MONTHYEARML24018A0112024-01-18018 January 2024 CFR 21 Report Emergency Diesel Generator Fuel Oil Piping ML23087A1292023-03-23023 March 2023 Trillium Valves USA - Part 21 Written Notification - Event Number: 56420 ML23082A1122023-03-17017 March 2023 10 CFR Part 21 Report – Inconsistent Crimping of Motor Leads to Ring Terminal Connectors and Failure to Comply. Trillium Valves USA Part 21 Evaluation I211003 ML22089A2442022-03-30030 March 2022 10 CFR 21 Report- Feedwater Isolation Valve Poppet Seal Failure ML21187A1242021-06-28028 June 2021 10CFR Part 21 Update - Deviation Identified in the Bolting Utilized to Maintain Seismic Qualification ML20366A0482020-12-0707 December 2020 10CFR21 Reporting of Defects and Non-Compliance - Engine Systems, Inc. Report No. 10 CFR21-0114, Rev. 1 NL-20-0764, Initial 10 CFR 21 Notification - Continuously Energized Eaton D26 Relays Could Fail to Deenergize Because of an Organic C3 Insulating Material2020-06-24024 June 2020 Initial 10 CFR 21 Notification - Continuously Energized Eaton D26 Relays Could Fail to Deenergize Because of an Organic C3 Insulating Material ML19346H8732019-12-12012 December 2019 Westinghouse Electric Company - Notification of the Potential Existence of Defect Pursuant to 10 CFR Part 21 ML19072A0632019-03-0606 March 2019 10 CFR Part 21 Report Notification of a Defect with Target Rock Modulating Valve Positioner; Model 810000-X ML18225A1182018-07-27027 July 2018 Ametek Solidstate Controls - Notification of Potential Defect-10CFR Part 21 ML17340A3922017-11-28028 November 2017 10CFR21 Reporting of Defects and Non-Compliance - Engine Systems, Inc. Report No. 10CFR21-0119, Rev. 0 ML17333A3792017-11-21021 November 2017 Engine Systems, Inc. 10 CFR 21 Reportable Notification on a Power Supply (P/N 2938604) ML17194A8252017-07-11011 July 2017 Part 21 Report Re Wedge Pin Failure in Anchor Darling Motor Operated Double Disc Gate Valves with Threaded Stem to Upper Wedge Connections ML17142A3222017-05-15015 May 2017 Part 21 - Potential Defect in Grayboot Socket Contacts ML17081A4532017-03-20020 March 2017 Part 21 - Plastic Jar Dedication Sampling ML17026A4142017-01-20020 January 2017 C&D Technologies, Inc. - Part 21 - Plastic Jar Dedication Sampling ML17032A0802016-12-30030 December 2016 Engine Systems, Inc., 10CFR21 Reporting of Defects and Non-Compliance, Report No. 10CFR21-0114, Rev. 0 ML17006A0102016-12-29029 December 2016 Engine Systems, Inc. - Part 21 Issues Identified with the Enterprise Diesel Engine Subcover ML16349A5902016-12-0202 December 2016 Interim 10 CFR Part 21 Report Regarding a Piping Spool Weld Nonconformance for AP1000 Project ML16321A4512016-10-21021 October 2016 Part 21 Reporting of Defects and Noncompliance ML16243A4722016-08-25025 August 2016 Part 21 Reporting of Defects and Noncompliance ML16188A3772016-06-21021 June 2016 Part 21 - Insufficient Valve Cage Hardfacing ML16174A3952016-06-21021 June 2016 Fisher Information Notice, (FIN) 2016-05 - Insufficient Valve Cage Hardfacing ML16139A8342016-05-10010 May 2016 Electroswitch - Transmittal of 10CFR Part 21 Reporting of Defects and Noncompliance Regarding Vendor Inspection of Electroswitch Corporation Docket No. 99900833 ML16127A5952016-05-0404 May 2016 Rotork Controls Inc. Part 21 Notification Concerning V12 (Pt No. N69-921) and K5 (N69-838 & N69-926) Safety Related Micro Switches ML15103A4852015-04-0707 April 2015 Itt Engineered Valves - 2nd Interim Report to the NRC of 10 CFR 21 Event 50285, Reported by Itt 07/18/14 Concerning M I Diaphragms, Customer Testing ML15103A2442015-04-0606 April 2015 Part 21 Report - Deviation of Hk Circuit Breaker Close Latch Spring ML15049A4582015-02-0606 February 2015 Thermo Gamma-Metrics, LLC - Part 21 Report Regarding Shutdown Margin Monitor Environmental Qualification Noncompliance ML15022A6502015-01-20020 January 2015 Letter from Steven R. Eisenberg USNRC 10CFR Part 21 Notification ML14335A2952014-11-13013 November 2014 Interim 10 CFR Part 21 Report Regarding Submodules CA20-03 and CA20-07A Nonconformances for V. C. Summer Unit 2, AP1000 Project ML14274A0522014-09-22022 September 2014 Final Report 10CFR Part 21 Evaluation Regarding Misaligned Separators in LCR-25 Standby Batteries, Revision 1 - Original Letter Did Not Include the List of Affected Utilities ML14261A1502014-09-17017 September 2014 Interim Report to the NRC of 10 CFR 21 Event 50285, Reported by Itt 07/18/14 Concerning M1 Diaphragms, Customer Testing ML14255A0172014-08-27027 August 2014 Interim 10 CFR Part 21 Report Regarding Submodule and Embedment Deviations for V. C. Summer Unit 2 AP1000 Project ML14113A3982014-04-17017 April 2014 Part 21 - Bearing Defect ML14099A5062014-03-27027 March 2014 Interim Report- 10CFR 21 Evaluation Regarding Potential Deficiencies in Testing of PV-62 ML14090A4312014-03-27027 March 2014 Interim Report - 10CFR 21 Evaluation Regarding Potential Deficiencies in Testing of PV-62 ML14090A4322014-03-27027 March 2014 Interim Report - 10CFR 21 Evaluation Regarding Potential Deficiencies in Seismic Qualifications for PV-62 ML14090A4332014-03-27027 March 2014 Interim Report- 10CFR 21 Evaluation Regarding Potential Deficiencies in Justification of Use of Prorate Spring in PV-62 ML14079A3532014-03-17017 March 2014 Notification of Part 21 Re Bearing Defect ML14034A1892014-01-23023 January 2014 Part 21 - Loose Battery Vent Assemblies ML13165A3422013-06-12012 June 2013 60-Day Interim Report Involving an Evaluation of a Design Change to Magne-Blast Circuit Breakers ML13064A0122013-02-25025 February 2013 Notification of Potential Part 21 Report Re Wedge Pin Failure of an Anchor/Darling Double-Disc Gate Valve ML12352A1232012-12-13013 December 2012 60-Day Interim Report Involving an Evaluation of a Design Change to Magne-Blast Circuit Breakers ML12348A1362012-12-13013 December 2012 Part 21 60-Day Interim Report Notification: Adequacy of Design Change in Am Magne-Blast Circuit Breakers ML12094A3712012-04-0202 April 2012 Part 21 Report - Rosemount Pressure Transmitters with Nonzero Based Calibrations ML12075A1062012-03-14014 March 2012 Notification of Potential Part 21 Re Defect on Arvan Electrical Terminal Blocks ML12097A3162012-03-0202 March 2012 Part 21 Report - Rosemont Pressure Tranmitters Out of Tolerance Condition ML12066A1182012-03-0202 March 2012 Part 21 Report - Rosemount Pressure Transmitters with Nonzero Based Calibrations ML12058A1412012-02-23023 February 2012 Part 21 Report - Rosemount Nuclear Instruments, Inc., Pressure Transmitter with Nonzero Based Calibrations ML11186A9042011-06-30030 June 2011 Notification of Potential Part 21 Appendix R Analyses Fails to Recognize Hot-Short Failure Resulting in the Loss of an Essential Electrical Bus 2024-01-18
[Table view] Category:Letter
MONTHYEARML24278A2832024-11-0707 November 2024 Letter to E. Carr Environmental Impact Statement Scoping Summary Report for Virgil C. Summer Nuclear Station Unit 1 ML24305A1302024-10-31031 October 2024 Submittal of 30 Day Report Per 10 CFR 26.719(c) Blind Performance Testing NL-24-0385, Request for Action Matrix Deviation Due to Recent Events Impacting the Unplanned Scram with Complications Performance Indicator2024-10-31031 October 2024 Request for Action Matrix Deviation Due to Recent Events Impacting the Unplanned Scram with Complications Performance Indicator IR 05000424/20240032024-10-30030 October 2024 – Integrated Inspection Report 05000424/2024003 and 05000425/2024003 NL-24-0386, License Amendment Request: Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves) Air Storage Tanks Response to Request for Additional Information2024-10-28028 October 2024 License Amendment Request: Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves) Air Storage Tanks Response to Request for Additional Information NL-24-0392, Response to Requests for Additional Information Related to Proposed Alternative GEN-ISI-AL T-2024-0022024-10-28028 October 2024 Response to Requests for Additional Information Related to Proposed Alternative GEN-ISI-AL T-2024-002 ML24308A0052024-10-28028 October 2024 10-28-24 NRC V.C. Summer Nuclear Station SLR Cherokee Nation Letter to USNRC ML24308A0062024-10-25025 October 2024 Subsequent License Renewal Application Area of Potential Effect (Ape) Clarification Fairfield County, South Carolina SHPO Project No. 22-EJ0147 NL-24-0366, Core Operating Limits Report, Cycle 26, Version 12024-10-25025 October 2024 Core Operating Limits Report, Cycle 26, Version 1 ML24302A1442024-10-24024 October 2024 Update to Subsequent License Renewal Application (SLRA) Supplement 4 and Requested Information Formation in Response to Limited Aging Management Audit ML24297A6482024-10-23023 October 2024 5 to the Updated Final Safety Analysis Report, Technical Specification Bases Changes, Technical Requirements Manual Changes, Summary Report and Revised NRC Commitments Report ML24255A3152024-10-22022 October 2024 Relief Request RR-5-V2 Regarding Pressure Isolation Valves ML24250A0782024-10-22022 October 2024 Relief Request RR-5-V1 Regarding Service Water Return Header Check Valves ML24256A2322024-10-22022 October 2024 Relief Request RR-5-P1 Charging/Safety Injection Pumps 05000395/LER-2024-002, Loss of Control Room Emergency Filtration System2024-10-15015 October 2024 Loss of Control Room Emergency Filtration System ML24290A1052024-10-0707 October 2024 Core Operating Limits Report VCSNS Unit 1 Cycle 29, Revision 0 ML24274A1942024-09-26026 September 2024 (Vcsns), Unit 1 Subsequent License Renewal Application (SLRA) First 10 CFR 54.21(b) Annual Amendment IR 05000395/20244042024-09-26026 September 2024 Cyber Security Inspection Report 05000395-2024404 - Public ML24269A2502024-09-26026 September 2024 Acknowledgement of the Withdrawal of the Requested Exemption and License Amendment Request to Remove Tier 1 and Tier 2* Requirements NL-24-0369, Withdrawal of License Amendment Request and Exemption Request: Remove Tier 1 and Tier 2 Requirements2024-09-25025 September 2024 Withdrawal of License Amendment Request and Exemption Request: Remove Tier 1 and Tier 2 Requirements NL-24-0350, Core Operating Limits Report, Cycle 24, Version 22024-09-25025 September 2024 Core Operating Limits Report, Cycle 24, Version 2 ML24267A0592024-09-23023 September 2024 Clarification Regarding Area of Potential Effect for the Subsequent Operating License Renewal for Virgil C. Summer Nuclear Station Fairfield County, South Carolina (SHPO Project Number: 22-EJ0147) (Docket Number: 50-395) ML24267A0542024-09-23023 September 2024 Clarification Regarding Area of Potential Effect for the Subsequent Operating License Renewal for Virgil C. Summer Nuclear Station Fairfield County, South Carolina (SHPO Project Number: 22-EJ0147) (Docket Number: 50-395) ML24267A0642024-09-23023 September 2024 Clarification Regarding Area of Potential Effect for the Subsequent Operating License Renewal for Virgil C. Summer Nuclear Station Fairfield County, South Carolina (SHPO Project Number: 22-EJ0147) (Docket Number: 50-395) ML24267A0552024-09-23023 September 2024 Clarification Regarding Area of Potential Effect for the Subsequent Operating License Renewal for Virgil C. Summer Nuclear Station Fairfield County, South Carolina (SHPO Project Number: 22-EJ0147) (Docket Number: 50-395) ML24221A2112024-09-23023 September 2024 Clarification Regarding Area of Potential Effect for the Subsequent Operating License Renewal for Virgil C. Summer Nuclear Station Fairfield County, South Carolina (SHPO Project Number: 22-EJ0147) (Docket Number: 50-395) IR 05000395/20244022024-09-10010 September 2024 Security Baseline Inspection Report 05000395/2024402 ML24243A0072024-09-10010 September 2024 – Correction of Amendment Nos. 223 and 206 Regarding Revision to Technical Specifications to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the COLR Consistent with WCAP-14483 NL-24-0337, Interim 10 CFR 21.21(a)(2) Report Regarding Operation Technology, Inc., ETAP Software Error in Transient Stability Program2024-09-0909 September 2024 Interim 10 CFR 21.21(a)(2) Report Regarding Operation Technology, Inc., ETAP Software Error in Transient Stability Program ML24102A2642024-09-0909 September 2024 – Exemption Request Regarding Final Safety Analysis Report Update Schedule (EPID L-2024-LLE-0013) - Letter ML24249A2942024-09-0606 September 2024 Correction of Amendment Nos. 218 and 201 Regarding Revision to Technical Specifications to Use Online Monitoring Methodology 05200025/LER-2024-002, Manual Reactor Protection System and Automatic Safeguards Actuation Due to an Unexpected Change in Position of a Main Feedwater Pump Minimum Flow Control Valve2024-09-0505 September 2024 Manual Reactor Protection System and Automatic Safeguards Actuation Due to an Unexpected Change in Position of a Main Feedwater Pump Minimum Flow Control Valve IR 05000424/20240052024-08-26026 August 2024 Updated Inspection Plan for Vogtle Electric Generating Plant, Units 1 and 2 - Report 05000424/2024005 and 05000425/2024005 ML24235A1952024-08-22022 August 2024 Updated Inspection Plan for Vogtle Electric Generating Plant, Units 3 and 4 - Report 05200025/2024005 and 05200026/2024005 IR 05000395/20240052024-08-22022 August 2024 Updated Inspection Plan for Virgil C. Summer Nuclear Station - Report 05000395/2024005 ML24190A4012024-08-19019 August 2024 Request for Withholding Information from Public Disclosure Regarding the Subsequent License Renewal Application - Dominion Energy Letter Dated May 30, 2024 IR 05000424/20244012024-08-15015 August 2024 4 - Security Baseline Inspection Report 05000424-2024401, 05000425-2024401, 05200025-2024402, and 05200026-2024403 - Cover Letter NL-24-0299, Exemption Request: Final Safety Analysis Report Update Schedule, Response to Request for Additional Information2024-08-14014 August 2024 Exemption Request: Final Safety Analysis Report Update Schedule, Response to Request for Additional Information IR 05000395/20240022024-08-12012 August 2024 Integrated Inspection Report 05000395/2024002 05000425/LER-2024-001, Manual Actuation of the Reactor Protection System Due to a Rod Control Fuse Opening Causing a Misaligned Shutdown Rod2024-08-0909 August 2024 Manual Actuation of the Reactor Protection System Due to a Rod Control Fuse Opening Causing a Misaligned Shutdown Rod ML24218A1842024-08-0707 August 2024 Examination Report and Cover Letter 05200026/LER-2024-001, Manual Reactor Protection System Actuation Due to Procedure Not Optimally Sequenced to Reset the Rapid Power Reduction Signal2024-08-0606 August 2024 Manual Reactor Protection System Actuation Due to Procedure Not Optimally Sequenced to Reset the Rapid Power Reduction Signal ML24180A0062024-08-0505 August 2024 Issuance of Amendment No. 227 to Modify Technical Specification 3.8.3.1 to Increase Completion Time for 120-Volt A.C. Vital Busses ML24218A3002024-08-0101 August 2024 Environmental Review Response to NRC Requests for Additional Information and Response to NRC Requests for Confirmation of Information Set 1 ML24212A1442024-08-0101 August 2024 Integrated Inspection Report 05200025/2024002 and 05200026/2024002 ML24158A3882024-07-31031 July 2024 Issuance of Amendment No. 226 to Change Emergency Plan Staff Augmentation Times and Relocate Emergency Operations Facility IR 05000424/20240022024-07-29029 July 2024 Integrated Inspection Report 05000424/2024002 and 05000425/2024002 IR 05000424/20244042024-07-26026 July 2024 Material Control and Accounting Program Inspection Report 05000424/2024404 and 05000425/2024404 (Cover Letter) NL-24-0282, License Amendment Request and Exemption Request: Remove Tier 1 and Tier 2* Requirements2024-07-25025 July 2024 License Amendment Request and Exemption Request: Remove Tier 1 and Tier 2* Requirements NL-24-0126, – Units 3 and 4, License Amendment Request: Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves) Action a and SR 3.7.6.62024-07-25025 July 2024 – Units 3 and 4, License Amendment Request: Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves) Action a and SR 3.7.6.6 2024-09-09
[Table view] |
Text
M arch 17, 2023
U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001
Subject:
10 CFR Part 21 Report - Inconsistent crimping of motor leads to ring terminal connectors and Failure to Comply. Trillium Valves USA Part 21 Evaluation I211003
Trillium Valves USA is providing this written notification in accordance with the requirements of 10 CFR 21.21(d)(3)(ii). This notification pertains to the inconsistent crimping of motor lead ring tongue terminal connectors attached to quick disconnect connectors for SMB actuators and failure to comply.
The failure to comply concerns failure to provide initial notification within 2 days and written notification within 30 days.
Sincerely,
Allen Fisher Director of Engineering Trillium Valves USA 29 Old Right Road Ipswich, MA 01938-1119 Phone +1 (978) 825-8451 Mobile+1 (252) 940-9508 Email allen.fisher@trilliumflow.com
Attachments:
- 1. Evaluation of ring tongue terminal connectors (8 pages)
- 2. List of affected orders (3 pages)
- 3. Reportable condition per 21.21(d)(4) (2 pages)
TRILLIUM Valves USA' O: +1 978 744 5690 29 Old Right Road Page 1 of 1 F: +1 978 741 3626 Ipswich, MA 01938-1119 USA E: valvesusa@trilliumflow.com
ATTACHMENT 1
Limitorque
LIMDOC-2022-004 July 1, 2022
Subject:
Inspection of terminal samples returned from Trillium Valve Photo # 1 provided by Trillium Valve shows five ring tongue terminal connectors removed from the actuator identified as serial #L983445. Two of these terminals were returned to Limitorque from Trillium Valve. The returned samples, designated as RS1 and RS2 are shown in photos # 2 & 3. The terminals were forwarded to the engineering special test lab for evaluation. For comparison purposes, Flowserve QA also provided the lab with three samples of terminal connectors that were installed and crimped by the Lynchburg production wiring department. These are shown in photo #4.
Comments from Lab Inspection:
Terminal RS1, identified as the terminal with the longest wire protruding, showed no continuity initially but when the end of the wire was manipulated continuity was intermittent. The wire appears to have been partially pulled out of the connector evident by the crimp impression in the wire insulation below the terminal and, also evident by the wire conductor not extending to the end of the barrel on the terminal side. Also, the wire did not appear to be firmly held when the wire was manipulated for the continuity test. The wire conductor was approximately 0.045 short of reaching the end of the terminal barrel.
Terminal RS2, identified as the terminal with the short wire protruding, initially checked good continuity however manipulation of the wire caused continuity to drop on at least one occasion. The wire appears to be still firmly held by the crimp however there is very little wire protruding from the terminal to make this evaluation. The wire conductor was approximately flush with the end of the terminal barrel.
The terminals provided by QA for comparison have an obviously different impression from the crimp tool than the samples returned from the customer. Also, the wire extends well beyond the end of the crimp barrel on these samples. Numbering on these terminals is different than those received from the Customer. (Regarding this comment, the terminals received from the customer are T & B part # RB863 which has a hole for a #8 screw typically used on the control and power Marathon terminal strip. The samples provided by QA are a T & B part # RB873 which has hole for a #10 screw typically used on the geared limit switch and torque switch terminals. Otherwise, the terminals are identical.)
Flowserve, Lynchburg VA Operations Page 1 of 8 Limitorque Engineering Department Limitorque
Discussion:
The crimping tool used by Limitorque (reference photo # 6) has jaws that crimps the connector in two places simultaneously. The primary crimp compresses the serrated barrel (reference Figure 1 and Photo #7) onto the wire conductor. The secondary crimp compresses the funnel entry barrel onto the outer wire insulation.
The three comparison samples shown in photo #5 are uniform in appearance. In contrast, the terminal connectors shown in photos #1, 2, 3, & 4 show inconsistencies in the location of the crimp and the extent of deformation of the barrel and insulator.
==
Conclusion:==
Limitorques inspection has determined that the root cause of the intermittent continuity at the wire conductor to terminal connection is likely attributable to a workmanship error resulting in inconsistent crimping of the lead wire to the terminal. On sample RS2, the conductor was not fully inserted into the terminal barrel prior to crimping. On samples RS1 & RS2, the crimping tool was not positioned properly on the terminal barrel prior to the crimp. The other terminals shown in photos 1 & 2 exhibit similar inconsistencies.
Prepared By: __ _________________________
Kyle Ramsey, Principal Engineer, Flowserve Limitorque
Reviewed By:
Nathan Sochor, Special Test Lab Supervisor, Flowserve, Lynchburg VA
Flowserve, Lynchburg VA Operations Page 2 of 8 Limitorque Engineering Department Limitorque
Photo # 1: Five Terminals Removed from Actuator
Photo # 2: Five Terminals Removed from Actuator
Flowserve, Lynchburg VA Operations Page 3 of 8 Limitorque Engineering Department Limitorque
Photo # 3: Samples Returned for Evaluation
RS1: Secondary crimp partially on the wire insulation rather than the terminal insulator
RS2: Primary crimp not positioned correctly over the barrel of the terminal housing the conductor
Flowserve, Lynchburg VA Operations Page 4 of 8 Limitorque Engineering Department Limitorque
Photo # 4: Samples Returned for Evaluation
RS2 RS1
Flowserve, Lynchburg VA Operations Page 5 of 8 Limitorque Engineering Department Limitorque
Photo # 5: Samples Provided for Comparison
Photo # 5 comment: There are two visible compression marks from the crimping tool. One crimp mark is directly over the barrel housing the conductor while the second crimp mark is over the barrel that clamps on the insulation of the wire.
Flowserve, Lynchburg VA Operations Page 6 of 8 Limitorque Engineering Department Limitorque
Photo # 6: Crimping Tool
Flowserve, Lynchburg VA Operations Page 7 of 8 Limitorque Engineering Department Limitorque
Figure 1: Details of Terminal
Photo # 7: Uncrimped Terminal with Blue Insulator Removed
Flowserve, Lynchburg VA Operations Page 8 of 8 Limitorque Engineering Department ATTACHMENT 2 List of affected orders
SCAR No IR-2022-7477 WEC PO 4500292480 Sanmen - 1
WEC Item Data Sheet Qty per unit Valve Serial Number Location Limitorque Serial Number
68 APP-PV11-Z0D-120 1 1-54536-J Aux L868152 69 APP-PV11-Z0D-121 1 1-54536-K Aux L868156 70 APP-PV11-Z0D-122 1 1-54536-L Aux L868159 70 APP-PV11-Z0D-122 1 2-54536-L Aux L868158 101 APP-PV11-Z0D-123 1 1-54536-W Cont L871810 102 APP-PV11-Z0D-124 1 1-54536-Z Cont L871811 77 APP-PV11-Z0D-145 1 1-54536-S Aux L879937 77 APP-PV11-Z0D-145 1 2-54536-S Aux L879938 124 APP-PV11-Z0D-245 1 3-54536-S Aux L879936 124 APP-PV11-Z0D-245 1 4-54536-S Aux L879935 76 APP-PV11-Z0D-140 1 1-54536-R Aux L879944 76 APP-PV11-Z0D-140 1 2-54536-R Aux L879943 105 APP-PV11-Z0D-119 1 1-54536-V Aux L890503 105 APP-PV11-Z0D-119 1 2-54536-V Aux L890504 118 APP-PV11-Z0D-141 1 1-00088-20 Aux L918547 118 APP-PV11-Z0D-141 1 2-00088-20 Aux L918546
WEC PO 4500292480 Haiyang - 1
WEC Item Data Sheet Qty per unit Valve Serial Number Location Limitorque Serial Number 87 APP-PV11-Z0D-120 1 1-54537-J Aux L868153 88 APP-PV11-Z0D-121 1 1-54537-K Aux L868154 89 APP-PV11-Z0D-122 1 1-54537-L Aux L868161 89 APP-PV11-Z0D-122 1 2-54537-L Aux L868162 103 APP-PV11-Z0D-123 1 1-54537-W Cont L871809 104 APP-PV11-Z0D-124 1 1-54537-Z Cont L871812 96 APP-PV11-Z0D-145 1 1-54537-S Aux L879940 96 APP-PV11-Z0D-145 1 2-54537-S Aux L879942 126 APP-PV11-Z0D-245 1 3-54537-S Aux L879939 126 APP-PV11-Z0D-245 1 4-54537-S Aux L879941 95 APP-PV11-Z0D-140 1 1-54537-R Aux L879946 95 APP-PV11-Z0D-140 1 2-54537-R Aux L879945 106 APP-PV11-Z0D-119 1 1-54537-V Aux L911178 106 APP-PV11-Z0D-119 1 2-54537-V Aux L911179 119 APP-PV11-Z0D-141 1 1-00088-21 Aux L918548 119 APP-PV11-Z0D-141 1 2-00088-21 Aux L918549
WEC PO 4500309727 Vogtle - 3
WEC Item Data Sheet Qty per unit Valve Serial Number Location Limitorque Serial Number
21 APP-PV11-Z0D-140 1 1-55022-R Aux L911115 21 APP-PV11-Z0D-140 1 2-55022-R Aux L911116 11 APP-PV11-Z0D-120 1 1-55022-J Aux L911614 12 APP-PV11-Z0D-121 1 1-55022-K Aux L911615 13 APP-PV11-Z0D-122 1 1-55022-L Aux L911617 13 APP-PV11-Z0D-122 1 2-55022-L Aux L911618 51 APP-PV11-Z0D-245 1 2-55022-Z Aux L911621 51 APP-PV11-Z0D-245 1 1-55022-Z Aux L911624 44 APP-PV11-Z0D-119 1 1-55022-X Aux L911629 44 APP-PV11-Z0D-119 1 2-55022-X Aux L911630
Page 1 of 3 List of affected orders SCAR No IR-2022-7477
22 APP-PV11-Z0D-145 1 1-55022-S Aux L912774 22 APP-PV11-Z0D-145 1 2-55022-S Aux L912776 46 APP-PV11-Z0D-123 1 1-55022-V Cont L912777 48 APP-PV11-Z0D-124 1 1-55022-W Cont L912782 58 APP-PV11-Z0D-141 1 1-00188-320 Aux L983444 58 APP-PV11-Z0D-141 1 2-00188-320 Aux L983445
WEC PO 4500309727 Vogtle - 4
WEC Item Data Sheet Qty per unit Valve Serial Number Location Limitorque Serial Number
62 APP-PV11-Z0D-141 1 2-00188-360 Aux L1003458 62 APP-PV11-Z0D-141 1 1-00188-360 Aux L1003459 42 APP-PV11-Z0D-140 1 3-55022R Aux L911111 42 APP-PV11-Z0D-140 1 4-55022R Aux L911112 43 APP-PV11-Z0D-145 1 3-55022S Aux L911622 53 APP-PV11-Z0D-245 1 4-55022Z Aux L911623 43 APP-PV11-Z0D-145 1 4-55022S Aux L911625 53 APP-PV11-Z0D-245 1 3-55022Z Aux L911627 33 APP-PV11-Z0D-121 1 2-55022K Aux L912764 32 APP-PV11-Z0D-120 1 2-55022J Aux L912766 34 APP-PV11-Z0D-122 1 3-55022L Aux L912768 47 APP-PV11-Z0D-123 1 2-55022V Cont L912778 49 APP-PV11-Z0D-124 1 2-55022W Cont L912781 45 APP-PV11-Z0D-119 1 3-55022X Aux L912787 45 APP-PV11-Z0D-119 1 4-55022X Aux L912788 34 APP-PV11-Z0D-122 1 4-55022L Aux L979720
WEC PO 4500309289 Summer - 2
WEC Item Data Sheet Qty per unit Valve Serial Number Location Limitorque Serial Number 21 APP-PV11-Z0D-140 1 1-55023R Aux L911113 21 APP-PV11-Z0D-140 1 2-55023R Aux L911114 11 APP-PV11-Z0D-120 1 1-55023J Aux L911613 12 APP-PV11-Z0D-121 1 1-55023K Aux L911616 13 APP-PV11-Z0D-122 1 2-55023L Aux L911619 22 APP-PV11-Z0D-145 1 2-55023S Aux L911626 44 APP-PV11-Z0D-119 1 1-55023X Aux L911631 44 APP-PV11-Z0D-119 1 2-55023X Aux L911632 13 APP-PV11-Z0D-122 1 1-55023L Aux L912767 51 APP-PV11-Z0D-245 1 2-55023Z Aux L912769 51 APP-PV11-Z0D-245 1 1-55023Z Aux L912770 22 APP-PV11-Z0D-145 1 1-55023S Aux L912772 46 APP-PV11-Z0D-123 1 1-55023V Cont L912780 48 APP-PV11-Z0D-124 1 1-55023W Cont L912784 58 APP-PV11-Z0D-141 1 1-00211-570 Aux L983442 58 APP-PV11-Z0D-141 1 2-00211-570 Aux L983443
WEC PO 4500309289 Summer - 3
WEC Item Data Sheet Qty per unit Valve Serial Number Location Limitorque Serial Number
62 APP-PV11-Z0D-141 1 1-00211-610 Aux L1003460 62 APP-PV11-Z0D-141 1 2-00211-610 Aux L1003461 42 APP-PV11-Z0D-140 1 3-55023R Aux L911117
Page 2 of 3 List of affected orders SCAR No IR-2022-7477
42 APP-PV11-Z0D-140 1 4-55023R Aux L911118 34 APP-PV11-Z0D-122 1 3-55023L Aux L911620 53 APP-PV11-Z0D-245 1 4-55023Z Aux L911628 32 APP-PV11-Z0D-120 1 2-55023J Aux L912763 33 APP-PV11-Z0D-121 1 2-55023K Aux L912765 43 APP-PV11-Z0D-145 1 4-55023S Aux L912771 53 APP-PV11-Z0D-245 1 3-55023Z Aux L912773 43 APP-PV11-Z0D-145 1 3-55023S Aux L912775 47 APP-PV11-Z0D-123 1 2-55023V Cont L912779 49 APP-PV11-Z0D-124 1 2-55023W Cont L912783 45 APP-PV11-Z0D-119 1 4-55023X Aux L912785 45 APP-PV11-Z0D-119 1 3-55023X Aux L912786 34 APP-PV11-Z0D-122 1 4-55023L Aux L979719
Page 3 of 3 M arch 17, 2023
Part 21 Evaluation I211003
ATTACHMENT 3: Reportable Condition per 21.21(d)(4)
- 1. Name and address of the individual or individuals informing the Commission.
Allen Fisher Director of Engineering Trillium Valves USA 29 Old Right Road Ipswich, MA 01938-1119
- 2. Identification of the facility, the activity, or the basic component supplied for such facility or such activity within the United States which fails to comply or contains a defect.
Butterfly Valves with SMB motor actuators supplied to Westinghouse Electric Company from 2010 to 2016.
- 3. Identification of the firm constructing the facility or supplying the basic component which fails to comply or contains a defect.
Trillium Valves USA 29 Old Right Road Ipswich, MA 01938-1119
- 4. Nature of the defect or failure to comply and the safety hazard which is created or could be created by such defect or failure to comply.
Inconsistent crimping of motor leads caused lack of continuity and intermittent function, or non-function of the actuator motor preventing the butterfly valve to close on demand.
See Attachment 1.
- 5. The date on which the information of such defect or failure to comply was obtained.
July 1, 2022, See Attachment 1.
- 6. In the case of a basic component which contains a defect or fails to comply, the number and location of these components in use at, supplied for, being supplied for, or may be supplied for, manufactured, or being manufactured for one or more facilities or activities subject to the regulations in this part.
The butterfly valves with motor actuators were supplied to Westinghouse Electric Company under orders identified in Attachment 2. Westinghouse was notified of the affected orders via their SCAR No IR-2022-7477 on March 6, 2023.
TRILLIUM Valves USA ' O: +1 978 744 5690 29 Old Right Road Page 1 of 2 F: +1 978 741 3626 Ipswich, MA 01938-1119 USA E: valvesusa@trilliumflow.com
M arch 17, 2023
Part 21 Evaluation I211003
- 7. The corrective action which has been, is being, or will be taken; the name of the individual or organization responsible for the action; and the length of time that has been or will be taken to complete the action.
(1) Trillium Valve USAs Approved Suppliers List has been updated to add restriction for any repairs or service of safety related equipment must be completed at the suppliers facility. No service or repair of safety related equipment at Trillium site.
This action was completed on March 2, 2023.
(2) The failure to comply with initial notification and written notification has been initiated under Trillium Valves USA Corrective Action Program. Corrective actions will include additional training on the implementation and reporting requirements under 10CFR21.
This action will be completed by March 31, 2023.
- 8. Any advice related to the defect or failure to comply about the facility, activity, or basic component that has been, is being, or will be given to purchasers or licensees.
Trillium Valves USA recommends the inspection of these actuators listed in Attachment 2 for the lack of continuity at the motor leads which may be impacted by inconsistent crimping of the lead wire to the ring tongue terminal.
- 9. In the case of an early site permit, the entities to whom an early site permit was transferred.
Not applicable.
TRILLIUM Valves USA ' O: +1 978 744 5690 29 Old Right Road Page 2 of 2 F: +1 978 741 3626 Ipswich, MA 01938-1119 USA E: valvesusa@trilliumflow.com