

This is contrary to the instructions in Step 4.4 of

OPOP01-ZA-0007, Revision 1, "Off-Normal Procedures Writer's

Guide," which states that notes should not be used as

instruction statements.

" Note: If Rx pwr is above P-8 and conditions exist calling

for an immediate RCP trip then trip the reactor first then

the RCP to ensure heat removal. I_f Rx power is less than

P-8, trip the RCP only."

Pending resolution, this is an open item (498/8708-64).

(d) OPOP09-AN-05M2-E-1, Revision 0, "RCP CCW Flow LO"

The immediate actions section (below) of the procedure

should also verify the remainder of the CCW system is in

service (i.e., per a POP or by looking at a control panel).

" Verify 1*CC-MOV-318, 1*CC-MOV-029, inlet isol. are open

and 1*CC-MOV-403, 1*CC-FV-4493, 1*CC-MOV-404, 1*CC-MOV-542,

outlet isolation valves are open."

(e) 1 POP 39-AN-05M2-E-3, Revision 0, "Rx VSL FLNGE LEAK TEMP HI"

_ - ____ - _ _____ -_____________-___ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _

o o

75

3rocedure states " Place HS-3400 to 'Close' position as

firected by Unit Supervisor," however, the switch is not

libeled as HS-3400 on the control board. Applicant has

aided this item to the labels correction log.

(f) IPOP09-AM-07M3-F-8, Revision 0, " SEAL LEAKOFF TANK LVL HI"

Supplementary actions states to " Manually control level

using Bypass Valve 1-FW-0483;" however, Valve 1-FW-0483 is

installed under floor grating that makes it not readily

accessible.

Pending resolution, this is an open item (498/8708-65).

(g) In general, action statements are inconsistent in the

amount of detail provided for performing the action. Some

of the action statements only give general guidance as in

Step 5.1 of IPOPO4-FW-0001, Revision 1, " Loss of Feedwater

Flow or Control" which states:

" Ensure steam dumps are operating properly and verify that

T

AVG

is being matched with T Ref' "

This action statement should be more specific by

referencing instruments to be monitored. Examples of

action statements which provide specific instructions are

Steps 4.1 and 5.1 of Procedure IPOP04-CR-0001, Revision 1,

" Main Condenser-Loss of Vacuum Off-Normal Procedures,"

which state respectively:

o "4.1, Verify all vacuum pumps operating (hogging)

(CD-009)."

o "5.1, Verify steam supply to turbine seals (CP-008)."

Pending resolution, this is an open item (498/8708-66).

f. Surveillance Procedures

The NRC inspectors performed the following activities to verify that

the applicant had established adequate procedures to perform required

TS surveillances:

o Compared the proof-and-review version of STP Unit 1 TSs to the

STP index of surveillance procedures to verify that the

applicant had established or was establishing a procedure to

accomplish each surveillance required by the TSs.

o Performed in-depth review of selected effective / approved

surveillance procedures to verify that TS surveillance

requirements were satisfied.

- _ - _ _ _ _ _ _

r

a .

76

o Performed in plant walkdowns of selected surveillance procedures

to verify that as-built equipment and indicators reflected the

TS requirements.

(1) Procedures Reviewed

(a) Administrative

Procedure No. Revision Title

OPGP03-ZE-0005 3 " Plant Surveillance Procedure

Preparation"

(b) Instrumentation and Control (I&C) Functional

Procedure No. Revision Title

  • 1 PSP 02-EH-6328, 0 " Turbine Thrott!e Valve

TA00T"

1 PSP 02-FW-0574 0 "SG-ID Narrow Range Level

Set 1 ACOT"

1 PSP 02-HC-0935 0 " Containment Pressure Set 3

ACOT"

1 PSP 02-MS-0506 1 " Turbine Impulse Chamber

Pressure Set 2 ACOT"

  • 1 PSP 02-NI-0042 0 " Power Range Neutron Flux

Channel II ACOT"

1 PSP 02-RC-0427 0 "RCS Flow Loop 2 Set 1 ACOT"

1 PSP 02-SI-0952 0 " Accumulator 18 Level

Group IV ACOT"

1 PSP 02-SP-0001R 0 "SSPS Logic Train R

Functional Test"

1 PSP 02-RC-0452 0 "RCS Temperature Loop II

Set 1 ACOT"

1 PSP 02-RC-0466 0 " Pressurizer Level Set II

ACOT"

(c) System and Component

IPSP03-AF-0004 1 "AFW Pump II Reference Value

Measure"

r

a o-

77

1 PSP 03-SI-0017 0 " Containment Spray Valve

Checklist"

1 PSP 03-CV-0007 0 " Boric Acid Transfer Pump 1A

Reference Valves Measures"

1 PSP 03-CV-0010 0 "Boration Flow Verification"

1 PSP 03-0G-0011 1 " Standby Diesel IZ Auto Start

on ESF Actuation Test

Signal"

1 PSP 03-EA-0002 0 "ESF Power Availability"

1 PSP 03-FP-0001 0 " Fire Protection System Valve

Operability Test"

1 PSP 03-RC-0006 0 " Reactor Coolant Inventory"

Pump 1B Reference Valve I

Measurement"

1 PSP 03-SI-0013 0 " Accumulator Isolation Valve

Verification"

Instrumentation Channel

Check"

1 PSP 03-0G-0003 1 " Standby Diesel B Operability

Test"

1 PSP 03-RM-0001 1 "Raactor Makeup Water System

Valve Operability Test"

(d) I&C Calibration

  • 1 PSP 05-AF-7524 0 "AFW Flow Loop II Channel B

Calibration"

1 PSP 05-FW-0503 0 "SG-IC Wide Range Level

Channel B Calibration"

1 PSP 05-AC-0936 0 " Feed Flow Loop I Set 3

Calibration"

1 PSP 05-NI-0031 0 " Source Range Channel I

Calibration"

. _ _ _ _ - - __

.- . - . _

o .

78

1 PSP 05-NI-0044 0 " Power Range Channel IV

Calibration"

1 PSP 05-RC-0417 0 "RCS Flow Loop I Set I

Calibration"

1 PSP 05-RC-0451 0 "RCS Temperature Loop I Set I

Calibration"

1 PSP 05-RC-0458 0 " Pressurizer Pressure Set IV

Calibration"

1 PSP 05-RC-0466 0 " Pressurizer Level Set II

Calibration"

1 PSP 05-SI-0954 1 " Accumulator 1C Level

Group III Calibration"

1 PSP 05-WL-0478 0 " Plant Liquid Waste Discharge

Flow Calibration"

1 PSP 05-CC-4503 b 0 "CCS Surge Tank Compartment A

Level Switch Calibration"

(e) Electrical

IPSP06-DG-0001 0 "Undervoltage Loss of Relay

Voltage Channel Calibration"

1 PSP 06-DJ-0004 0 "125 V Class 1E Battery

Service Surveillance Test"

  • Procedures selected for in plant walkdown.

(2) NRC Inspector Observations / Concerns

(a) 1 PSP 03-SP-0001, Revision 1, " Remote Shutdown Monitoring

Instrumentation Channel Check"

The acceptance criteria in Step 7-1 on channel checks needs

to be more specific. Tolerances should be included so the

test parformer knows when an indicator is not functioning

properly. Presently the only criteria is that an

indication exists. The NRC inspector determined from

discussions with applicant personnel that the applicant

feels that since a quantitative assessment of the channel

behavior is not required by the TS that a tolerance is not

desired. The procedure does include a step that states

that if in the operators judgement the indications are in

error he is to report that information to the shift

supervisor.

_ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ - _ - _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

r

e. m

79

(b) IPSP03-RH-0005, Revision 0, " Residual Heat Removal Pump 18

Reference Values Measurement"

This procedure lines up the system to run the RHR pump with

the suction valve closed. This did not appear to be a good

practice since the small volume of water within that closed

system could heat up rapidly and could cause cavitation and

possible water hammer problems. The NRC inspector

determined from discussion with applicant personnel that

the system design allows for cooling by the CCW system of

the water being pumped. The utility feels that this will

be sufficient to prevent cavitation problems due to heatup.

(c) OPGP03-ZE-0005, Revision 3, " Plant Surveillance Procedure

Preparation"

Step 3.2.4.b specifies that any LC0 which may be entered

during the performance of a surveillance test be inserted

in the pretest verification section of the procedure. This

was omitted from many of the procedures that were reviewed.

Applicant personnel stated that during the next revision to

PGP03-ZE-0005, " Plant Surveillance Procedure Preparation,"

the instructions for the contents of the pre-test

verification section will be modified.

Pending this revision, this is an open item (498/8708-67).

(d) 1 PSP 03-RC-0006, Revision 0, " Reactor Coolant Inventory,"

Procedure does not specifically address " leakage to RCP

seals." This leakage to the seals is stated in TS

Surveillance 4.4.6.2.1.c. Applicant states that TS

Surveillance 4.4.6.2.1.c is being deleted.

Pending this deletion and correcting the procedure, if

required, this is an open item (498/8708-68).

(e) IPSP03-SI-0013, Revision 0, " Accumulation Isolation Valve

Verification"

Step 5.3 states that an indicating light on the main

control board is used to verify power removed to the valve

operator. This verification should be done by breaker

position. The NRC inspector determined from discussion

with applicant personnel that the design of the controls on

the main control board provides for removal of control

power to the isolation valve and indication of such removal

and valve position. This is sufficient to ensure that

power has been removed to the isolation valve.

(f) IPSP03-SP-0001, Revision 0, " Remote Shutdown Monitoring

Instrumentation Channel Check"

_ _ - _ _ _ _ _ _ _ _ - _ _ _ - _ - _ _ _ _ _

r-

w .

80

Performance frequency for this procedure was listed as

quarterly in the surveillance procedure index computer

printout; however, TS 4.3.3.5, Table 4.3-6, requires the

surveillance to be performed monthly. Applicant revised

the surveillance testing master index so that the frequency

for this procedure was changed to monthly to comply with TS

requirements.

(g) The NRC inspector observed that QC should be involved in

performance of surveillance procedures. It was noted that

some procedures have QC involvement but most do not. The

NRC inspector determined from discussions with applicant

personnel that it is the applicants philosophy to have QC

be on the worker level. The applicant feels that the

training given the worker is sufficient to ensure quality

control and it is not necessary to include QC on all

procedures. The quality assurance department spot checks

the performance of procedures.

No violations or deviations were identified.

17. Exit Interview

The NRC resident inspectors met with -licensee representatives (denoted in

paragraph 1) on April 10, 1987, and summarized the scope and findings of

the inspection. Other meetings between NRC inspectors and licensee

management were held periodically during the inspection to discuss

identified concerns.

.. .. .